Ihab Saad – Schedule Updating

Ihab Saad
AI: Summary ©
The speakers discuss the process of updating and maintaining a schedule, identifying the cause of deviation from the baseline and addressing mistakes to avoid them in the future. They also discuss the importance of proper actions to prevent future mistakes and the need for continuous monitoring and updating the schedule. The process of planning and executing a project is discussed, including monitoring performance, updating objectives, and tracking progress. The weight of completed activities is measured, and progress is measured by the actual date and the weight of completed activities is various percentages. The sub strengthen completion percentage is calculated, and the payment request is reviewed and resubmitted.
AI: Transcript ©
00:00:01 --> 00:00:04

Hello again, in new in a new lecture of construction

00:00:04 --> 00:00:07

scheduling, and today we're going to start talking about schedule

00:00:07 --> 00:00:10

updating. As you remember, when we discussed the time management

00:00:11 --> 00:00:15

steps, we mentioned six steps. The first one was activity definition,

00:00:16 --> 00:00:20

the second one was activity sequencing, followed by resource

00:00:20 --> 00:00:24

estimating and duration estimating, and then we have

00:00:24 --> 00:00:28

scheduled development, and finally, scheduled control. So

00:00:28 --> 00:00:32

far, we have talked about maybe five of these steps, which ended

00:00:32 --> 00:00:36

up with schedule development, where we have managed to develop a

00:00:36 --> 00:00:39

schedule, calculate the early start, early finish, late start

00:00:39 --> 00:00:42

and late finish, total float and free float for different

00:00:42 --> 00:00:45

activities. And now that we have a schedule, we have to put it to

00:00:45 --> 00:00:50

work, and we have to see whether it's feasible or not, and we have

00:00:50 --> 00:00:53

to maintain and update the schedule, as we have already

00:00:53 --> 00:00:56

mentioned in class. We have while developing the schedule, we have

00:00:56 --> 00:01:01

to develop a schedule maintenance for management plan. This schedule

00:01:01 --> 00:01:04

management plan basically says, how often are we going to update

00:01:04 --> 00:01:08

the schedule? How are we going to update the schedule? In some

00:01:08 --> 00:01:11

cases, this is mandated by the contract where the contractor has

00:01:11 --> 00:01:15

to submit, at the end of each month with the progress report, an

00:01:15 --> 00:01:18

updated schedule reflecting the current status of the project. And

00:01:18 --> 00:01:21

in some cases, the contractor would take that initiative on his

00:01:21 --> 00:01:24

or her own, because they want to make sure that the schedule that

00:01:24 --> 00:01:28

they have developed is feasible and practical at the same time,

00:01:28 --> 00:01:31

and they want to know at each point in time, at any point in

00:01:31 --> 00:01:35

time, where are they compared to their baseline or their

00:01:35 --> 00:01:39

established approved schedule. So the topic today that we're going

00:01:39 --> 00:01:44

to talk about is how to update the schedule and keep it in a proper

00:01:44 --> 00:01:44

shape.

