Ihab Saad – Tue, Apr 10, 11 30 AM

Ihab Saad
Share Page

AI: Summary ©

The speaker explains how to add costs and resources to a schedule, create filters and calendars, and use the "actuated activity" tool to allocate resources to different activities. They also explain how to create a new graph and create a new calendar for a project. The speaker provides information on how to create a schedule and use the filters for certain activities, and how to add reserves and construction activities to a project. They also explain how to create a professional or look ahead schedule filter and how to add resources and costs to the project. The speaker provides information on how to use the filters and add them to the schedule, and reminds the audience to see the speaker in another lesson about working with a Phoenix project.

AI: Summary ©

00:00:03 --> 00:00:07
			Good afternoon today, we're going
to start talking about Phoenix
		
00:00:07 --> 00:00:11
			Project scheduler, and as you can
see on the screen here, we have a
		
00:00:11 --> 00:00:14
			basic schedule, and what we're
going to learn about today is how
		
00:00:14 --> 00:00:17
			to add costs and resources to the
schedule. We're also going to
		
00:00:17 --> 00:00:22
			learn about how to create filters,
how to change calendars and how to
		
00:00:22 --> 00:00:28
			show the BCWS or planned value
curve once we add the costs to the
		
00:00:28 --> 00:00:32
			schedule. So the first thing that
we're going to do here is, let's
		
00:00:32 --> 00:00:35
			just have a look at the screen. On
the left side of the screen, we
		
00:00:35 --> 00:00:38
			have information about the
activities, including the activity
		
00:00:38 --> 00:00:42
			ID, activity description, original
duration, start and finish.
		
00:00:43 --> 00:00:46
			Remember that when you are
entering the information in the
		
00:00:46 --> 00:00:51
			schedule, you do not add anything
in the actual data, actual start
		
00:00:51 --> 00:00:54
			and actual finish. This is not
done once you initiate the
		
00:00:54 --> 00:00:57
			schedule. It's done later on when
you update the schedule on a
		
00:00:57 --> 00:01:01
			regular basis. So what we're going
to be doing right now, we're going
		
00:01:01 --> 00:01:05
			to start learning about what's
called the resource calendar. So,
		
00:01:05 --> 00:01:08
			as we mentioned in class,
resources can be added in
		
00:01:08 --> 00:01:13
			different ways. One way is to do
it in the very detailed way,
		
00:01:13 --> 00:01:16
			entering individual resources,
like, for example, carpenters or
		
00:01:16 --> 00:01:23
			electricians or rebar or concrete
or individual resources. That's
		
00:01:23 --> 00:01:26
			one way of doing it. And each
resource, in this case, is going
		
00:01:26 --> 00:01:30
			to have its own unit. But again,
the common unit among all of these
		
00:01:30 --> 00:01:33
			resources, in the end, is going to
be the cost of these resources, as
		
00:01:33 --> 00:01:38
			we have agreed before resources
can be explained or translated
		
00:01:38 --> 00:01:42
			into their money value. So that's
one way of adding the resources,
		
00:01:42 --> 00:01:46
			which is the most detailed and
accurate way. However, there's
		
00:01:46 --> 00:01:50
			another shortcut, which is a
simplified way. It's not
		
00:01:50 --> 00:01:54
			inaccurate, but it saves a lot of
time, which is basically going
		
00:01:54 --> 00:01:58
			through the step of translating
all the resources into their money
		
00:01:58 --> 00:02:02
			value, which means we're going to
represent only one resource, and
		
00:02:02 --> 00:02:05
			in this case, we're going to call
it cache. So let's go ahead and
		
00:02:05 --> 00:02:08
			see how we're going to do that. If
you go to the drop down menu
		
00:02:08 --> 00:02:13
			called info and you click on
Resource Library, this is the tab
		
00:02:13 --> 00:02:16
			that we're looking for. So we're
going to look at this resource
		
00:02:16 --> 00:02:19
			library tab. We're going to click
on it, and as you can see, it
		
00:02:19 --> 00:02:24
			shows a blank screen, since we
haven't added any resources yet.
		
00:02:25 --> 00:02:29
			So what we're going to do next is
going to add a new resource. Click
		
00:02:29 --> 00:02:32
			on Add, and here we're going to
enter the name of the resource,
		
00:02:32 --> 00:02:34
			the name for of this resource.
We're going to call it cache,
		
00:02:36 --> 00:02:40
			and it's asking us whether it's
labor, non labor, or material.
		
