The speaker explains how to modify and schedule a project, including using calendars and scheduling different work days. They also explain how to designate certain days as nonwork and add new calendars. The speaker provides guidance on creating a new calendar for work days, assigning activity to certain work days, and modifying an existing calendar. They provide guidance on how to assign a calendar to certain work days and how to modify an existing one.

AI: Summary ©

00:00:03 --> 00:00:08
			All right, welcome to the second
lecture in Microsoft Project. And
		
00:00:08 --> 00:00:11
			basically, in this lecture, we're
going to learn about calendars.
		
00:00:11 --> 00:00:16
			What are calendars? How can we
modify calendars? How can we add
		
00:00:16 --> 00:00:18
			calendars? How do we assign
different calendars to different
		
00:00:18 --> 00:00:23
			activities and schedule the
project accordingly. So basically,
		
00:00:23 --> 00:00:27
			a calendar shows how many work
days do we have per week, what are
		
00:00:27 --> 00:00:31
			the working times, and so on and
so forth. And then if we have any
		
00:00:31 --> 00:00:35
			holidays, or if any, if we have
any non work days, whether they
		
00:00:35 --> 00:00:39
			are regular non work days, like,
for example, Easter or the Fourth
		
00:00:39 --> 00:00:44
			of July or Labor Day and stuff
like that, or if we have any
		
00:00:44 --> 00:00:48
			particular non work days for that
particular project. So for
		
00:00:48 --> 00:00:51
			example, we're going to have a
shutdown of a certain plant, or
		
00:00:51 --> 00:00:54
			we're going to have maintenance on
certain equipment and things like
		
00:00:54 --> 00:00:56
			that, so we're not going to have
work during that time.
		
00:00:57 --> 00:01:03
			The other issue is how to make a
non work day a working day. So for
		
00:01:03 --> 00:01:07
			example, Saturdays and Sundays are
usually non work days. What if we
		
00:01:07 --> 00:01:12
			have to work on a certain Saturday
or a certain Sunday to allow for
		
00:01:12 --> 00:01:16
			the project to finish on time and
things of that sort? So the first
		
00:01:16 --> 00:01:20
			thing that we're going to do is
learn about calendars, and in
		
00:01:20 --> 00:01:23
			order to do that, we are going to
go to project
		
00:01:27 --> 00:01:31
			and we are going to go to Change
Working times.
		
00:01:34 --> 00:01:37
			So under Change Working time you
have, you can see here that we
		
00:01:37 --> 00:01:40
			have a calendar, a standard
calendar. I have gone already and
		
00:01:40 --> 00:01:45
			added a couple of non work days
and so on. So the calendar shows
		
00:01:45 --> 00:01:49
			that we have five work days per
week, Monday through Friday, and
		
00:01:49 --> 00:01:54
			then Saturday and Sunday are the
non work days or the weekend. Here
		
00:01:54 --> 00:01:56
			at the bottom, we have something
called exceptions. And here you
		
00:01:56 --> 00:01:59
			have the legend on the on the side
that shows what's a working day,
		
00:01:59 --> 00:02:03
			what's non working and so on. And
then here we have the exceptions,
		
00:02:03 --> 00:02:08
			if I want to designate a certain
day as an exception, so if it is a
		
00:02:08 --> 00:02:12
			working day and I want to make it
a non work day, or the opposite,
		
00:02:12 --> 00:02:15
			if it's a non work day and I want
to make it a working day. So for
		
00:02:15 --> 00:02:19
			example, here we have Independence
Day, the Fourth of July. I have
		
00:02:19 --> 00:02:24
			already added that, and the way to
do that is quite simple. Let's say
		
00:02:24 --> 00:02:26
			I want to designate
		
00:02:28 --> 00:02:31
			april 11 as a non work day.
		
00:02:33 --> 00:02:36
			So I'm going to go here, and I'm
going to call it
		
00:02:38 --> 00:02:39
			non work.
		
00:02:40 --> 00:02:44
			Of course, we have to give a
certain reason for that, and I'm
		
00:02:44 --> 00:02:46
			going to enter the date,
		
00:02:47 --> 00:02:52
			which is, in this case, april 11.
And now it has been designated as
		
00:02:52 --> 00:02:55
			a non work day. It's that simple,
		
00:02:56 --> 00:03:00
			if I go down, as you can see now,
it has been shaded so it shows
		
00:03:00 --> 00:03:03
			that this is a an exception day,
becoming a non work day.
		
00:03:04 --> 00:03:09
			The other way around is, if I want
to make a Saturday, for example, a
		
00:03:09 --> 00:03:12
			working day, I can do the same
thing here,
		
00:03:13 --> 00:03:15
			and I can call this
		
00:03:17 --> 00:03:17
			receiving
		
00:03:19 --> 00:03:20
			equipment,
		
00:03:21 --> 00:03:24
			if certain equipment is going to
arrive on site on that day, and I
		
00:03:24 --> 00:03:28
			need someone to be there to
receive that equipment. So now
		
00:03:28 --> 00:03:33
			that particular Saturday has been
designated as a work day, which is
		
00:03:33 --> 00:03:36
			the exception from being a non
work day.
		
00:03:41 --> 00:03:41
			Okay.
		
00:03:42 --> 00:03:46
			Now if I want to add a new
calendar, let's say for my
		
00:03:46 --> 00:03:50
			calendar right now is a five
workday per week. Let's say I want
		
00:03:50 --> 00:03:54
			to add another calendar, and I'm
going to call it I am going to
		
00:03:54 --> 00:03:55
			create a new calendar
		
00:03:57 --> 00:03:58
			and I'm going to call it six day.
		
00:04:01 --> 00:04:05
			Basically this calendar is going
to be a six working day per week,
		
00:04:05 --> 00:04:10
			and I'm going to make an exact
copy of my standard calendar.
		