00:01:45 --> 00:01:49

So schedule development serves two major tasks. The first one is

00:01:49 --> 00:01:52

planning and control. So we want to know what are we going to do,

00:01:52 --> 00:01:55

and then while we are performing the project, we want to know

00:01:55 --> 00:01:58

whether we are doing it as planned or not. So that's the planning and

00:01:58 --> 00:02:02

control aspects of schedule development in time planning

00:02:02 --> 00:02:06

schedule is developed to establish a baseline or benchmark to be

00:02:06 --> 00:02:09

monitored and controlled during the project execution. This is

00:02:09 --> 00:02:12

what we're going to call the baseline schedule, which is going

00:02:12 --> 00:02:16

to be an approved document. Once it's approved by the owner, it

00:02:16 --> 00:02:20

becomes sort of a contractual document that the contractor and

00:02:20 --> 00:02:24

the owner are going to be bound to so in project control, the actual

00:02:24 --> 00:02:28

performance is compared to the baseline. And once we make that

00:02:28 --> 00:02:32

comparison, which is what we call control monitoring and control,

00:02:32 --> 00:02:34

we're going to monitor the progress. And then in case of any

00:02:34 --> 00:02:39

deviation from the plan or the baseline, we need to know how much

00:02:39 --> 00:02:43

is that deviation. Why did it happen? We have to analyze the

00:02:43 --> 00:02:47

root cause and find out solutions and try to make sure that the

00:02:47 --> 00:02:50

problems that occurred in the past do not keep perpetuating and

00:02:50 --> 00:02:54

repeating it themselves in the future. So the scheduler compares

00:02:54 --> 00:02:57

the actual performance with the baseline performance to discern

00:02:57 --> 00:03:01

any deviation, not just for preparation and presentation to

00:03:01 --> 00:03:04

the owner before commencement of the work, and not just as a

00:03:04 --> 00:03:08

satisfaction of contractual requirements, but primarily to

00:03:08 --> 00:03:12

keep the project under control and maintain its major milestones, to

00:03:12 --> 00:03:15

make sure the project is not slipping gradually.

00:03:17 --> 00:03:21

So in case of deviation from the baseline, and this is almost

00:03:21 --> 00:03:24

always going to happen. I have personally not seen any project

00:03:24 --> 00:03:28

finishing exactly as planned. There's always going to be some

00:03:28 --> 00:03:30

fine tuning to that plan. There's going to be some deviation from

00:03:30 --> 00:03:34

the plan, whether it's based on uncontrollable conditions, which

00:03:34 --> 00:03:38

is what we called in class force majeure, or something beyond the

00:03:38 --> 00:03:41

control of all the contractual parties, or it might be due to

00:03:41 --> 00:03:47

some mistake or fault, due to action or inaction by any of the

00:03:47 --> 00:03:50

contractual parties, whether it's the owner, the contractor or the

00:03:50 --> 00:03:54

Arctic engineer, the construction manager, subcontractors and so on

00:03:54 --> 00:03:58

and so forth. It could be unexpected soil conditions, it

00:03:58 --> 00:04:01

could be inclement weather. It could be Equipment Breakdown, so

00:04:01 --> 00:04:05

many different factors that can lead to deviation from the

00:04:05 --> 00:04:09

baseline schedule. So the manager, the project manager, needs to know

00:04:09 --> 00:04:12

where is the deviation in which activity or which set of

00:04:12 --> 00:04:15

activities, what's the cause of that deviation, whether it's the

00:04:15 --> 00:04:19

schedule initially was defective in its initial assessment, or the

00:04:19 --> 00:04:23

performance did not match the expected production rates. For

00:04:23 --> 00:04:27

example, what is the magnitude of the deviation? Again, if we're

00:04:27 --> 00:04:29

talking about a three year project and we have a deviation of three

00:04:29 --> 00:04:33

days, no big deal. We kind of covered that very easily. But if

00:04:33 --> 00:04:37

we're talking about a project with a six month duration and we have

00:04:37 --> 00:04:40

three weeks of delay, this is really considerable.

00:04:41 --> 00:04:46

So once we analyze the deviation and we know its magnitude, what's

00:04:46 --> 00:04:49

the required corrective action to be taken? How can we correct that

00:04:49 --> 00:04:53

mistake? Is it through filing a claim for time extension, for

00:04:53 --> 00:04:56

example? Is it through acceleration of work, working

00:04:56 --> 00:04:59

another shift or using bigger equipment, using additional

00:04:59 --> 00:04:59

resources?

