Ihab Saad – Tue, Apr 10, 11 30 AM

Ihab Saad
AI: Summary ©
The speaker explains how to add costs and resources to a schedule, create filters and calendars, and use the "actuated activity" tool to allocate resources to different activities. They also explain how to create a new graph and create a new calendar for a project. The speaker provides information on how to create a schedule and use the filters for certain activities, and how to add reserves and construction activities to a project. They also explain how to create a professional or look ahead schedule filter and how to add resources and costs to the project. The speaker provides information on how to use the filters and add them to the schedule, and reminds the audience to see the speaker in another lesson about working with a Phoenix project.
AI: Transcript ©
00:00:03 --> 00:00:07

Good afternoon today, we're going to start talking about Phoenix

00:00:07 --> 00:00:11

Project scheduler, and as you can see on the screen here, we have a

00:00:11 --> 00:00:14

basic schedule, and what we're going to learn about today is how

00:00:14 --> 00:00:17

to add costs and resources to the schedule. We're also going to

00:00:17 --> 00:00:22

learn about how to create filters, how to change calendars and how to

00:00:22 --> 00:00:28

show the BCWS or planned value curve once we add the costs to the

00:00:28 --> 00:00:32

schedule. So the first thing that we're going to do here is, let's

00:00:32 --> 00:00:35

just have a look at the screen. On the left side of the screen, we

00:00:35 --> 00:00:38

have information about the activities, including the activity

00:00:38 --> 00:00:42

ID, activity description, original duration, start and finish.

00:00:43 --> 00:00:46

Remember that when you are entering the information in the

00:00:46 --> 00:00:51

schedule, you do not add anything in the actual data, actual start

00:00:51 --> 00:00:54

and actual finish. This is not done once you initiate the

00:00:54 --> 00:00:57

schedule. It's done later on when you update the schedule on a

00:00:57 --> 00:01:01

regular basis. So what we're going to be doing right now, we're going

00:01:01 --> 00:01:05

to start learning about what's called the resource calendar. So,

00:01:05 --> 00:01:08

as we mentioned in class, resources can be added in

00:01:08 --> 00:01:13

different ways. One way is to do it in the very detailed way,

00:01:13 --> 00:01:16

entering individual resources, like, for example, carpenters or

00:01:16 --> 00:01:23

electricians or rebar or concrete or individual resources. That's

00:01:23 --> 00:01:26

one way of doing it. And each resource, in this case, is going

00:01:26 --> 00:01:30

to have its own unit. But again, the common unit among all of these

00:01:30 --> 00:01:33

resources, in the end, is going to be the cost of these resources, as

00:01:33 --> 00:01:38

we have agreed before resources can be explained or translated

00:01:38 --> 00:01:42

into their money value. So that's one way of adding the resources,

00:01:42 --> 00:01:46

which is the most detailed and accurate way. However, there's

00:01:46 --> 00:01:50

another shortcut, which is a simplified way. It's not

00:01:50 --> 00:01:54

inaccurate, but it saves a lot of time, which is basically going

00:01:54 --> 00:01:58

through the step of translating all the resources into their money

00:01:58 --> 00:02:02

value, which means we're going to represent only one resource, and

00:02:02 --> 00:02:05

in this case, we're going to call it cache. So let's go ahead and

00:02:05 --> 00:02:08

see how we're going to do that. If you go to the drop down menu

00:02:08 --> 00:02:13

called info and you click on Resource Library, this is the tab

00:02:13 --> 00:02:16

that we're looking for. So we're going to look at this resource

00:02:16 --> 00:02:19

library tab. We're going to click on it, and as you can see, it

00:02:19 --> 00:02:24

shows a blank screen, since we haven't added any resources yet.

00:02:25 --> 00:02:29

So what we're going to do next is going to add a new resource. Click

00:02:29 --> 00:02:32

on Add, and here we're going to enter the name of the resource,

00:02:32 --> 00:02:34

the name for of this resource. We're going to call it cache,

00:02:36 --> 00:02:40

and it's asking us whether it's labor, non labor, or material.

00:02:40 --> 00:02:43

It's neither labor nor material. So we're going to select non labor

00:02:45 --> 00:02:47

and the unit label. We're going to call it US Dollars

00:02:50 --> 00:02:53

maximum. What is the maximum amount that you can that's going

00:02:53 --> 00:02:57

to be available to you on a time unit basis? We selected the time

00:02:57 --> 00:03:01

unit to be the day. So basically, we're asking here, what's the

00:03:01 --> 00:03:04

maximum allowable amount for you to spend every day? Let's add

00:03:04 --> 00:03:06

300,000 for example.

