Ihab Saad – MS Project Session 1 Adding and Linking activities

Ihab Saad
Share Page

AI: Summary ©

The speaker introduces a video lecture on Microsoft Project, starting with a presentation of the software and then a demonstration of the tool. They explain how to add a new project, add activities, and schedule a project. The speaker also explains how to link activities and auto-schedule a new project, and how to summarize and edit the activities. The video lecture is then turned into a presentation of the tool.

AI: Summary ©

00:00:01 --> 00:00:05
			Music. Welcome to the first video
lecture on Microsoft Project. In
		
00:00:05 --> 00:00:08
			this lecture, we're going to be
introduced to the software, and
		
00:00:08 --> 00:00:12
			we're going to learn how to add a
new project and how to add
		
00:00:12 --> 00:00:17
			activities, link these activities,
and how to indent and unindent
		
00:00:17 --> 00:00:20
			activities, and how to schedule
our first project.
		
00:00:21 --> 00:00:24
			The first thing to do is, if you
go to File
		
00:00:28 --> 00:00:33
			New and click on New, is going to
create a new project. And that
		
00:00:33 --> 00:00:37
			way, you can create a new project
and add it to your list. Once
		
00:00:37 --> 00:00:41
			we're doing we've done that, we
can go to the next tab, which is
		
00:00:41 --> 00:00:46
			task. And as you can see, we have
some common Microsoft shortcuts
		
00:00:46 --> 00:00:50
			here, and buttons, Cut, Copy,
Paste, format, painter, etc. So
		
00:00:50 --> 00:00:54
			our first view is going to be the
Gantt chart where we're going to
		
00:00:54 --> 00:00:59
			enter the activities in both the
tabular site, which is on the left
		
00:00:59 --> 00:01:03
			hand side, and the graphic side,
which also on the right hand side.
		
00:01:04 --> 00:01:08
			First thing to do we're going to
add a new task, and let's call
		
00:01:08 --> 00:01:10
			this task notice to proceed.
		
00:01:15 --> 00:01:18
			The next thing to do is to add the
duration for this task. The
		
00:01:18 --> 00:01:23
			duration is going to be set in
days. You can add days by clicking
		
00:01:23 --> 00:01:23
			on the up arrow
		
00:01:25 --> 00:01:30
			or remove days by clicking on the
down arrow. Let's say the notice
		
00:01:30 --> 00:01:32
			to produce proceed is going to
take one day.
		
00:01:33 --> 00:01:35
			My next activity is going to be
		
00:01:37 --> 00:01:38
			surveying
		
00:01:39 --> 00:01:41
			and layout. And
		
00:01:44 --> 00:01:48
			that's going to take three days.
We can enter it by clicking on the
		
00:01:48 --> 00:01:48
			keyboard.
		
00:01:50 --> 00:01:53
			And the following activity is
going to be mobilization
		
00:01:57 --> 00:01:58
			and setup,
		
00:01:59 --> 00:02:03
			to set up my site, and let's say
this is going to take four days.
		
00:02:06 --> 00:02:09
			As you can see, we have entered
three activities so far. And you
		
00:02:09 --> 00:02:15
			have here the timeline, the data
date or the cutoff date, as of
		
00:02:15 --> 00:02:19
			which I'm entering, my durations.
I have here the activities that
		
00:02:19 --> 00:02:25
			appear in these bars, but all the
activities appear to be starting
		
00:02:25 --> 00:02:28
			on the same day, which is not
exactly what I'm looking forward
		
00:02:28 --> 00:02:32
			to. So what I'm going to do now,
I'm going to do two things. I'm
		
00:02:32 --> 00:02:33
			going to click on
		
00:02:35 --> 00:02:39
			link these activities. I'm going
to highlight these activities
		
00:02:39 --> 00:02:45
			first, like that, by clicking and
pulling down on the mouse, and I'm
		
00:02:45 --> 00:02:47
			going to click on auto schedule.
		
00:02:49 --> 00:02:51
			So auto schedule is going to
automatically calculate my
		
00:02:51 --> 00:02:55
			schedule without me entering any
dates for the activities. They're
		
00:02:55 --> 00:02:58
			going to be automatically
calculation calculated by the
		
00:02:58 --> 00:03:01
			software. So the next step again,
my activities appear to be
		
00:03:01 --> 00:03:04
			starting on the same day. So the
next thing to do is to link these
		
00:03:04 --> 00:03:08
			activities, and that can be done
very easily by clicking on this
		
00:03:08 --> 00:03:14
			link here. Link tasks with the
shortcut as Ctrl f2 if I click on
		
00:03:14 --> 00:03:17
			this, it's going to assume a
default relationship between the
		
00:03:17 --> 00:03:20
			activities, which is a finish to
start relationship.
		
00:03:21 --> 00:03:24
			So now it shows that these
activities are going to start as
		
00:03:25 --> 00:03:28
			one activity is going to start as
the predecessor has been
		
00:03:28 --> 00:03:31
			completed. And it has
automatically scheduled the
		
00:03:31 --> 00:03:35
			durations and the calculated the
schedule for this project so far,
		
00:03:37 --> 00:03:41
			and it shows the predecessors as
well. Now if I want to change any
		
00:03:41 --> 00:03:44
			of these relationships. It's very
simple. I can click on the arrow,
		
00:03:46 --> 00:03:50
			and I can change that from finish
to start, into any of the other
		
00:03:50 --> 00:03:56
			relationships, start to start, for
example. And I can add some lag
		
00:03:56 --> 00:03:59
			and overlap. So positive is going
to be lag,
		
00:04:01 --> 00:04:03
			negative is going to be overlap.
		