00:02:40 --> 00:02:43
			It's neither labor nor material.
So we're going to select non labor
		
00:02:45 --> 00:02:47
			and the unit label. We're going to
call it US Dollars
		
00:02:50 --> 00:02:53
			maximum. What is the maximum
amount that you can that's going
		
00:02:53 --> 00:02:57
			to be available to you on a time
unit basis? We selected the time
		
00:02:57 --> 00:03:01
			unit to be the day. So basically,
we're asking here, what's the
		
00:03:01 --> 00:03:04
			maximum allowable amount for you
to spend every day? Let's add
		
00:03:04 --> 00:03:06
			300,000 for example.
		
00:03:09 --> 00:03:13
			And that is asking us about the
monetary value of that resource.
		
00:03:13 --> 00:03:16
			The translation between this
resource and money is one to one,
		
00:03:16 --> 00:03:21
			because the units are dollars, and
the cost is in dollars, so it's
		
00:03:21 --> 00:03:26
			going to be build per day, and the
rate is going to be one,
		
00:03:27 --> 00:03:30
			and the cost per use is going to
be one.
		
00:03:31 --> 00:03:34
			So now that we have identified the
resource that we're going to be
		
00:03:34 --> 00:03:38
			using, we're just going to add it
to our resource library, and here
		
00:03:38 --> 00:03:42
			it appears that's the resource
that we have. So now we're going
		
00:03:42 --> 00:03:44
			to click, OK, accepting this
resource.
		
00:03:46 --> 00:03:50
			That's the very simple way of
selecting resources for our
		
00:03:50 --> 00:03:55
			project. The next step is going to
be to apply these resources to the
		
00:03:55 --> 00:03:58
			different activities. So I'm going
to go to one activity here, for
		
00:03:58 --> 00:04:01
			example. Let's say site
mobilization.
		
00:04:02 --> 00:04:03
			And
		
00:04:07 --> 00:04:11
			what we're going to do here, as
you can see, these are the
		
00:04:11 --> 00:04:17
			different drop down menus. So now
we are going to assign this
		
00:04:17 --> 00:04:21
			resource to the activity. So here
		
00:04:22 --> 00:04:23
			we are going to select
		
00:04:26 --> 00:04:28
			double click on the activity to
show the Activity Viewer at the
		
00:04:28 --> 00:04:30
			bottom of the screen, we can
		
00:04:31 --> 00:04:35
			the activity editor here. Remember
here we do not enter anything
		
00:04:35 --> 00:04:39
			under budget. We do not enter
anything under cost today for the
		
00:04:39 --> 00:04:44
			time being. So this is not where
we're going to be adding our
		
00:04:44 --> 00:04:48
			resources. So now we're going to
select the
		
00:04:49 --> 00:04:53
			resource assignment window. So
we're going to click on this icon
		
00:04:53 --> 00:04:53
			here,
		
00:04:54 --> 00:04:57
			and this shows the resource
assignment window for this
		
00:04:57 --> 00:04:59
			activity. So now we're going to go
to.
		
00:05:00 --> 00:05:03
			The library to select which
resource, assuming that you have
		
00:05:03 --> 00:05:06
			multiple resources. In this case,
we have only one resource. So if I
		
00:05:06 --> 00:05:09
			click on Library, it's going to
show me the available resource
		
00:05:09 --> 00:05:12
			that we have. So I'm going to
select this and click on Add.
		
00:05:15 --> 00:05:18
			We're going to we're just going to
select this
		
00:05:19 --> 00:05:25
			and add it to our activity and
		
00:05:32 --> 00:05:32
			see here.
		