00:03:09 --> 00:03:13

And that is asking us about the monetary value of that resource.

00:03:13 --> 00:03:16

The translation between this resource and money is one to one,

00:03:16 --> 00:03:21

because the units are dollars, and the cost is in dollars, so it's

00:03:21 --> 00:03:26

going to be build per day, and the rate is going to be one,

00:03:27 --> 00:03:30

and the cost per use is going to be one.

00:03:31 --> 00:03:34

So now that we have identified the resource that we're going to be

00:03:34 --> 00:03:38

using, we're just going to add it to our resource library, and here

00:03:38 --> 00:03:42

it appears that's the resource that we have. So now we're going

00:03:42 --> 00:03:44

to click, OK, accepting this resource.

00:03:46 --> 00:03:50

That's the very simple way of selecting resources for our

00:03:50 --> 00:03:55

project. The next step is going to be to apply these resources to the

00:03:55 --> 00:03:58

different activities. So I'm going to go to one activity here, for

00:03:58 --> 00:04:01

example. Let's say site mobilization.

00:04:02 --> 00:04:03

And

00:04:07 --> 00:04:11

what we're going to do here, as you can see, these are the

00:04:11 --> 00:04:17

different drop down menus. So now we are going to assign this

00:04:17 --> 00:04:21

resource to the activity. So here

00:04:22 --> 00:04:23

we are going to select

00:04:26 --> 00:04:28

double click on the activity to show the Activity Viewer at the

00:04:28 --> 00:04:30

bottom of the screen, we can

00:04:31 --> 00:04:35

the activity editor here. Remember here we do not enter anything

00:04:35 --> 00:04:39

under budget. We do not enter anything under cost today for the

00:04:39 --> 00:04:44

time being. So this is not where we're going to be adding our

00:04:44 --> 00:04:48

resources. So now we're going to select the

00:04:49 --> 00:04:53

resource assignment window. So we're going to click on this icon

00:04:53 --> 00:04:53

here,

00:04:54 --> 00:04:57

and this shows the resource assignment window for this

00:04:57 --> 00:04:59

activity. So now we're going to go to.

00:05:00 --> 00:05:03

The library to select which resource, assuming that you have

00:05:03 --> 00:05:06

multiple resources. In this case, we have only one resource. So if I

00:05:06 --> 00:05:09

click on Library, it's going to show me the available resource

00:05:09 --> 00:05:12

that we have. So I'm going to select this and click on Add.

00:05:15 --> 00:05:18

We're going to we're just going to select this

00:05:19 --> 00:05:25

and add it to our activity and

00:05:32 --> 00:05:32

see here.

00:05:34 --> 00:05:37

So we're going to add the resource, we're going to select

00:05:37 --> 00:05:44

cache, and how much are we going to spend for this activity? So the

00:05:44 --> 00:05:48

question now is, how are we going to allocate this resource to the

00:05:48 --> 00:05:51

activity? Is it going to be distributed along the duration of

00:05:51 --> 00:05:53

the activity? As we have a greeting class, we have three

00:05:53 --> 00:05:58

different types of allocations. If it's going to be self performed,

00:05:58 --> 00:06:00

if the activity is going to be self performed, we're going to

00:06:00 --> 00:06:03

spend each and every day of performing this activity. So we're

00:06:03 --> 00:06:07

going to have it as prorated. On the other hand, if the activity is

00:06:07 --> 00:06:10

going to be subcontracted, you are going to pay your subcontractor at

00:06:10 --> 00:06:15

the end of doing the activity. So it's going to be at the end. If

00:06:16 --> 00:06:19

it's a long lead item that you have to pay for in advance, then

00:06:19 --> 00:06:22

in this case, we're going to select Start. So what we're going

00:06:22 --> 00:06:25

to do here, we're going to allocate how much money are we

00:06:25 --> 00:06:28

going to stand on site mobilization, for example, let's

00:06:28 --> 00:06:29

say $25,000

00:06:33 --> 00:06:36

now this is going to be a self performed activity, so we're going

00:06:36 --> 00:06:39

to leave it as prorated. And now we're going to click OK.

