Ihab Saad – MS Project Session 1 Adding and Linking activities

Ihab Saad
AI: Summary ©
The speaker introduces a video lecture on Microsoft Project, starting with a presentation of the software and then a demonstration of the tool. They explain how to add a new project, add activities, and schedule a project. The speaker also explains how to link activities and auto-schedule a new project, and how to summarize and edit the activities. The video lecture is then turned into a presentation of the tool.
AI: Transcript ©
00:00:01 --> 00:00:05

Music. Welcome to the first video lecture on Microsoft Project. In

00:00:05 --> 00:00:08

this lecture, we're going to be introduced to the software, and

00:00:08 --> 00:00:12

we're going to learn how to add a new project and how to add

00:00:12 --> 00:00:17

activities, link these activities, and how to indent and unindent

00:00:17 --> 00:00:20

activities, and how to schedule our first project.

00:00:21 --> 00:00:24

The first thing to do is, if you go to File

00:00:28 --> 00:00:33

New and click on New, is going to create a new project. And that

00:00:33 --> 00:00:37

way, you can create a new project and add it to your list. Once

00:00:37 --> 00:00:41

we're doing we've done that, we can go to the next tab, which is

00:00:41 --> 00:00:46

task. And as you can see, we have some common Microsoft shortcuts

00:00:46 --> 00:00:50

here, and buttons, Cut, Copy, Paste, format, painter, etc. So

00:00:50 --> 00:00:54

our first view is going to be the Gantt chart where we're going to

00:00:54 --> 00:00:59

enter the activities in both the tabular site, which is on the left

00:00:59 --> 00:01:03

hand side, and the graphic side, which also on the right hand side.

00:01:04 --> 00:01:08

First thing to do we're going to add a new task, and let's call

00:01:08 --> 00:01:10

this task notice to proceed.

00:01:15 --> 00:01:18

The next thing to do is to add the duration for this task. The

00:01:18 --> 00:01:23

duration is going to be set in days. You can add days by clicking

00:01:23 --> 00:01:23

on the up arrow

00:01:25 --> 00:01:30

or remove days by clicking on the down arrow. Let's say the notice

00:01:30 --> 00:01:32

to produce proceed is going to take one day.

00:01:33 --> 00:01:35

My next activity is going to be

00:01:37 --> 00:01:38

surveying

00:01:39 --> 00:01:41

and layout. And

00:01:44 --> 00:01:48

that's going to take three days. We can enter it by clicking on the

00:01:48 --> 00:01:48

keyboard.

00:01:50 --> 00:01:53

And the following activity is going to be mobilization

00:01:57 --> 00:01:58

and setup,

00:01:59 --> 00:02:03

to set up my site, and let's say this is going to take four days.

00:02:06 --> 00:02:09

As you can see, we have entered three activities so far. And you

00:02:09 --> 00:02:15

have here the timeline, the data date or the cutoff date, as of

00:02:15 --> 00:02:19

which I'm entering, my durations. I have here the activities that

00:02:19 --> 00:02:25

appear in these bars, but all the activities appear to be starting

00:02:25 --> 00:02:28

on the same day, which is not exactly what I'm looking forward

00:02:28 --> 00:02:32

to. So what I'm going to do now, I'm going to do two things. I'm

00:02:32 --> 00:02:33

going to click on

00:02:35 --> 00:02:39

link these activities. I'm going to highlight these activities

00:02:39 --> 00:02:45

first, like that, by clicking and pulling down on the mouse, and I'm

00:02:45 --> 00:02:47

going to click on auto schedule.

00:02:49 --> 00:02:51

So auto schedule is going to automatically calculate my

00:02:51 --> 00:02:55

schedule without me entering any dates for the activities. They're

00:02:55 --> 00:02:58

going to be automatically calculation calculated by the

00:02:58 --> 00:03:01

software. So the next step again, my activities appear to be

00:03:01 --> 00:03:04

starting on the same day. So the next thing to do is to link these

00:03:04 --> 00:03:08

activities, and that can be done very easily by clicking on this

00:03:08 --> 00:03:14

link here. Link tasks with the shortcut as Ctrl f2 if I click on

00:03:14 --> 00:03:17

this, it's going to assume a default relationship between the

00:03:17 --> 00:03:20

activities, which is a finish to start relationship.

00:03:21 --> 00:03:24

So now it shows that these activities are going to start as

00:03:25 --> 00:03:28

one activity is going to start as the predecessor has been

00:03:28 --> 00:03:31

completed. And it has automatically scheduled the

00:03:31 --> 00:03:35

durations and the calculated the schedule for this project so far,

00:03:37 --> 00:03:41

and it shows the predecessors as well. Now if I want to change any

00:03:41 --> 00:03:44

of these relationships. It's very simple. I can click on the arrow,

00:03:46 --> 00:03:50

and I can change that from finish to start, into any of the other

00:03:50 --> 00:03:56

relationships, start to start, for example. And I can add some lag

00:03:56 --> 00:03:59

and overlap. So positive is going to be lag,

00:04:01 --> 00:04:03

negative is going to be overlap.