00:05:34 --> 00:05:37
			So we're going to add the
resource, we're going to select
		
00:05:37 --> 00:05:44
			cache, and how much are we going
to spend for this activity? So the
		
00:05:44 --> 00:05:48
			question now is, how are we going
to allocate this resource to the
		
00:05:48 --> 00:05:51
			activity? Is it going to be
distributed along the duration of
		
00:05:51 --> 00:05:53
			the activity? As we have a
greeting class, we have three
		
00:05:53 --> 00:05:58
			different types of allocations. If
it's going to be self performed,
		
00:05:58 --> 00:06:00
			if the activity is going to be
self performed, we're going to
		
00:06:00 --> 00:06:03
			spend each and every day of
performing this activity. So we're
		
00:06:03 --> 00:06:07
			going to have it as prorated. On
the other hand, if the activity is
		
00:06:07 --> 00:06:10
			going to be subcontracted, you are
going to pay your subcontractor at
		
00:06:10 --> 00:06:15
			the end of doing the activity. So
it's going to be at the end. If
		
00:06:16 --> 00:06:19
			it's a long lead item that you
have to pay for in advance, then
		
00:06:19 --> 00:06:22
			in this case, we're going to
select Start. So what we're going
		
00:06:22 --> 00:06:25
			to do here, we're going to
allocate how much money are we
		
00:06:25 --> 00:06:28
			going to stand on site
mobilization, for example, let's
		
00:06:28 --> 00:06:29
			say $25,000
		
00:06:33 --> 00:06:36
			now this is going to be a self
performed activity, so we're going
		
00:06:36 --> 00:06:39
			to leave it as prorated. And now
we're going to click OK.
		
00:06:40 --> 00:06:43
			Notice what happened here. The
duration of this activity was five
		
00:06:43 --> 00:06:48
			days. The budgeted amount was
25,020 $5,000 we agreed that it's
		
00:06:48 --> 00:06:53
			going to be prorated. So it's
showing us the daily cost for this
		
00:06:53 --> 00:06:57
			activity, which is going to be the
25,000 divided by the duration
		
00:06:57 --> 00:06:58
			five days. So it's 5000
		
00:06:59 --> 00:07:03
			now let's go to the next activity,
site clearing. And here again,
		
00:07:03 --> 00:07:05
			we're going to add the resource.
		
00:07:06 --> 00:07:10
			We're going to select this cash.
How much money are we going to
		
00:07:10 --> 00:07:12
			allocate for that? Let's say it's
going to be $12,000
		
00:07:15 --> 00:07:18
			and let's say that we're going to
hire a subcontractor to clear the
		
00:07:18 --> 00:07:22
			site. So in this case, it's going
to be paid in the end.
		
00:07:23 --> 00:07:28
			And we're going to say, OK, so now
it shows that the $12,000 are
		
00:07:28 --> 00:07:31
			going to be applied to this
activity. If it were to be
		
00:07:31 --> 00:07:36
			prorated, it would have been
$1,200 per day the next activity,
		
00:07:36 --> 00:07:40
			excavation for foundations, again,
let's say it's going to be
		
00:07:40 --> 00:07:46
			subcontracted, so we're going to
select our resource, and the
		
00:07:46 --> 00:07:48
			excavation, let's say, is going to
be $32,000
		
00:07:51 --> 00:07:55
			and this is also going to be in
the end, and OK, and this is
		
00:07:55 --> 00:07:59
			basically the idea you can see how
to add the resources to the
		
00:07:59 --> 00:08:02
			different activities, assuming now
that we have added the resources
		
00:08:02 --> 00:08:06
			for all of these activities, we
want to have a look at, how is the
		
00:08:06 --> 00:08:11
			S curve going to look like? How is
the planned cost curve going to
		
00:08:11 --> 00:08:14
			look like? So basically, in this
case, we're going to go to this
		
00:08:15 --> 00:08:20
			tab, this icon, toggle time scale
graphs,
		
00:08:21 --> 00:08:24
			and we're going to create a new
graph. Notice here it opened this
		
00:08:24 --> 00:08:26
			window at the bottom of the
screen. We're going to create a
		
00:08:26 --> 00:08:30
			new graph. So the graph that we're
going to do is for the resource
		
00:08:30 --> 00:08:34
			that we have, which is cache.
We're going to select cache. And
		
00:08:34 --> 00:08:37
			in this case, it doesn't matter
whether you're going to do costs
		
00:08:37 --> 00:08:40
			or units, because the translation
is one to one.
		
00:08:42 --> 00:08:46
			We do not want current dates
because, again, current date means
		
00:08:46 --> 00:08:49
			that, after updating the project
that includes the actual start,
		
00:08:49 --> 00:08:53
			the actual finish, etc. But for
the time being, we're going to use
		
00:08:53 --> 00:08:56
			the original dates, and we're
going to select the early dates.
		