00:06:40 --> 00:06:43

Notice what happened here. The duration of this activity was five

00:06:43 --> 00:06:48

days. The budgeted amount was 25,020 $5,000 we agreed that it's

00:06:48 --> 00:06:53

going to be prorated. So it's showing us the daily cost for this

00:06:53 --> 00:06:57

activity, which is going to be the 25,000 divided by the duration

00:06:57 --> 00:06:58

five days. So it's 5000

00:06:59 --> 00:07:03

now let's go to the next activity, site clearing. And here again,

00:07:03 --> 00:07:05

we're going to add the resource.

00:07:06 --> 00:07:10

We're going to select this cash. How much money are we going to

00:07:10 --> 00:07:12

allocate for that? Let's say it's going to be $12,000

00:07:15 --> 00:07:18

and let's say that we're going to hire a subcontractor to clear the

00:07:18 --> 00:07:22

site. So in this case, it's going to be paid in the end.

00:07:23 --> 00:07:28

And we're going to say, OK, so now it shows that the $12,000 are

00:07:28 --> 00:07:31

going to be applied to this activity. If it were to be

00:07:31 --> 00:07:36

prorated, it would have been $1,200 per day the next activity,

00:07:36 --> 00:07:40

excavation for foundations, again, let's say it's going to be

00:07:40 --> 00:07:46

subcontracted, so we're going to select our resource, and the

00:07:46 --> 00:07:48

excavation, let's say, is going to be $32,000

00:07:51 --> 00:07:55

and this is also going to be in the end, and OK, and this is

00:07:55 --> 00:07:59

basically the idea you can see how to add the resources to the

00:07:59 --> 00:08:02

different activities, assuming now that we have added the resources

00:08:02 --> 00:08:06

for all of these activities, we want to have a look at, how is the

00:08:06 --> 00:08:11

S curve going to look like? How is the planned cost curve going to

00:08:11 --> 00:08:14

look like? So basically, in this case, we're going to go to this

00:08:15 --> 00:08:20

tab, this icon, toggle time scale graphs,

00:08:21 --> 00:08:24

and we're going to create a new graph. Notice here it opened this

00:08:24 --> 00:08:26

window at the bottom of the screen. We're going to create a

00:08:26 --> 00:08:30

new graph. So the graph that we're going to do is for the resource

00:08:30 --> 00:08:34

that we have, which is cache. We're going to select cache. And

00:08:34 --> 00:08:37

in this case, it doesn't matter whether you're going to do costs

00:08:37 --> 00:08:40

or units, because the translation is one to one.

00:08:42 --> 00:08:46

We do not want current dates because, again, current date means

00:08:46 --> 00:08:49

that, after updating the project that includes the actual start,

00:08:49 --> 00:08:53

the actual finish, etc. But for the time being, we're going to use

00:08:53 --> 00:08:56

the original dates, and we're going to select the early dates.

00:08:56 --> 00:08:57

That's how we're going to

00:08:58 --> 00:09:03

portray this S curve for the original dates. Do you want to

00:09:03 --> 00:09:05

show it as a histogram or as a curve? Let's say for the

00:09:05 --> 00:09:07

beginning, we're going to show it as a curve,

00:09:08 --> 00:09:10

and now we're going to add it,

00:09:12 --> 00:09:14

and we're going to say, okay,

00:09:16 --> 00:09:20

and now we want to show it here at the bottom of the screen. So this

00:09:20 --> 00:09:22

is for the activities that we have added. Of course, if you have

00:09:22 --> 00:09:26

added it for all the activities, it would show you the S curve for

00:09:26 --> 00:09:30

the whole project. Let's say now I want to show this curve in a

00:09:30 --> 00:09:34

different way. I want to show it as a histogram, showing day by day

00:09:34 --> 00:09:38

how much money is going to be allocated or spent. I can create a

00:09:38 --> 00:09:41

new curve, and in this case, it's going to be pretty much the same

00:09:41 --> 00:09:42

thing. The

00:09:43 --> 00:09:46

only difference is going to be, I'm going to select Histogram

00:09:46 --> 00:09:49

instead of selecting curve, and I'm going to add and I'm going to

00:09:49 --> 00:09:50

select, OK,

00:09:52 --> 00:09:57

and now I can select this one. And here it shows the resource

00:09:57 --> 00:09:59

allocation pretty much per day.

00:10:00 --> 00:10:03

Or per time period, showing how much money is going to be spent.

