Ihab Saad – Hydraulic Excavators

Ihab Saad
AI: Summary ©
The use of hydraulic excavators for various construction projects, including construction equipment, has been discussed. The factors affecting the production rate include weight, load factor, and pressure, as well as the use of a hydraulic casting machine and Trenching booms. The machine can dig deeper deeper deeper into deeper deeper soil and improve productivity. The importance of proper tool use and proper construction equipment use is emphasized.
AI: Transcript ©
00:00:06 --> 00:00:09

Welcome to another lecture in construction equipment, and today

00:00:09 --> 00:00:12

we're going to talk about hydraulic excavators. We're going

00:00:12 --> 00:00:15

to start talking about different types of equipment, their

00:00:15 --> 00:00:18

production rates, their cycle times, etc. We're going to have a

00:00:18 --> 00:00:22

few ideas about what are these equipment used for and how to

00:00:22 --> 00:00:26

maximize the efficiency of their use. So the first piece of

00:00:26 --> 00:00:29

equipment that we're going to start talking about is a set of

00:00:29 --> 00:00:32

types of equipment called hydraulic excavators, used

00:00:32 --> 00:00:34

primarily for excavation.

00:00:36 --> 00:00:40

So what are they? They're an excavator is a power driven

00:00:40 --> 00:00:45

digging machine, so the primary use is to dig or to excavate.

00:00:45 --> 00:00:50

Major types include hydraulic excavators, shovels, drag lines,

00:00:51 --> 00:00:56

hose or back hose and clam shells. All of these are considered under

00:00:56 --> 00:01:00

one major group of equipment called hydraulic excavators, A

00:01:03 --> 00:01:06

is other equipment, such as dozers, loaders and scrapers may

00:01:06 --> 00:01:10

also use, be used as excavators, although that's not the primary

00:01:10 --> 00:01:16

use of these equipment. So if we do not have any of the first type

00:01:16 --> 00:01:21

or first group, backhoes, shovels, clamshells, drag lights and so on.

00:01:22 --> 00:01:25

To a certain extent, we can use the bulldozers or the loaders or

00:01:25 --> 00:01:31

the scrapers in an A sub optimal use, just to excavate, although

00:01:31 --> 00:01:33

that's not their primary use, as I just mentioned.

00:01:36 --> 00:01:40

So here are some samples. Here we have a drag line.

00:01:41 --> 00:01:43

This is a backhoe.

00:01:44 --> 00:01:48

And this is a clamshell, as you can see, all of them are used for

00:01:48 --> 00:01:52

excavation for different types of soils, for different types of

00:01:52 --> 00:01:52

projects.

00:01:56 --> 00:01:59

Now we start, we need to start talking about the production of

00:01:59 --> 00:02:04

the excavator. How can we measure its production? The production of

00:02:04 --> 00:02:07

an excavator can be simply calculated from the equation,

00:02:08 --> 00:02:12

production per hour is equal to volume per cycle times cycles per

00:02:12 --> 00:02:16

hour. So depending on the volume that you can achieve per cycle,

00:02:16 --> 00:02:20

whether it's on the bucket or the drag line or the clamshell, its

00:02:20 --> 00:02:24

capacity times, how many cycles per hour? How many repetitive

00:02:24 --> 00:02:26

cycles can we achieve per hour?

00:02:28 --> 00:02:31

The volume per cycle depends on the rated bucket capacity and the

00:02:31 --> 00:02:37

bucket fill factor. So there are two major elements here. Rated

00:02:37 --> 00:02:41

bucket capacity, which is the size of the bucket and the bucket fill

00:02:41 --> 00:02:43

factor, how far can you fill it?

00:02:45 --> 00:02:50

And here we have a couple of tables that show, for different

00:02:50 --> 00:02:55

types of machines, what would be the rated bucket capacity, and for

00:02:55 --> 00:02:59

different types of materials, what would be the bucket fill factor.