00:08:56 --> 00:08:57
			That's how we're going to
		
00:08:58 --> 00:09:03
			portray this S curve for the
original dates. Do you want to
		
00:09:03 --> 00:09:05
			show it as a histogram or as a
curve? Let's say for the
		
00:09:05 --> 00:09:07
			beginning, we're going to show it
as a curve,
		
00:09:08 --> 00:09:10
			and now we're going to add it,
		
00:09:12 --> 00:09:14
			and we're going to say, okay,
		
00:09:16 --> 00:09:20
			and now we want to show it here at
the bottom of the screen. So this
		
00:09:20 --> 00:09:22
			is for the activities that we have
added. Of course, if you have
		
00:09:22 --> 00:09:26
			added it for all the activities,
it would show you the S curve for
		
00:09:26 --> 00:09:30
			the whole project. Let's say now I
want to show this curve in a
		
00:09:30 --> 00:09:34
			different way. I want to show it
as a histogram, showing day by day
		
00:09:34 --> 00:09:38
			how much money is going to be
allocated or spent. I can create a
		
00:09:38 --> 00:09:41
			new curve, and in this case, it's
going to be pretty much the same
		
00:09:41 --> 00:09:42
			thing. The
		
00:09:43 --> 00:09:46
			only difference is going to be,
I'm going to select Histogram
		
00:09:46 --> 00:09:49
			instead of selecting curve, and
I'm going to add and I'm going to
		
00:09:49 --> 00:09:50
			select, OK,
		
00:09:52 --> 00:09:57
			and now I can select this one. And
here it shows the resource
		
00:09:57 --> 00:09:59
			allocation pretty much per day.
		
00:10:00 --> 00:10:03
			Or per time period, showing how
much money is going to be spent.
		
00:10:03 --> 00:10:07
			Again, if you do that for all the
activities, it's going to show you
		
00:10:07 --> 00:10:11
			the ups and downs of the resource
profile, or the resource
		
00:10:11 --> 00:10:15
			allocation curve. So this is the
first part of our discussion about
		
00:10:15 --> 00:10:20
			how to add costs and resources to
the different activities. Now
		
00:10:20 --> 00:10:23
			let's proceed to the next part,
which is talking about calendars.
		
00:10:25 --> 00:10:29
			Let's say you have an Arctic
engineer who works only five days
		
00:10:29 --> 00:10:33
			a week, whereas the site is going
to work six days a week. The
		
00:10:33 --> 00:10:36
			Arctic engineer has some
activities related to the approval
		
00:10:36 --> 00:10:39
			of submittals, the approval of
shop drawings, some inspections
		
00:10:39 --> 00:10:43
			and so on. So these are going to
be done only on a five day basis,
		
00:10:43 --> 00:10:47
			whereas the site is going to be
working on a six workday basis.
		
00:10:47 --> 00:10:51
			Can we allocate more than one
calendar for the same project? The
		
00:10:51 --> 00:10:55
			answer is yes. How many calendars
can we apply for one project? As
		
00:10:55 --> 00:10:59
			many as you want, or as many as
the project needs? So let's go
		
00:10:59 --> 00:11:03
			ahead and see. How are we going to
create a calendar or modify an
		
00:11:03 --> 00:11:07
			existing calendar? And how can we
allocate different calendars to
		
00:11:07 --> 00:11:11
			different activities? So if you go
again to the tab called info,
		
00:11:11 --> 00:11:15
			you're going to find that the
second selection here is
		
00:11:15 --> 00:11:19
			calendars. We are going to click
on this calendars, and now it
		
00:11:19 --> 00:11:22
			shows here some default calendars
that have been built into the
		
00:11:22 --> 00:11:25
			schedule. One of them is a five
day calendar, and notice this
		
00:11:25 --> 00:11:29
			check mark here that shows that
this is the default calendar,
		
00:11:29 --> 00:11:32
			which means if you do not change
it, all the activities are going
		
00:11:32 --> 00:11:37
			to be following that five workday
calendar. The second one is a six
		
00:11:37 --> 00:11:41
			day, and the third one is a seven
day. We can add other calendars as
		
00:11:41 --> 00:11:45
			we want, as needed for the
project. Now notice on the right
		
00:11:45 --> 00:11:47
			side of the screen, here we have
		
00:11:48 --> 00:11:56
			it shows by default, our day today
as highlighted. And if I click on
		
00:11:56 --> 00:12:00
			the five day calendar, notice that
all the days have the same color
		
00:12:01 --> 00:12:04
			when it comes to work days, none
of these boxes is checked. Notice
		
00:12:04 --> 00:12:07
			what's going to happen when I
click on the five day calendar.
		
