Ihab Saad – MS Project session 2 Calendars

Ihab Saad
AI: Summary ©
The speaker explains how to modify and schedule a project, including using calendars and scheduling different work days. They also explain how to designate certain days as nonwork and add new calendars. The speaker provides guidance on creating a new calendar for work days, assigning activity to certain work days, and modifying an existing calendar. They provide guidance on how to assign a calendar to certain work days and how to modify an existing one.
AI: Transcript ©
00:00:03 --> 00:00:08

All right, welcome to the second lecture in Microsoft Project. And

00:00:08 --> 00:00:11

basically, in this lecture, we're going to learn about calendars.

00:00:11 --> 00:00:16

What are calendars? How can we modify calendars? How can we add

00:00:16 --> 00:00:18

calendars? How do we assign different calendars to different

00:00:18 --> 00:00:23

activities and schedule the project accordingly. So basically,

00:00:23 --> 00:00:27

a calendar shows how many work days do we have per week, what are

00:00:27 --> 00:00:31

the working times, and so on and so forth. And then if we have any

00:00:31 --> 00:00:35

holidays, or if any, if we have any non work days, whether they

00:00:35 --> 00:00:39

are regular non work days, like, for example, Easter or the Fourth

00:00:39 --> 00:00:44

of July or Labor Day and stuff like that, or if we have any

00:00:44 --> 00:00:48

particular non work days for that particular project. So for

00:00:48 --> 00:00:51

example, we're going to have a shutdown of a certain plant, or

00:00:51 --> 00:00:54

we're going to have maintenance on certain equipment and things like

00:00:54 --> 00:00:56

that, so we're not going to have work during that time.

00:00:57 --> 00:01:03

The other issue is how to make a non work day a working day. So for

00:01:03 --> 00:01:07

example, Saturdays and Sundays are usually non work days. What if we

00:01:07 --> 00:01:12

have to work on a certain Saturday or a certain Sunday to allow for

00:01:12 --> 00:01:16

the project to finish on time and things of that sort? So the first

00:01:16 --> 00:01:20

thing that we're going to do is learn about calendars, and in

00:01:20 --> 00:01:23

order to do that, we are going to go to project

00:01:27 --> 00:01:31

and we are going to go to Change Working times.

00:01:34 --> 00:01:37

So under Change Working time you have, you can see here that we

00:01:37 --> 00:01:40

have a calendar, a standard calendar. I have gone already and

00:01:40 --> 00:01:45

added a couple of non work days and so on. So the calendar shows

00:01:45 --> 00:01:49

that we have five work days per week, Monday through Friday, and

00:01:49 --> 00:01:54

then Saturday and Sunday are the non work days or the weekend. Here

00:01:54 --> 00:01:56

at the bottom, we have something called exceptions. And here you

00:01:56 --> 00:01:59

have the legend on the on the side that shows what's a working day,

00:01:59 --> 00:02:03

what's non working and so on. And then here we have the exceptions,

00:02:03 --> 00:02:08

if I want to designate a certain day as an exception, so if it is a

00:02:08 --> 00:02:12

working day and I want to make it a non work day, or the opposite,

00:02:12 --> 00:02:15

if it's a non work day and I want to make it a working day. So for

00:02:15 --> 00:02:19

example, here we have Independence Day, the Fourth of July. I have

00:02:19 --> 00:02:24

already added that, and the way to do that is quite simple. Let's say

00:02:24 --> 00:02:26

I want to designate

00:02:28 --> 00:02:31

april 11 as a non work day.

00:02:33 --> 00:02:36

So I'm going to go here, and I'm going to call it

00:02:38 --> 00:02:39

non work.

00:02:40 --> 00:02:44

Of course, we have to give a certain reason for that, and I'm

00:02:44 --> 00:02:46

going to enter the date,

00:02:47 --> 00:02:52

which is, in this case, april 11. And now it has been designated as

00:02:52 --> 00:02:55

a non work day. It's that simple,

00:02:56 --> 00:03:00

if I go down, as you can see now, it has been shaded so it shows

00:03:00 --> 00:03:03

that this is a an exception day, becoming a non work day.

00:03:04 --> 00:03:09

The other way around is, if I want to make a Saturday, for example, a

00:03:09 --> 00:03:12

working day, I can do the same thing here,

00:03:13 --> 00:03:15

and I can call this

00:03:17 --> 00:03:17

receiving

00:03:19 --> 00:03:20

equipment,

00:03:21 --> 00:03:24

if certain equipment is going to arrive on site on that day, and I

00:03:24 --> 00:03:28

need someone to be there to receive that equipment. So now

00:03:28 --> 00:03:33

that particular Saturday has been designated as a work day, which is

00:03:33 --> 00:03:36

the exception from being a non work day.

00:03:41 --> 00:03:41

Okay.

00:03:42 --> 00:03:46

Now if I want to add a new calendar, let's say for my

00:03:46 --> 00:03:50

calendar right now is a five workday per week. Let's say I want

00:03:50 --> 00:03:54

to add another calendar, and I'm going to call it I am going to

00:03:54 --> 00:03:55

create a new calendar

00:03:57 --> 00:03:58

and I'm going to call it six day.