00:05:00 --> 00:05:03

So what kind of preventive action should be taken to avoid

00:05:03 --> 00:05:06

repetition of the causes of that deviation, just to make sure that

00:05:06 --> 00:05:09

we do not repeat the same mistakes? And what is the end

00:05:09 --> 00:05:13

forecast, if we keep progressing at the same pace, are we going to

00:05:13 --> 00:05:16

be able to finish on time? If it's a non critical activity, are we

00:05:16 --> 00:05:19

within our float so it does not affect the schedule? If we are in

00:05:19 --> 00:05:22

a critical activity, then definitely it's going to affect

00:05:22 --> 00:05:26

the schedule, and most importantly, which is what you can

00:05:26 --> 00:05:29

carry from one project to another, is what are the lessons learned?

00:05:32 --> 00:05:36

So this is this graph shows basically a the project control

00:05:36 --> 00:05:40

cycle, where we start planning, we develop the project objectives, we

00:05:40 --> 00:05:44

implement the project and keep monitoring the performance, and

00:05:44 --> 00:05:50

then we measure the progress on a scheduled frequent basis, and then

00:05:50 --> 00:05:54

we find what the root cause is of any deviation, if any. And then we

00:05:54 --> 00:05:57

implement the controls, whether it's corrective action or

00:05:57 --> 00:06:02

preventive action. And then we update the project objectives, and

00:06:02 --> 00:06:06

then we keep repeat the same cycle again. We do that on a weekly

00:06:06 --> 00:06:10

basis, bi monthly basis, monthly basis. We need to keep doing that

00:06:10 --> 00:06:12

as long as the project is progressing.

00:06:15 --> 00:06:18

Control means not only monitoring, so monitoring is observing and

00:06:18 --> 00:06:22

measuring, but what is the result of that monitoring and observing?

00:06:22 --> 00:06:26

It's the the decision that we're going to make. So track. It's

00:06:26 --> 00:06:30

taking the corrective measures whenever and wherever necessary to

00:06:30 --> 00:06:34

control is to compare. So we have to have a baseline or a benchmark

00:06:34 --> 00:06:38

to compare to. We have to have a fixed target, and then we have to

00:06:38 --> 00:06:42

have to have a moving object, which is the schedule under

00:06:42 --> 00:06:46

progress, we have to compare that moving object to the to the fixed

00:06:46 --> 00:06:49

target to know exactly how are we performing.

00:06:52 --> 00:06:55

So the baseline is also known as the target schedule, as we just

00:06:55 --> 00:06:59

mentioned, and it may be different with as planned schedule. So we

00:06:59 --> 00:07:03

keep updating that basically due to contractual changes, for

00:07:03 --> 00:07:04

example, that have

00:07:05 --> 00:07:08

shown after we have signed the contract and things like that.

00:07:08 --> 00:07:11

It's going to be prepared by the general contractor, usually to

00:07:11 --> 00:07:15

incorporate all the sub schedule develop schedules developed by the

00:07:15 --> 00:07:19

subcontractors and suppliers. And it has to be developed before the

00:07:19 --> 00:07:22

start of the project, because, as we mentioned in most of the cases,

00:07:22 --> 00:07:26

this is going to be a contractual document that everyone is going to

00:07:26 --> 00:07:29

be using in the future. It's going to be used for performance

00:07:29 --> 00:07:33

comparison, and if approved by the owner, it becomes a part of the

00:07:33 --> 00:07:34

contract documents.