00:12:09 --> 00:12:13
			Now it shows that Monday, Tuesday,
Wednesday, Thursday and Friday are
		
00:12:13 --> 00:12:16
			checked, whereas Sunday and
Saturday are not checked, which
		
00:12:16 --> 00:12:20
			means these are the non work days
and the other five are the work
		
00:12:20 --> 00:12:23
			days. Now if I go to the six day
calendar, what's going to happen
		
00:12:23 --> 00:12:27
			is that Saturday is going to be
considered as a work day. So
		
00:12:27 --> 00:12:31
			notice here that Saturday also is
checked, and the only day that
		
00:12:31 --> 00:12:35
			appears in red, which is the non
work day, this is Sunday for the
		
00:12:35 --> 00:12:37
			seventh day. Of course, all the
days are going to be checked,
		
00:12:37 --> 00:12:41
			which means the site is working
seven days a week. So let's go
		
00:12:41 --> 00:12:44
			back to the five day calendar,
assuming that, for example, our
		
00:12:44 --> 00:12:45
			project is going to
		
00:12:47 --> 00:12:50
			last for a year. Are we going to
work on the Fourth of July?
		
00:12:50 --> 00:12:54
			Probably not. Are we going to work
on december 25 Christmas Day?
		
00:12:55 --> 00:13:00
			Probably not. So let us designate
these as non work days so that if
		
00:13:02 --> 00:13:05
			work comes through these days,
it's going to jump over that day
		
00:13:05 --> 00:13:10
			and count the following work day
as a continuation of the previous
		
00:13:10 --> 00:13:13
			work. So let's go to July,
		
00:13:14 --> 00:13:18
			and July 4 this year is going to
be on a Wednesday. So I'm going to
		
00:13:18 --> 00:13:24
			click on July 4 and I'm going to
select it as set as non work
		
00:13:24 --> 00:13:28
			notice what's going to happen when
I do that. It has changed its
		
00:13:28 --> 00:13:33
			color to red, which means now it's
a non work day. I can do the same
		
00:13:33 --> 00:13:38
			thing for December, and I can
select december 25 currently it's
		
00:13:38 --> 00:13:40
			a work day. So we're going to
change that, and we're going to
		
00:13:40 --> 00:13:44
			call it a non work day. And there
it is.
		
00:13:45 --> 00:13:50
			Now, let's say I want to assign a
six
		
00:13:52 --> 00:13:56
			workday calendar to backfilling
and compaction, for example. So
		
00:13:56 --> 00:13:59
			here I'm going to accept these
calendars, okay?
		
00:14:00 --> 00:14:02
			And now I'm going to go to the
activity backfilling and
		
00:14:02 --> 00:14:06
			compaction, highlight it and look
at the activity editor here. At
		
00:14:06 --> 00:14:10
			the bottom, it shows calendar, a
tab called calendar. If you click
		
00:14:10 --> 00:14:13
			on this down arrow, it's going to
show you what are the available
		
00:14:13 --> 00:14:16
			calendars based on what we have
created or what we have edited. So
		
00:14:16 --> 00:14:19
			if I click on this arrow, it's
going to show me the five day
		
00:14:19 --> 00:14:22
			calendar, the six day calendar of
the seven day calendar. Let's say
		
00:14:22 --> 00:14:26
			we're going to select the six day
calendar for this activity. So
		
00:14:26 --> 00:14:29
			here it is six day and enter
		
00:14:30 --> 00:14:35
			now we have assigned this activity
to a six workday week. We can do
		
00:14:35 --> 00:14:39
			the same for the other activities
as well. So you might, as we
		
00:14:39 --> 00:14:42
			mentioned, we you can have
multiple calendars for the same
		
00:14:42 --> 00:14:45
			project, depending on the needs
and depending on the different
		
00:14:45 --> 00:14:47
			parties work schedule.
		
00:14:48 --> 00:14:51
			So that's the second part that
covers the area of calendars. Of
		
00:14:51 --> 00:14:56
			course, you can change a work day
into a non work day and vice versa
		
00:14:56 --> 00:14:59
			by checking the box that has this
day or just sell.
		