00:10:03 --> 00:10:07

Again, if you do that for all the activities, it's going to show you

00:10:07 --> 00:10:11

the ups and downs of the resource profile, or the resource

00:10:11 --> 00:10:15

allocation curve. So this is the first part of our discussion about

00:10:15 --> 00:10:20

how to add costs and resources to the different activities. Now

00:10:20 --> 00:10:23

let's proceed to the next part, which is talking about calendars.

00:10:25 --> 00:10:29

Let's say you have an Arctic engineer who works only five days

00:10:29 --> 00:10:33

a week, whereas the site is going to work six days a week. The

00:10:33 --> 00:10:36

Arctic engineer has some activities related to the approval

00:10:36 --> 00:10:39

of submittals, the approval of shop drawings, some inspections

00:10:39 --> 00:10:43

and so on. So these are going to be done only on a five day basis,

00:10:43 --> 00:10:47

whereas the site is going to be working on a six workday basis.

00:10:47 --> 00:10:51

Can we allocate more than one calendar for the same project? The

00:10:51 --> 00:10:55

answer is yes. How many calendars can we apply for one project? As

00:10:55 --> 00:10:59

many as you want, or as many as the project needs? So let's go

00:10:59 --> 00:11:03

ahead and see. How are we going to create a calendar or modify an

00:11:03 --> 00:11:07

existing calendar? And how can we allocate different calendars to

00:11:07 --> 00:11:11

different activities? So if you go again to the tab called info,

00:11:11 --> 00:11:15

you're going to find that the second selection here is

00:11:15 --> 00:11:19

calendars. We are going to click on this calendars, and now it

00:11:19 --> 00:11:22

shows here some default calendars that have been built into the

00:11:22 --> 00:11:25

schedule. One of them is a five day calendar, and notice this

00:11:25 --> 00:11:29

check mark here that shows that this is the default calendar,

00:11:29 --> 00:11:32

which means if you do not change it, all the activities are going

00:11:32 --> 00:11:37

to be following that five workday calendar. The second one is a six

00:11:37 --> 00:11:41

day, and the third one is a seven day. We can add other calendars as

00:11:41 --> 00:11:45

we want, as needed for the project. Now notice on the right

00:11:45 --> 00:11:47

side of the screen, here we have

00:11:48 --> 00:11:56

it shows by default, our day today as highlighted. And if I click on

00:11:56 --> 00:12:00

the five day calendar, notice that all the days have the same color

00:12:01 --> 00:12:04

when it comes to work days, none of these boxes is checked. Notice

00:12:04 --> 00:12:07

what's going to happen when I click on the five day calendar.

00:12:09 --> 00:12:13

Now it shows that Monday, Tuesday, Wednesday, Thursday and Friday are

00:12:13 --> 00:12:16

checked, whereas Sunday and Saturday are not checked, which

00:12:16 --> 00:12:20

means these are the non work days and the other five are the work

00:12:20 --> 00:12:23

days. Now if I go to the six day calendar, what's going to happen

00:12:23 --> 00:12:27

is that Saturday is going to be considered as a work day. So

00:12:27 --> 00:12:31

notice here that Saturday also is checked, and the only day that

00:12:31 --> 00:12:35

appears in red, which is the non work day, this is Sunday for the

00:12:35 --> 00:12:37

seventh day. Of course, all the days are going to be checked,

00:12:37 --> 00:12:41

which means the site is working seven days a week. So let's go

00:12:41 --> 00:12:44

back to the five day calendar, assuming that, for example, our

00:12:44 --> 00:12:45

project is going to

00:12:47 --> 00:12:50

last for a year. Are we going to work on the Fourth of July?

00:12:50 --> 00:12:54

Probably not. Are we going to work on december 25 Christmas Day?

00:12:55 --> 00:13:00

Probably not. So let us designate these as non work days so that if

00:13:02 --> 00:13:05

work comes through these days, it's going to jump over that day

00:13:05 --> 00:13:10

and count the following work day as a continuation of the previous

00:13:10 --> 00:13:13

work. So let's go to July,

00:13:14 --> 00:13:18

and July 4 this year is going to be on a Wednesday. So I'm going to

00:13:18 --> 00:13:24

click on July 4 and I'm going to select it as set as non work

00:13:24 --> 00:13:28

notice what's going to happen when I do that. It has changed its

00:13:28 --> 00:13:33

color to red, which means now it's a non work day. I can do the same

00:13:33 --> 00:13:38

thing for December, and I can select december 25 currently it's

00:13:38 --> 00:13:40

a work day. So we're going to change that, and we're going to

00:13:40 --> 00:13:44

call it a non work day. And there it is.