00:04:04 --> 00:04:07

So let's put one day of lag,

00:04:09 --> 00:04:11

and we're going to hit okay.

00:04:12 --> 00:04:15

So now we choose the relationship as being start to start with one

00:04:15 --> 00:04:15

day of lag.

00:04:17 --> 00:04:21

My next step, we can add all the other activities from the

00:04:21 --> 00:04:25

spreadsheet that you have produced, or the word list that

00:04:25 --> 00:04:29

you have produced that shows all the activities in in the proper

00:04:29 --> 00:04:33

sequence, and so on. So now what we're going to do is we're going

00:04:33 --> 00:04:39

to add some other activities here. For example, I'm going to add a an

00:04:39 --> 00:04:40

activity called site work. I'm

00:04:44 --> 00:04:46

not going to enter a duration for this activity, for the time being,

00:04:46 --> 00:04:50

and we're going to see in a minute, why for the site work. I'm

00:04:50 --> 00:04:53

going to say the first step is going to be excavation

00:04:55 --> 00:04:58

and site doubling. I'm.

00:05:01 --> 00:05:04

Yeah, and this is going to take four days.

00:05:07 --> 00:05:09

The next step is going to be

00:05:10 --> 00:05:11

underground

00:05:14 --> 00:05:15

utilities.

00:05:17 --> 00:05:22

These include any water, sewage cables and so on. And let's say

00:05:22 --> 00:05:24

this is going to take five days.

00:05:27 --> 00:05:30

The next activity is going to be for work,

00:05:33 --> 00:05:33

for

00:05:34 --> 00:05:36

SOG slab on grade

00:05:37 --> 00:05:40

following. And that's going to take just one day

00:05:41 --> 00:05:44

following that is going to be rebar

00:05:45 --> 00:05:47

for slab on grade,

00:05:50 --> 00:05:55

and that's going to take three days. And finally, concrete

00:05:56 --> 00:06:00

for slab on grade, and that's going to take one day.

00:06:03 --> 00:06:06

So what we have done so far, we have added a series of activities.

00:06:07 --> 00:06:12

What I want to do is I want to change this task mode into auto

00:06:12 --> 00:06:13

schedule,

00:06:15 --> 00:06:17

instead of manually scheduled. That's the other option where I

00:06:17 --> 00:06:23

can enter dates manually. And then what I'm going to do, I'm going to

00:06:23 --> 00:06:25

select all of these activities here,

00:06:26 --> 00:06:30

and I'm going to indent them as all of these activities are parts

00:06:30 --> 00:06:35

of the site work. So I'm going to indent by clicking on this button.

00:06:36 --> 00:06:38

And now it has calculated

00:06:39 --> 00:06:42

site work as being five days, but that's assuming that all the

00:06:42 --> 00:06:46

activities are going to start at the same time. So the next thing

00:06:46 --> 00:06:49

to do is to link these activities,

00:06:53 --> 00:06:57

and the final thing is to link and now you can see that the site work

00:06:57 --> 00:07:02

is 14 days instead of just five. And now I can link mobilization

00:07:02 --> 00:07:04

and setup to site work.

00:07:06 --> 00:07:07

And there you have.

00:07:08 --> 00:07:13

The activities have been properly indented. I can collapse these

00:07:13 --> 00:07:17

activities to show only one activity for site work, like that.

00:07:18 --> 00:07:21

So now all the site work has been summarized into one activity, and

00:07:21 --> 00:07:27

I can collect I can expand it to show all the activities. This

00:07:27 --> 00:07:31

concludes our lesson number one, in which we have learned about how

00:07:31 --> 00:07:35

to add a new project, how to add activities to the project, how to

00:07:36 --> 00:07:40

automatically link the activities and how to auto schedule allow the

00:07:40 --> 00:07:44

software to calculate the dates by itself, how to create a group of

00:07:44 --> 00:07:49

activities and how to summarize them by indenting them, and then

00:07:49 --> 00:07:54

how to expand these activities and collapsing them depending on the

00:07:54 --> 00:07:55

view that we want to have.

00:07:57 --> 00:08:00

This is the end of Lesson number one. Now you can go ahead and add

00:08:00 --> 00:08:05

your activities in the software, and you can create a new project,

00:08:05 --> 00:08:09

and you can link these activities, and I'm going to be looking

00:08:09 --> 00:08:12

forward to seeing you for lesson number two. Thank you very much.

00:08:12 --> 00:08:12

Thank.

Share Page