00:15:00 --> 00:15:04
			One particular day and marking it
as a non work day, or as a work
		
00:15:04 --> 00:15:05
			day.
		
00:15:07 --> 00:15:10
			The third step that we want to
achieve today is
		
00:15:11 --> 00:15:16
			looking at creating sub schedules
from my master schedule. If I have
		
00:15:16 --> 00:15:21
			a project that has 3000
activities, 5000 activities, and I
		
00:15:21 --> 00:15:23
			have multiple subcontractors,
let's say I have 30
		
00:15:23 --> 00:15:27
			subcontractors. Some of them have
activities that are maybe 150
		
00:15:28 --> 00:15:31
			activities, but some of them have
maybe three or four activities. It
		
00:15:31 --> 00:15:34
			doesn't make much sense to give
all of them copies of the same
		
00:15:34 --> 00:15:37
			master schedule that has 5000
activities. They're going to be
		
00:15:37 --> 00:15:41
			totally lost. So the solution in
this case, is for me to create a
		
00:15:41 --> 00:15:46
			sub schedule from the master
schedule. Does that mean that for
		
00:15:46 --> 00:15:48
			each one of these different
subcontractors, I'm going to
		
00:15:48 --> 00:15:52
			create a new schedule? Again? That
would be a waste of time, but if
		
00:15:52 --> 00:15:55
			you develop your schedule
correctly, the first time, we are
		
00:15:55 --> 00:15:59
			going to add tags to certain
activities, or we are going to
		
00:15:59 --> 00:16:03
			create filters through which we're
going to pull all the activities
		
00:16:03 --> 00:16:08
			and then set criteria for the
opening of that filter, which
		
00:16:08 --> 00:16:11
			activities can pass through and
which activities are going to be
		
00:16:11 --> 00:16:15
			withheld. So this concept is
called filters, and that's one of
		
00:16:15 --> 00:16:18
			the strong features of any
scheduling software. Some
		
00:16:18 --> 00:16:21
			softwares do have it. Some
softwares do not have it, so that
		
00:16:22 --> 00:16:25
			would be an indication of whether
that software is really
		
00:16:25 --> 00:16:29
			professional and practical or not.
So let's go ahead. How to create a
		
00:16:29 --> 00:16:33
			filter. Again, look at these
icons. You're going to find one
		
00:16:33 --> 00:16:36
			that looks like a funnel, and
that's basically what a filter is.
		
00:16:36 --> 00:16:40
			So now we're going to create a
filter. Let's say, for example, as
		
00:16:40 --> 00:16:43
			you can see here on the screen,
that's first of all, let's make
		
00:16:43 --> 00:16:46
			these parts disappear. We don't
need them,
		
00:16:47 --> 00:16:50
			and we don't need the activity
editor either. If you look at the
		
00:16:50 --> 00:16:52
			schedule, you're gonna have that,
you're gonna find that we have
		
00:16:52 --> 00:16:56
			some critical activities, the ones
that are shown in red, and some
		
00:16:56 --> 00:16:59
			non critical activities, which are
the ones that that are shown in
		
00:16:59 --> 00:16:59
			green.
		
00:17:00 --> 00:17:03
			And let's say now I want to focus
primarily on the critical
		
00:17:03 --> 00:17:06
			activities. That's going to be my
main concern, because these are
		
00:17:06 --> 00:17:10
			the ones that really affect the
total duration of the project. So
		
00:17:10 --> 00:17:13
			how are we going to do that? I
want to tell the software. Look at
		
00:17:13 --> 00:17:14
			all the activities.
		
00:17:15 --> 00:17:19
			If the activity is critical,
select it. If it is not critical,
		
00:17:19 --> 00:17:25
			set it aside, what is the main
criterion for a critical activity?
		