00:04:10 --> 00:04:13
			Instead of adding all the holidays
and the non work days and so on,
		
00:04:13 --> 00:04:16
			I'm just going to make a copy, and
then I'm going to modify that as
		
00:04:16 --> 00:04:20
			well. So I'm going to go to, okay,
make a copy of standard Okay,
		
00:04:23 --> 00:04:28
			make changes? Yes, because we have
not closed standard. So now it has
		
00:04:28 --> 00:04:33
			created a new calendar called six
day. What I want to do now? I want
		
00:04:33 --> 00:04:37
			to designate Saturdays. All
Saturdays as being work days. So
		
00:04:37 --> 00:04:41
			let's say the site works six days
per week and the office works five
		
00:04:41 --> 00:04:45
			days a week. So any activity
related to the site, I'm going to
		
00:04:45 --> 00:04:48
			assign it to this calendar six
day, and any activity related to
		
00:04:48 --> 00:04:51
			the office or to certain other
trades outside, I'm going to
		
00:04:51 --> 00:04:56
			assign to the five work day. So
what I have to do now, instead of
		
00:04:56 --> 00:04:59
			going through every Saturday and
designating it as a next.
		
00:05:00 --> 00:05:03
			Option. There's another easier way
of doing that. I'm going to go to
		
00:05:03 --> 00:05:04
			work weeks,
		
00:05:06 --> 00:05:07
			and
		
00:05:08 --> 00:05:11
			I'm going to click here.
		
00:05:14 --> 00:05:16
			I'm going to click on options.
		
00:05:20 --> 00:05:25
			Now this shows here, the week
starts on Monday, and the times of
		
00:05:25 --> 00:05:28
			work and hours per week and so on
and so forth.
		
00:05:29 --> 00:05:32
			Now I'm going to go on Saturday.
Click on Saturday. I
		
00:05:43 --> 00:05:45
			and I'm going to click on details.
		
00:05:49 --> 00:05:53
			Now it shows the seven days of the
week. I'm going to click on
		
00:05:53 --> 00:05:53
			Saturday. So
		
00:05:55 --> 00:05:58
			this is going to apply from now on
to all Saturdays in this calendar.
		
00:05:58 --> 00:06:03
			And I'm going to click on Set days
to these specific working times, I
		
00:06:03 --> 00:06:06
			want to designate what is going to
be the working time on Saturdays.
		
00:06:06 --> 00:06:10
			So we're going to make it a
regular work day. So we're going
		
00:06:10 --> 00:06:11
			to start at 8am
		
00:06:18 --> 00:06:18
			two
		
00:06:20 --> 00:06:21
			is going to be
		
00:06:22 --> 00:06:22
			12.
		
00:06:28 --> 00:06:30
			Let's go back here, 8am
		
00:06:33 --> 00:06:34
			to
		
00:06:40 --> 00:06:41
			12. We're
		
00:06:42 --> 00:06:43
			going to make that PM,
		
00:06:46 --> 00:06:49
			and then after lunch, we're going
to start at 1pm
		
00:06:52 --> 00:06:53
			two,
		
00:06:56 --> 00:06:57
			5pm
		
00:07:01 --> 00:07:01
			and hit OK.
		
00:07:03 --> 00:07:08
			And now, as you can see, all
Saturdays became work days. So
		
00:07:08 --> 00:07:11
			this is the second thing that we
new thing that we've learned today
		
00:07:11 --> 00:07:14
			we learned so far about how to
modify an existing calendar, which
		
00:07:14 --> 00:07:19
			is the standard calendar, and then
how to add non work days, and how
		
00:07:19 --> 00:07:24
			to convert a non work day into a
working day. And then we learned
		
00:07:24 --> 00:07:27
			about how to add a new calendar,
the six work day calendar, and how
		
00:07:27 --> 00:07:28
			to
		
00:07:29 --> 00:07:34
			assign, basically Saturdays as a
working day. Now we're going to go
		
00:07:34 --> 00:07:35
			to OK,
		
00:07:39 --> 00:07:40
			and basically
		
00:07:42 --> 00:07:44
			I'll go now to task.
		
00:07:45 --> 00:07:49
			And what I want to do is assign
Calendar Number two, the six
		
00:07:49 --> 00:07:52
			workday calendar, to certain
activities. So whichever
		
00:07:52 --> 00:07:54
			activities are going to follow
that calendar, they have to be
		
00:07:54 --> 00:07:58
			assigned to that calendar. Let's
say I'm going to go to excavation
		
00:07:58 --> 00:07:59
			and site leveling.
		
00:08:01 --> 00:08:05
			This activity here, this task, and
I'm going to click on information,
		
00:08:08 --> 00:08:08
			and
		
00:08:10 --> 00:08:12
			if I go to Advanced,
		
00:08:15 --> 00:08:18
			it's going to show me calendar.
Which calendar is this activity
		
00:08:18 --> 00:08:21
			going to follow? I'm going to call
the six day calendar
		
00:08:24 --> 00:08:25
			and hit OK,
		
00:08:26 --> 00:08:31
			and now it's going to show here,
under the task indicators, that
		
00:08:31 --> 00:08:35
			this activity has been assigned to
the calendar six day. So the
		
00:08:35 --> 00:08:37
			calendar six days assigned to the
task.
		
00:08:41 --> 00:08:43
			Now that we've done that, we can
do that to other activities as
		
00:08:43 --> 00:08:48
			well and so on. So basically, this
is the end of the second lesson on
		
00:08:48 --> 00:08:55
			how to modify calendars and how to
assign different calendars to
		
00:08:55 --> 00:08:58
			different activities. Well, see
you next time in the next lesson.