00:04:01 --> 00:04:05

Basically this calendar is going to be a six working day per week,

00:04:05 --> 00:04:10

and I'm going to make an exact copy of my standard calendar.

00:04:10 --> 00:04:13

Instead of adding all the holidays and the non work days and so on,

00:04:13 --> 00:04:16

I'm just going to make a copy, and then I'm going to modify that as

00:04:16 --> 00:04:20

well. So I'm going to go to, okay, make a copy of standard Okay,

00:04:23 --> 00:04:28

make changes? Yes, because we have not closed standard. So now it has

00:04:28 --> 00:04:33

created a new calendar called six day. What I want to do now? I want

00:04:33 --> 00:04:37

to designate Saturdays. All Saturdays as being work days. So

00:04:37 --> 00:04:41

let's say the site works six days per week and the office works five

00:04:41 --> 00:04:45

days a week. So any activity related to the site, I'm going to

00:04:45 --> 00:04:48

assign it to this calendar six day, and any activity related to

00:04:48 --> 00:04:51

the office or to certain other trades outside, I'm going to

00:04:51 --> 00:04:56

assign to the five work day. So what I have to do now, instead of

00:04:56 --> 00:04:59

going through every Saturday and designating it as a next.

00:05:00 --> 00:05:03

Option. There's another easier way of doing that. I'm going to go to

00:05:03 --> 00:05:04

work weeks,

00:05:06 --> 00:05:07

and

00:05:08 --> 00:05:11

I'm going to click here.

00:05:14 --> 00:05:16

I'm going to click on options.

00:05:20 --> 00:05:25

Now this shows here, the week starts on Monday, and the times of

00:05:25 --> 00:05:28

work and hours per week and so on and so forth.

00:05:29 --> 00:05:32

Now I'm going to go on Saturday. Click on Saturday. I

00:05:43 --> 00:05:45

and I'm going to click on details.

00:05:49 --> 00:05:53

Now it shows the seven days of the week. I'm going to click on

00:05:53 --> 00:05:53

Saturday. So

00:05:55 --> 00:05:58

this is going to apply from now on to all Saturdays in this calendar.

00:05:58 --> 00:06:03

And I'm going to click on Set days to these specific working times, I

00:06:03 --> 00:06:06

want to designate what is going to be the working time on Saturdays.

00:06:06 --> 00:06:10

So we're going to make it a regular work day. So we're going

00:06:10 --> 00:06:11

to start at 8am

00:06:18 --> 00:06:18

two

00:06:20 --> 00:06:21

is going to be

00:06:22 --> 00:06:22

12.

00:06:28 --> 00:06:30

Let's go back here, 8am

00:06:33 --> 00:06:34

to

00:06:40 --> 00:06:41

12. We're

00:06:42 --> 00:06:43

going to make that PM,

00:06:46 --> 00:06:49

and then after lunch, we're going to start at 1pm

00:06:52 --> 00:06:53

two,

00:06:56 --> 00:06:57

5pm

00:07:01 --> 00:07:01

and hit OK.

00:07:03 --> 00:07:08

And now, as you can see, all Saturdays became work days. So

00:07:08 --> 00:07:11

this is the second thing that we new thing that we've learned today

00:07:11 --> 00:07:14

we learned so far about how to modify an existing calendar, which

00:07:14 --> 00:07:19

is the standard calendar, and then how to add non work days, and how

00:07:19 --> 00:07:24

to convert a non work day into a working day. And then we learned

00:07:24 --> 00:07:27

about how to add a new calendar, the six work day calendar, and how

00:07:27 --> 00:07:28

to

00:07:29 --> 00:07:34

assign, basically Saturdays as a working day. Now we're going to go

00:07:34 --> 00:07:35

to OK,

00:07:39 --> 00:07:40

and basically

00:07:42 --> 00:07:44

I'll go now to task.

00:07:45 --> 00:07:49

And what I want to do is assign Calendar Number two, the six

00:07:49 --> 00:07:52

workday calendar, to certain activities. So whichever

00:07:52 --> 00:07:54

activities are going to follow that calendar, they have to be

00:07:54 --> 00:07:58

assigned to that calendar. Let's say I'm going to go to excavation

00:07:58 --> 00:07:59

and site leveling.

00:08:01 --> 00:08:05

This activity here, this task, and I'm going to click on information,

00:08:08 --> 00:08:08

and

00:08:10 --> 00:08:12

if I go to Advanced,

00:08:15 --> 00:08:18

it's going to show me calendar. Which calendar is this activity

00:08:18 --> 00:08:21

going to follow? I'm going to call the six day calendar

00:08:24 --> 00:08:25

and hit OK,

00:08:26 --> 00:08:31

and now it's going to show here, under the task indicators, that

00:08:31 --> 00:08:35

this activity has been assigned to the calendar six day. So the

00:08:35 --> 00:08:37

calendar six days assigned to the task.

00:08:41 --> 00:08:43

Now that we've done that, we can do that to other activities as

00:08:43 --> 00:08:48

well and so on. So basically, this is the end of the second lesson on

00:08:48 --> 00:08:55

how to modify calendars and how to assign different calendars to

00:08:55 --> 00:08:58

different activities. Well, see you next time in the next lesson.