00:17:26 --> 00:17:30
			A critical activity has a total
float equal to zero before
		
00:17:30 --> 00:17:33
			updating the project, or anything
like that, before having negative
		
00:17:33 --> 00:17:37
			total float, which may happen if
the project is behind schedule. So
		
00:17:37 --> 00:17:41
			for the time being, a critical
activity is one that has zero
		
00:17:41 --> 00:17:45
			total float. So we're going to
tell the filter. We're going to
		
00:17:45 --> 00:17:49
			create a filter, telling it,
please select the activity if its
		
00:17:49 --> 00:17:53
			total float is equal to zero, if
it's more than zero, do not select
		
00:17:53 --> 00:17:56
			it, which means, if it's non
critical, we're not currently
		
00:17:56 --> 00:18:00
			interested in it. So I'm going to
click on Filters, and here it's
		
00:18:00 --> 00:18:04
			going to show that it already has
some filters built in. Let's say
		
00:18:04 --> 00:18:08
			I'm going to create a new filter
to start from scratch, and I'm
		
00:18:08 --> 00:18:10
			going to call it critical
activities only.
		
00:18:16 --> 00:18:17
			So
		
00:18:18 --> 00:18:24
			we're going to add new criteria.
So what the criteria? Which field
		
00:18:24 --> 00:18:27
			am I going to be looking at? I'm
going to be looking at the total
		
00:18:27 --> 00:18:31
			float. So on this, in this drop
down menu, I'm going to scroll
		
00:18:31 --> 00:18:34
			down until I find the total float.
Here it is.
		
00:18:35 --> 00:18:41
			Now, do I want to select critical
or non critical activities? If I
		
00:18:41 --> 00:18:46
			look at the equality here, it says
either is equal to or is greater
		
00:18:46 --> 00:18:51
			than, greater than or equal to
less than less than or equal to
		
00:18:51 --> 00:18:55
			and so on and so forth. So the one
that I'm looking for is is equal
		
00:18:55 --> 00:18:59
			to zero. That's basically the
value that I'm looking for for the
		
00:18:59 --> 00:19:03
			critical activities. So I'm going
to select is equal to and we
		
00:19:03 --> 00:19:05
			accept zero, and I'm going to say,
OK.
		
00:19:07 --> 00:19:12
			And now I'm going to select this
filter critical activities only.
		
00:19:12 --> 00:19:15
			I'm going to add to the active
filters, which is at the bottom of
		
00:19:15 --> 00:19:17
			the screen, and I'm going to say,
apply.
		
00:19:18 --> 00:19:24
			And OK. And there it is. Now we
have only the critical activities.
		
00:19:25 --> 00:19:29
			Let's say I'm done with that, and
I want to go back to the whole
		
00:19:29 --> 00:19:32
			schedule, including critical and
non critical. So I'm going to go
		
00:19:32 --> 00:19:38
			to the filters again, and I'm
going to clear the filter. I don't
		
00:19:38 --> 00:19:41
			want to delete it, I just want to
clear it from this box. So it's
		
00:19:41 --> 00:19:46
			going to go back to the top box,
so Clear Filters apply. And OK,
		
00:19:47 --> 00:19:49
			and here I have all the activities
at that.
		
00:19:50 --> 00:19:53
			Now let's create another very
common and popular and
		
00:19:53 --> 00:19:56
			professional filter, which is, I
want to focus only on the
		
00:19:56 --> 00:19:59
			activities that are going to be
done next month or next.
		
00:20:00 --> 00:20:03
			Six weeks or next eight weeks,
which is called a look ahead
		
00:20:03 --> 00:20:07
			schedule. It could be the most
common one is a six week look
		
00:20:07 --> 00:20:10
			ahead schedule, or eight week look
ahead schedule. So how are we
		
00:20:10 --> 00:20:13
			going to designate that it's going
to be based on dates? So
		
00:20:14 --> 00:20:17
			basically, I'm going to tell the
software that I want to create a
		
00:20:17 --> 00:20:21
			filter that shows the activities
that have a start date or an early
		
00:20:21 --> 00:20:25
			date start or finish. So if this
activity is going to start or
		
00:20:25 --> 00:20:31
			finish between today and the next
six weeks, select this activity.
		
00:20:31 --> 00:20:36
			If not, do not select it. So I'm
going to go here again to filters,
		
00:20:36 --> 00:20:39
			and I'm going to create a new
filter, and I'm going to call it
		
00:20:39 --> 00:20:40
			six week.
		
00:20:41 --> 00:20:42
			Look ahead.
		
00:20:47 --> 00:20:49
			Now we're going to add the
criteria.
		