00:04:04 --> 00:04:07
			So let's put one day of lag,
		
00:04:09 --> 00:04:11
			and we're going to hit okay.
		
00:04:12 --> 00:04:15
			So now we choose the relationship
as being start to start with one
		
00:04:15 --> 00:04:15
			day of lag.
		
00:04:17 --> 00:04:21
			My next step, we can add all the
other activities from the
		
00:04:21 --> 00:04:25
			spreadsheet that you have
produced, or the word list that
		
00:04:25 --> 00:04:29
			you have produced that shows all
the activities in in the proper
		
00:04:29 --> 00:04:33
			sequence, and so on. So now what
we're going to do is we're going
		
00:04:33 --> 00:04:39
			to add some other activities here.
For example, I'm going to add a an
		
00:04:39 --> 00:04:40
			activity called site work. I'm
		
00:04:44 --> 00:04:46
			not going to enter a duration for
this activity, for the time being,
		
00:04:46 --> 00:04:50
			and we're going to see in a
minute, why for the site work. I'm
		
00:04:50 --> 00:04:53
			going to say the first step is
going to be excavation
		
00:04:55 --> 00:04:58
			and site doubling. I'm.
		
00:05:01 --> 00:05:04
			Yeah, and this is going to take
four days.
		
00:05:07 --> 00:05:09
			The next step is going to be
		
00:05:10 --> 00:05:11
			underground
		
00:05:14 --> 00:05:15
			utilities.
		
00:05:17 --> 00:05:22
			These include any water, sewage
cables and so on. And let's say
		
00:05:22 --> 00:05:24
			this is going to take five days.
		
00:05:27 --> 00:05:30
			The next activity is going to be
for work,
		
00:05:33 --> 00:05:33
			for
		
00:05:34 --> 00:05:36
			SOG slab on grade
		
00:05:37 --> 00:05:40
			following. And that's going to
take just one day
		
00:05:41 --> 00:05:44
			following that is going to be
rebar
		
00:05:45 --> 00:05:47
			for slab on grade,
		
00:05:50 --> 00:05:55
			and that's going to take three
days. And finally, concrete
		
00:05:56 --> 00:06:00
			for slab on grade, and that's
going to take one day.
		
00:06:03 --> 00:06:06
			So what we have done so far, we
have added a series of activities.
		
00:06:07 --> 00:06:12
			What I want to do is I want to
change this task mode into auto
		
00:06:12 --> 00:06:13
			schedule,
		
00:06:15 --> 00:06:17
			instead of manually scheduled.
That's the other option where I
		
00:06:17 --> 00:06:23
			can enter dates manually. And then
what I'm going to do, I'm going to
		
00:06:23 --> 00:06:25
			select all of these activities
here,
		
00:06:26 --> 00:06:30
			and I'm going to indent them as
all of these activities are parts
		
00:06:30 --> 00:06:35
			of the site work. So I'm going to
indent by clicking on this button.
		
00:06:36 --> 00:06:38
			And now it has calculated
		
00:06:39 --> 00:06:42
			site work as being five days, but
that's assuming that all the
		
00:06:42 --> 00:06:46
			activities are going to start at
the same time. So the next thing
		
00:06:46 --> 00:06:49
			to do is to link these activities,
		
00:06:53 --> 00:06:57
			and the final thing is to link and
now you can see that the site work
		
00:06:57 --> 00:07:02
			is 14 days instead of just five.
And now I can link mobilization
		
00:07:02 --> 00:07:04
			and setup to site work.
		
00:07:06 --> 00:07:07
			And there you have.
		
00:07:08 --> 00:07:13
			The activities have been properly
indented. I can collapse these
		
00:07:13 --> 00:07:17
			activities to show only one
activity for site work, like that.
		
00:07:18 --> 00:07:21
			So now all the site work has been
summarized into one activity, and
		
00:07:21 --> 00:07:27
			I can collect I can expand it to
show all the activities. This
		
00:07:27 --> 00:07:31
			concludes our lesson number one,
in which we have learned about how
		
00:07:31 --> 00:07:35
			to add a new project, how to add
activities to the project, how to
		
00:07:36 --> 00:07:40
			automatically link the activities
and how to auto schedule allow the
		
00:07:40 --> 00:07:44
			software to calculate the dates by
itself, how to create a group of
		
00:07:44 --> 00:07:49
			activities and how to summarize
them by indenting them, and then
		
00:07:49 --> 00:07:54
			how to expand these activities and
collapsing them depending on the
		
00:07:54 --> 00:07:55
			view that we want to have.
		
00:07:57 --> 00:08:00
			This is the end of Lesson number
one. Now you can go ahead and add
		
00:08:00 --> 00:08:05
			your activities in the software,
and you can create a new project,
		
00:08:05 --> 00:08:09
			and you can link these activities,
and I'm going to be looking
		
00:08:09 --> 00:08:12
			forward to seeing you for lesson
number two. Thank you very much.
		
00:08:12 --> 00:08:12
			Thank.