00:07:36 --> 00:07:39

The updated schedule is the schedule reflecting the actual

00:07:39 --> 00:07:42

performance information. So this is not the target schedule

00:07:42 --> 00:07:45

anymore. Now we're moving. We're talking about the moving object

00:07:45 --> 00:07:50

that that vehicle that's moving along, the project completion. It

00:07:50 --> 00:07:54

includes the time of occurrence of different activities, amount or

00:07:54 --> 00:07:59

percentage of work completed, what we call the PCT, and changes to

00:07:59 --> 00:08:03

future work. So as a definition, a revised schedule reflecting the

00:08:03 --> 00:08:07

project information at a given data date we're gone. That's the

00:08:07 --> 00:08:10

data date, the measuring date where we're gonna measure our

00:08:10 --> 00:08:14

performance and decide how we're doing regarding completed

00:08:14 --> 00:08:17

activities in progress, activities and changes in the logic, cost and

00:08:17 --> 00:08:22

resources required and allocated at any activity level, it reflects

00:08:22 --> 00:08:25

the actual start and finish dates for activities as well as the

00:08:25 --> 00:08:29

percentage of completion PCT. So these are at least three pieces of

00:08:29 --> 00:08:31

information that we need to collect during the monitoring

00:08:31 --> 00:08:34

process. For the activities that have started, what was their

00:08:34 --> 00:08:38

actual start? If the activity is complete, what was the actual

00:08:38 --> 00:08:41

finish for that activity? And if the activity has started, but it's

00:08:41 --> 00:08:44

still in progress. It's not complete yet. What is the percent

00:08:44 --> 00:08:47

complete, or the percentage of completion of that activity? And

00:08:47 --> 00:08:50

we're going to see different ways of measuring that percentage of

00:08:50 --> 00:08:51

completion.

00:08:53 --> 00:08:57

So the data date is also known as the as of date schedule, date

00:08:57 --> 00:09:01

status, date, update, date. All of these are the same things talking

00:09:01 --> 00:09:05

about the same concept, which is the date as of which all progress

00:09:05 --> 00:09:09

on the project is reported. It is not the current date or the time

00:09:09 --> 00:09:15

now, because, for example, today might be March 10 or March 9, but

00:09:15 --> 00:09:20

I based my schedule on an update on or a cutoff date on March 5,

00:09:20 --> 00:09:21

for example.

00:09:24 --> 00:09:26

So some of the required information that we need to

00:09:26 --> 00:09:30

collect are the actual start, which denotes the actual start

00:09:30 --> 00:09:33

date of the activity obtained from the construction site or from the

00:09:33 --> 00:09:36

key performer of the activity. If it's done in a shop by

00:09:36 --> 00:09:40

subcontractor or supplier, they are going to provide that provide

00:09:40 --> 00:09:43

us with that actual start, and the actual finish denotes the date by

00:09:43 --> 00:09:47

which the activity is considered to be complete, whether it's

00:09:47 --> 00:09:49

substantial completion or practical completion. This is

00:09:49 --> 00:09:53

something to discuss a little bit later, PCT or percent complete,

00:09:53 --> 00:09:56

which applies to activities that have an actual start. If it has

00:09:56 --> 00:09:59

not started yet, then the Percent Complete is zero. If the.

00:20:00 --> 00:20:00

It 100%

00:20:01 --> 00:20:08

if it is not complete, it is 0% so if it has not started, 0% started

00:20:08 --> 00:20:11

but not yet finished. Either I give it an arbitrary amount or

00:20:11 --> 00:20:15

start just give it zero or wait until it's complete. And then in

00:20:15 --> 00:20:19

this case, I'm going to count it as 100% and this can be very

00:20:19 --> 00:20:23

useful only for very short activities with a very short

00:20:23 --> 00:20:23

duration.