00:20:50 --> 00:20:53
			So what am I going am I going to
be looking for? I'm looking for,
		
00:20:54 --> 00:20:58
			is it looking at actual start or
actual finish or actual dates? No,
		
00:20:59 --> 00:21:02
			is it looking at early start to
early finish, not only that, but
		
00:21:02 --> 00:21:05
			both of them. So I'm going to
select early dates, select if
		
00:21:05 --> 00:21:10
			early dates is equal to something
or is within a certain range. Now
		
00:21:10 --> 00:21:15
			I want it to be between today and
six weeks later, so I'm going to
		
00:21:15 --> 00:21:19
			go again to my equality, and I'm
going to select within range.
		
00:21:21 --> 00:21:25
			Notice that as soon as I said
dates, it recognized that the
		
00:21:25 --> 00:21:29
			values are going to be dates, so
it showed me a calendar. So I'm
		
00:21:29 --> 00:21:34
			going to select between, let's say
the project here starts on in
		
00:21:34 --> 00:21:39
			February of 2017 so I'm going to
go to the calendar of 2017
		
00:21:40 --> 00:21:46
			and and let's say beginning
February 1, 2017
		
00:21:49 --> 00:21:55
			and ending on six weeks later. So
let's say mid March, 2017
		
00:22:02 --> 00:22:05
			so that's a six week look ahead.
I'm going to say, Okay.
		
00:22:06 --> 00:22:13
			And now I'm going to add my filter
to the active filters. I'm going
		
00:22:13 --> 00:22:14
			to say, apply.
		
00:22:15 --> 00:22:19
			And okay. And now it shows me the
activities that are going to take
		
00:22:19 --> 00:22:25
			place, if their early dates are
between February 1 and March 15.
		
00:22:25 --> 00:22:29
			Notice that it shows an activity
that ends after March 15 because
		
00:22:29 --> 00:22:34
			its start was within that range.
So if the start or the end of the
		
00:22:34 --> 00:22:36
			activity fall within that range,
is going to be selected.
		
00:22:37 --> 00:22:42
			Now I have seen this. So what I'm
going to do go back to now is I'm
		
00:22:42 --> 00:22:44
			going to go back to remove this
filter,
		
00:22:45 --> 00:22:51
			Clear Filters and apply ok, and
we're back to the whole scale.
		
00:22:52 --> 00:22:56
			So in our discussion today, we
have learned a few things. One is
		
00:22:56 --> 00:23:01
			learning about resources and cost,
how to add resources and cost of
		
00:23:01 --> 00:23:04
			the project, and how to apply
these costs to the different
		
00:23:04 --> 00:23:09
			activities, and how to draw the
graph, the smooth curve, the S
		
00:23:09 --> 00:23:13
			curve, BCWS, or planned value, and
how also to show the resource
		
00:23:13 --> 00:23:18
			loading histogram for individual
units of time. And then we learned
		
00:23:18 --> 00:23:22
			about the calendars, how to create
new calendars, or how to edit
		
00:23:22 --> 00:23:27
			existing calendars by adding work
days or non work days, and how to
		
00:23:27 --> 00:23:30
			assign or allocate these calendars
to the different activities. And
		
00:23:30 --> 00:23:33
			we agreed that the project can
have multiple calendars. And then
		
00:23:33 --> 00:23:38
			finally, we learned about the
filters. How can we from one
		
00:23:38 --> 00:23:42
			master schedule? How can we select
sub schedules depending on what
		
00:23:42 --> 00:23:45
			are we looking for, whether it's
on the critical activities or
		
00:23:45 --> 00:23:49
			activities that are done within a
period of time. Later on, we are
		
00:23:49 --> 00:23:53
			going to learn about another kind
of tags, which is called activity
		
00:23:53 --> 00:23:56
			codes, that also enables us which
are
		
00:23:58 --> 00:24:01
			fields that we create on our own.
We can customize the schedule
		
00:24:01 --> 00:24:04
			whichever way we want, and these
are going to be tools or tags that
		
00:24:04 --> 00:24:08
			are going to enable us to select
and sort different activities and
		
00:24:08 --> 00:24:13
			different filters based on these
codes. That is the end of our
		
00:24:13 --> 00:24:16
			discussion for today. So until
next time, I'm going to see you in
		
00:24:16 --> 00:24:22
			another lesson about working with
Phoenix project schedule, thank
		
00:24:22 --> 00:24:22
			you. Thank.