00:13:45 --> 00:13:50

Now, let's say I want to assign a six

00:13:52 --> 00:13:56

workday calendar to backfilling and compaction, for example. So

00:13:56 --> 00:13:59

here I'm going to accept these calendars, okay?

00:14:00 --> 00:14:02

And now I'm going to go to the activity backfilling and

00:14:02 --> 00:14:06

compaction, highlight it and look at the activity editor here. At

00:14:06 --> 00:14:10

the bottom, it shows calendar, a tab called calendar. If you click

00:14:10 --> 00:14:13

on this down arrow, it's going to show you what are the available

00:14:13 --> 00:14:16

calendars based on what we have created or what we have edited. So

00:14:16 --> 00:14:19

if I click on this arrow, it's going to show me the five day

00:14:19 --> 00:14:22

calendar, the six day calendar of the seven day calendar. Let's say

00:14:22 --> 00:14:26

we're going to select the six day calendar for this activity. So

00:14:26 --> 00:14:29

here it is six day and enter

00:14:30 --> 00:14:35

now we have assigned this activity to a six workday week. We can do

00:14:35 --> 00:14:39

the same for the other activities as well. So you might, as we

00:14:39 --> 00:14:42

mentioned, we you can have multiple calendars for the same

00:14:42 --> 00:14:45

project, depending on the needs and depending on the different

00:14:45 --> 00:14:47

parties work schedule.

00:14:48 --> 00:14:51

So that's the second part that covers the area of calendars. Of

00:14:51 --> 00:14:56

course, you can change a work day into a non work day and vice versa

00:14:56 --> 00:14:59

by checking the box that has this day or just sell.

00:15:00 --> 00:15:04

One particular day and marking it as a non work day, or as a work

00:15:04 --> 00:15:05

day.

00:15:07 --> 00:15:10

The third step that we want to achieve today is

00:15:11 --> 00:15:16

looking at creating sub schedules from my master schedule. If I have

00:15:16 --> 00:15:21

a project that has 3000 activities, 5000 activities, and I

00:15:21 --> 00:15:23

have multiple subcontractors, let's say I have 30

00:15:23 --> 00:15:27

subcontractors. Some of them have activities that are maybe 150

00:15:28 --> 00:15:31

activities, but some of them have maybe three or four activities. It

00:15:31 --> 00:15:34

doesn't make much sense to give all of them copies of the same

00:15:34 --> 00:15:37

master schedule that has 5000 activities. They're going to be

00:15:37 --> 00:15:41

totally lost. So the solution in this case, is for me to create a

00:15:41 --> 00:15:46

sub schedule from the master schedule. Does that mean that for

00:15:46 --> 00:15:48

each one of these different subcontractors, I'm going to

00:15:48 --> 00:15:52

create a new schedule? Again? That would be a waste of time, but if

00:15:52 --> 00:15:55

you develop your schedule correctly, the first time, we are

00:15:55 --> 00:15:59

going to add tags to certain activities, or we are going to

00:15:59 --> 00:16:03

create filters through which we're going to pull all the activities

00:16:03 --> 00:16:08

and then set criteria for the opening of that filter, which

00:16:08 --> 00:16:11

activities can pass through and which activities are going to be

00:16:11 --> 00:16:15

withheld. So this concept is called filters, and that's one of

00:16:15 --> 00:16:18

the strong features of any scheduling software. Some

00:16:18 --> 00:16:21

softwares do have it. Some softwares do not have it, so that

00:16:22 --> 00:16:25

would be an indication of whether that software is really

00:16:25 --> 00:16:29

professional and practical or not. So let's go ahead. How to create a

00:16:29 --> 00:16:33

filter. Again, look at these icons. You're going to find one

00:16:33 --> 00:16:36

that looks like a funnel, and that's basically what a filter is.

00:16:36 --> 00:16:40

So now we're going to create a filter. Let's say, for example, as

00:16:40 --> 00:16:43

you can see here on the screen, that's first of all, let's make

00:16:43 --> 00:16:46

these parts disappear. We don't need them,

00:16:47 --> 00:16:50

and we don't need the activity editor either. If you look at the

00:16:50 --> 00:16:52

schedule, you're gonna have that, you're gonna find that we have

00:16:52 --> 00:16:56

some critical activities, the ones that are shown in red, and some

00:16:56 --> 00:16:59

non critical activities, which are the ones that that are shown in

00:16:59 --> 00:16:59

green.