00:20:27 --> 00:20:30

Another elaboration on the all or nothing is the incremental

00:20:30 --> 00:20:34

milestones. If I have, for example, a large slab on grade,

00:20:34 --> 00:20:35

and in that slab on grade, I have

00:20:37 --> 00:20:42

some underground pipes and cables, and I have rebar, and I have

00:20:42 --> 00:20:47

concrete and so on, and I have curing of that concrete. So if the

00:20:47 --> 00:20:53

rebar is 50% complete, am I going to consider it zero and wait until

00:20:53 --> 00:20:55

it's 100% to call, to call, to count it as 100%

00:20:56 --> 00:20:59

that would be relatively unfair, because this might be a long

00:20:59 --> 00:21:02

activity with a long duration. So it's used for activities that

00:21:02 --> 00:21:07

contain a set of tasks or stages. I can say, for example, that once

00:21:08 --> 00:21:12

the four more for that slab on grade is done, this is, let's say,

00:21:12 --> 00:21:12

10%

00:21:13 --> 00:21:19

once the underground utilities are done. This is 50% once the rebar

00:21:19 --> 00:21:24

is done. That's another 30% so it's a total of 90% or 80% and

00:21:24 --> 00:21:28

then once I have placed the concrete, that's another 10% and

00:21:28 --> 00:21:31

once I cure the concrete and I remove the forms, then this is the

00:21:31 --> 00:21:35

remaining amount, and that way I can measure the progress of that

00:21:35 --> 00:21:39

activity based on which subtasks have been completed. So each stage

00:21:39 --> 00:21:43

of a given activities assigned a weight that's approximately equal

00:21:43 --> 00:21:47

to its percentage share in the effort in the total activity. Then

00:21:47 --> 00:21:52

each stage is treated as all or nothing. So if the rebar is not

00:21:52 --> 00:21:55

complete, I'm not I'm going to give it a zero. If it's complete,

00:21:55 --> 00:21:58

I'm going to give it all of the 40% which is the weight of that

00:21:58 --> 00:21:59

rebar and so on.

00:22:01 --> 00:22:04

So here is an example of incremental milestones a

00:22:04 --> 00:22:08

contractor is installing. 25 doors. Four doors have not yet

00:22:08 --> 00:22:11

been started, so percent complete is 08.

00:22:12 --> 00:22:15

Doors had their frames erected, and we consider that the frame

00:22:15 --> 00:22:17

erection for each door is 30% of the work.

00:22:18 --> 00:22:22

Six doors have been hung. We consider hanging the doors is 50%

00:22:23 --> 00:22:27

of the work. Four doors after being hung have been painted, so

00:22:27 --> 00:22:31

we consider that as 70% 75% of the work. And then the last three

00:22:31 --> 00:22:35

doors had all of the previous steps completed, plus the hardware

00:22:35 --> 00:22:39

also installed, which is remaining 25% so now these three doors are

00:22:39 --> 00:22:44

100% complete. Now, if I want to know what's the total progress of

00:22:44 --> 00:22:48

that activity, of hanging these and installing these 25 doors,

00:22:48 --> 00:22:53

here's the example. So for the activity not yet started, four

00:22:53 --> 00:22:56

times zero is zero. We can consider that the total weight is

00:22:56 --> 00:23:01

25 which is 25 doors times 100 points for each door. So a total

00:23:01 --> 00:23:06

is 2500 points. So for the doors that have not been installed, it's

00:23:06 --> 00:23:10

four times zero. So it's zero. For the doors that have been

00:23:11 --> 00:23:16

erected or manufactured, it's eight doors, and that's 30%

00:23:18 --> 00:23:25

so eight times 30, times 30, that's going to give us 9.6%

00:23:26 --> 00:23:31

or eight times 30, which, which is 240 points, compared to the 2500

00:23:31 --> 00:23:35

points. That's 9.6% the doors that have been already hung

00:23:36 --> 00:23:41

six doors. So again, six times 50 because that's 50%

00:23:42 --> 00:23:47

so that's a total of 300 points divided by 2500 that's another 12%

00:23:48 --> 00:23:51

the doors that have been painted four doors times 75%

00:23:52 --> 00:23:58

which is 75 points. So 300 points divided by 2500 that's another 12%

00:23:58 --> 00:24:01

and finally, three doors have been completed. And these are 300

00:24:02 --> 00:24:06

points, because it's 100% for these three doors. So 300 divided

00:24:06 --> 00:24:11

by 2500 that's another 12% so when we add that total, it gives us a

00:24:11 --> 00:24:14

percentage of completion for that activity of installing the 25

00:24:15 --> 00:24:16

doors of 45.6%

00:24:22 --> 00:24:25

method number five is supervisors opinion, and that's sort of

00:24:25 --> 00:24:29

subjective, because the supervisors or the superintendents

00:24:29 --> 00:24:32

might have different opinions on the progress of the activity. They

00:24:32 --> 00:24:35

might think that the hard part has already passed and what's left is

00:24:36 --> 00:24:39

quite easy work, so they might give a higher percentage of

00:24:39 --> 00:24:44

completion. No other method can be suited, it's going to be used if

00:24:44 --> 00:24:47

no other method can be suited, suitably applied only in this

00:24:47 --> 00:24:51

case, and it relies totally on the foreman or superintendent's

00:24:51 --> 00:24:55

judgment. So it's most convenient, because it's easy to obtain, but

00:24:55 --> 00:24:59

it might be the least accurate because it's, again, a subjective,

00:24:59 --> 00:24:59

uh.