00:17:00 --> 00:17:03

And let's say now I want to focus primarily on the critical

00:17:03 --> 00:17:06

activities. That's going to be my main concern, because these are

00:17:06 --> 00:17:10

the ones that really affect the total duration of the project. So

00:17:10 --> 00:17:13

how are we going to do that? I want to tell the software. Look at

00:17:13 --> 00:17:14

all the activities.

00:17:15 --> 00:17:19

If the activity is critical, select it. If it is not critical,

00:17:19 --> 00:17:25

set it aside, what is the main criterion for a critical activity?

00:17:26 --> 00:17:30

A critical activity has a total float equal to zero before

00:17:30 --> 00:17:33

updating the project, or anything like that, before having negative

00:17:33 --> 00:17:37

total float, which may happen if the project is behind schedule. So

00:17:37 --> 00:17:41

for the time being, a critical activity is one that has zero

00:17:41 --> 00:17:45

total float. So we're going to tell the filter. We're going to

00:17:45 --> 00:17:49

create a filter, telling it, please select the activity if its

00:17:49 --> 00:17:53

total float is equal to zero, if it's more than zero, do not select

00:17:53 --> 00:17:56

it, which means, if it's non critical, we're not currently

00:17:56 --> 00:18:00

interested in it. So I'm going to click on Filters, and here it's

00:18:00 --> 00:18:04

going to show that it already has some filters built in. Let's say

00:18:04 --> 00:18:08

I'm going to create a new filter to start from scratch, and I'm

00:18:08 --> 00:18:10

going to call it critical activities only.

00:18:16 --> 00:18:17

So

00:18:18 --> 00:18:24

we're going to add new criteria. So what the criteria? Which field

00:18:24 --> 00:18:27

am I going to be looking at? I'm going to be looking at the total

00:18:27 --> 00:18:31

float. So on this, in this drop down menu, I'm going to scroll

00:18:31 --> 00:18:34

down until I find the total float. Here it is.

00:18:35 --> 00:18:41

Now, do I want to select critical or non critical activities? If I

00:18:41 --> 00:18:46

look at the equality here, it says either is equal to or is greater

00:18:46 --> 00:18:51

than, greater than or equal to less than less than or equal to

00:18:51 --> 00:18:55

and so on and so forth. So the one that I'm looking for is is equal

00:18:55 --> 00:18:59

to zero. That's basically the value that I'm looking for for the

00:18:59 --> 00:19:03

critical activities. So I'm going to select is equal to and we

00:19:03 --> 00:19:05

accept zero, and I'm going to say, OK.

00:19:07 --> 00:19:12

And now I'm going to select this filter critical activities only.

00:19:12 --> 00:19:15

I'm going to add to the active filters, which is at the bottom of

00:19:15 --> 00:19:17

the screen, and I'm going to say, apply.

00:19:18 --> 00:19:24

And OK. And there it is. Now we have only the critical activities.

00:19:25 --> 00:19:29

Let's say I'm done with that, and I want to go back to the whole

00:19:29 --> 00:19:32

schedule, including critical and non critical. So I'm going to go

00:19:32 --> 00:19:38

to the filters again, and I'm going to clear the filter. I don't

00:19:38 --> 00:19:41

want to delete it, I just want to clear it from this box. So it's

00:19:41 --> 00:19:46

going to go back to the top box, so Clear Filters apply. And OK,

00:19:47 --> 00:19:49

and here I have all the activities at that.

00:19:50 --> 00:19:53

Now let's create another very common and popular and

00:19:53 --> 00:19:56

professional filter, which is, I want to focus only on the

00:19:56 --> 00:19:59

activities that are going to be done next month or next.

00:20:00 --> 00:20:03

Six weeks or next eight weeks, which is called a look ahead

00:20:03 --> 00:20:07

schedule. It could be the most common one is a six week look

00:20:07 --> 00:20:10

ahead schedule, or eight week look ahead schedule. So how are we

00:20:10 --> 00:20:13

going to designate that it's going to be based on dates? So

00:20:14 --> 00:20:17

basically, I'm going to tell the software that I want to create a

00:20:17 --> 00:20:21

filter that shows the activities that have a start date or an early

00:20:21 --> 00:20:25

date start or finish. So if this activity is going to start or

00:20:25 --> 00:20:31

finish between today and the next six weeks, select this activity.