00:30:00 --> 00:30:03

By the fifth day of the month, the general contractor is going to

00:30:03 --> 00:30:07

list all the activities that had that had work done on them since

00:30:07 --> 00:30:10

the previous period. We're going to say this month we have worked

00:30:10 --> 00:30:10

on 12345,

00:30:11 --> 00:30:15

and this is the these are the actual dates, and these are the

00:30:15 --> 00:30:19

percentage of completion for each activity that's going to include

00:30:19 --> 00:30:22

the actual start, actual finished, percent complete and original

00:30:22 --> 00:30:26

budget, cost to this of this period, cost to date and cost to

00:30:26 --> 00:30:28

complete what's the left, the remaining cost to complete that

00:30:28 --> 00:30:33

activity, and the general contractor and the subcontractor

00:30:33 --> 00:30:36

have to concur on percent complete. So again, if you have a

00:30:36 --> 00:30:39

subcontractor that submitted this information to you, you have to

00:30:39 --> 00:30:43

agree with the subcontractor. So only 1% complete is going to be

00:30:43 --> 00:30:47

submitted, and it's usually going to be on the conservative side. So

00:30:47 --> 00:30:51

if the subcontractor says it's 75% and you, as a GC, say, No, it's

00:30:51 --> 00:30:55

only 70% what you're going to submit is the 70% not the 75 the

00:30:57 --> 00:31:00

report is going to be reviewed and verified by the owner or the

00:31:00 --> 00:31:04

owner's representative, the Arctic engineer, for example, or the

00:31:04 --> 00:31:07

construction manager for the owner. And they're going to check

00:31:07 --> 00:31:09

the completed quantity. They're going to ensure that these

00:31:09 --> 00:31:13

quantities have been completed properly according to the specs

00:31:13 --> 00:31:16

and they've been accepted. They're going to review the unit prices as

00:31:16 --> 00:31:20

per the bid price, and the totals are going to be calculated in the

00:31:20 --> 00:31:24

payment request. The payment request can be approved as is, if

00:31:24 --> 00:31:28

there's no disagreement between the client and the contractor, or

00:31:28 --> 00:31:31

approved with some numbers this approved. So we're gonna hold on

00:31:31 --> 00:31:34

on these numbers. We're not we're going to investigate them a little

00:31:34 --> 00:31:37

more, but in order not to delay the whole payment, we're going to

00:31:37 --> 00:31:40

set them aside and give you the release for the approved amount,

00:31:40 --> 00:31:43

or totally rejected and sent for resubmit if there are some

00:31:43 --> 00:31:47

erroneous quantities or erroneous calculations or disagreement on

00:31:47 --> 00:31:50

conceptual issues in that payment, it might be returned to the

00:31:50 --> 00:31:54

contractor for review and resubmittal, and the schedule of

00:31:54 --> 00:31:58

values must be updated with the cost of any change orders to

00:31:58 --> 00:32:02

reflect that the new unit price Is is this and not the old one in the

00:32:02 --> 00:32:03

bit?

00:32:04 --> 00:32:07

And basically, this is the end of this lecture talking about

00:32:07 --> 00:32:12

schedule updating. I hope now, by now, you know what scheduled

00:32:12 --> 00:32:15

updating means and how it's going to be used to maintain the project

00:32:16 --> 00:32:19

schedule. Thank you and see you in the next lecture. Bye, bye.