00:20:31 --> 00:20:36

If not, do not select it. So I'm going to go here again to filters,

00:20:36 --> 00:20:39

and I'm going to create a new filter, and I'm going to call it

00:20:39 --> 00:20:40

six week.

00:20:41 --> 00:20:42

Look ahead.

00:20:47 --> 00:20:49

Now we're going to add the criteria.

00:20:50 --> 00:20:53

So what am I going am I going to be looking for? I'm looking for,

00:20:54 --> 00:20:58

is it looking at actual start or actual finish or actual dates? No,

00:20:59 --> 00:21:02

is it looking at early start to early finish, not only that, but

00:21:02 --> 00:21:05

both of them. So I'm going to select early dates, select if

00:21:05 --> 00:21:10

early dates is equal to something or is within a certain range. Now

00:21:10 --> 00:21:15

I want it to be between today and six weeks later, so I'm going to

00:21:15 --> 00:21:19

go again to my equality, and I'm going to select within range.

00:21:21 --> 00:21:25

Notice that as soon as I said dates, it recognized that the

00:21:25 --> 00:21:29

values are going to be dates, so it showed me a calendar. So I'm

00:21:29 --> 00:21:34

going to select between, let's say the project here starts on in

00:21:34 --> 00:21:39

February of 2017 so I'm going to go to the calendar of 2017

00:21:40 --> 00:21:46

and and let's say beginning February 1, 2017

00:21:49 --> 00:21:55

and ending on six weeks later. So let's say mid March, 2017

00:22:02 --> 00:22:05

so that's a six week look ahead. I'm going to say, Okay.

00:22:06 --> 00:22:13

And now I'm going to add my filter to the active filters. I'm going

00:22:13 --> 00:22:14

to say, apply.

00:22:15 --> 00:22:19

And okay. And now it shows me the activities that are going to take

00:22:19 --> 00:22:25

place, if their early dates are between February 1 and March 15.

00:22:25 --> 00:22:29

Notice that it shows an activity that ends after March 15 because

00:22:29 --> 00:22:34

its start was within that range. So if the start or the end of the

00:22:34 --> 00:22:36

activity fall within that range, is going to be selected.

00:22:37 --> 00:22:42

Now I have seen this. So what I'm going to do go back to now is I'm

00:22:42 --> 00:22:44

going to go back to remove this filter,

00:22:45 --> 00:22:51

Clear Filters and apply ok, and we're back to the whole scale.

00:22:52 --> 00:22:56

So in our discussion today, we have learned a few things. One is

00:22:56 --> 00:23:01

learning about resources and cost, how to add resources and cost of

00:23:01 --> 00:23:04

the project, and how to apply these costs to the different

00:23:04 --> 00:23:09

activities, and how to draw the graph, the smooth curve, the S

00:23:09 --> 00:23:13

curve, BCWS, or planned value, and how also to show the resource

00:23:13 --> 00:23:18

loading histogram for individual units of time. And then we learned

00:23:18 --> 00:23:22

about the calendars, how to create new calendars, or how to edit

00:23:22 --> 00:23:27

existing calendars by adding work days or non work days, and how to

00:23:27 --> 00:23:30

assign or allocate these calendars to the different activities. And

00:23:30 --> 00:23:33

we agreed that the project can have multiple calendars. And then

00:23:33 --> 00:23:38

finally, we learned about the filters. How can we from one

00:23:38 --> 00:23:42

master schedule? How can we select sub schedules depending on what

00:23:42 --> 00:23:45

are we looking for, whether it's on the critical activities or

00:23:45 --> 00:23:49

activities that are done within a period of time. Later on, we are

00:23:49 --> 00:23:53

going to learn about another kind of tags, which is called activity

00:23:53 --> 00:23:56

codes, that also enables us which are

00:23:58 --> 00:24:01

fields that we create on our own. We can customize the schedule

00:24:01 --> 00:24:04

whichever way we want, and these are going to be tools or tags that

00:24:04 --> 00:24:08

are going to enable us to select and sort different activities and

00:24:08 --> 00:24:13

different filters based on these codes. That is the end of our

00:24:13 --> 00:24:16

discussion for today. So until next time, I'm going to see you in

00:24:16 --> 00:24:22

another lesson about working with Phoenix project schedule, thank

00:24:22 --> 00:24:22

you. Thank.

Share Page