00:02:59 --> 00:03:04

So for example, for a backhoe or shovel, that's cable,

00:03:06 --> 00:03:10

the rated bucket capacity is the struck volume. So if the bucket

00:03:10 --> 00:03:14

size is, let's say, two cubic yards, the struck volume means

00:03:14 --> 00:03:18

that there's no heap just at the surface of the bucket. That's the

00:03:18 --> 00:03:24

maximum capacity. And if it's a hydraulic backhoe or shovel, then

00:03:24 --> 00:03:28

the heaped volume at a one to one angle of repose. So there's going

00:03:28 --> 00:03:33

to be a heap on top of the rated capacity of the bucket, plus that,

00:03:33 --> 00:03:36

that heap, which is going to be something like a cone or a

00:03:36 --> 00:03:39

pyramid, at that angle of slope of one to one, which is the angle

00:03:39 --> 00:03:43

where the soil can support itself without without any additional

00:03:43 --> 00:03:47

support. For clam shells, it's going to be the plate line, or

00:03:47 --> 00:03:51

water line volume for the drag line, 90%

00:03:52 --> 00:03:54

of the struck volume, and we're going to see why. Because once you

00:03:54 --> 00:03:58

drag that bucket and you start lifting it, some soil is going to

00:03:58 --> 00:04:02

fall down. So that amount for about 10% of the volume of the

00:04:02 --> 00:04:08

bucket. And for a loader, which is a front loader, not a backhoe,

00:04:08 --> 00:04:13

front loader lifts from the front, is going to be a heap volume at

00:04:13 --> 00:04:18

two to one angle of repose. So with the hydraulic backhoe, is

00:04:18 --> 00:04:21

going to be one to one angle of repose. With the loader, it's

00:04:21 --> 00:04:25

going to be two to one angle of repose. Now, based on the material

00:04:25 --> 00:04:27

itself that we're going to carry inside that bucket,

00:04:28 --> 00:04:31

the more the finer the grain of that material, the more volume we

00:04:31 --> 00:04:35

can carry. Of course, the coarser the grain, the less volume. So we

00:04:35 --> 00:04:36

can see here, for example,

00:04:37 --> 00:04:43

for common earth or loan with very fine particles, the bucket fill

00:04:43 --> 00:04:46

factor is going to be anywhere between point eight to 1.1

00:04:48 --> 00:04:52

the capacity or the size of that bucket for sand or gravel is going

00:04:52 --> 00:04:57

to be anywhere between point nine and one for hard clay, point six,

00:04:57 --> 00:04:59

five to point nine, five is.

00:05:00 --> 00:05:02

For wet clay. Point five, 2.9

00:05:03 --> 00:05:06

for rock that's well blasted. Point seven, 2.9

00:05:07 --> 00:05:10

for rock that's poorly blasted is going to be much less than that.

00:05:10 --> 00:05:18

Point four, 2.7 because of the angular shape of these rock parts

00:05:18 --> 00:05:22

or parts of rock, and the amount of air that's going to be in

00:05:22 --> 00:05:25

between, because they're not going to be interlocking together in an

00:05:25 --> 00:05:26

efficient way.

00:05:28 --> 00:05:33

So let's look at an example. Here estimate the hourly production of

00:05:33 --> 00:05:38

a loader with a bucket heaped capacity of five cubic yards. The

00:05:38 --> 00:05:42

soil is sand, and the load factor, which is to convert from loose to

00:05:42 --> 00:05:47

bank volume that's going to take care of the swell, is point eight.

00:05:48 --> 00:05:54

The Cycle Time for the loader is one minute and 30 seconds, which

00:05:54 --> 00:05:59

is basically 90 seconds. And the job efficiency is 80% which means

00:05:59 --> 00:06:03

out of every hour we can use 80% which is 48 minutes.

00:06:04 --> 00:06:08

So to solve this problem, we need to get the number of cycles per

00:06:08 --> 00:06:11

hour times the bucket capacity.

00:06:14 --> 00:06:17

The bucket load is going to be equal to the fill factor times the

00:06:17 --> 00:06:24

bucket heat capacity, which is point nine times 4.5 here we have

00:06:26 --> 00:06:29

we're going to look at the table that's going to give us that point

00:06:29 --> 00:06:34

nine and the bucket heat capacity was five cubic yards, and that's

00:06:34 --> 00:06:37

going to be in loose cubic yards. Then to convert from loose cubic

00:06:37 --> 00:06:41

yards to bank cubic yards, we multiply by the load factor. So

00:06:41 --> 00:06:47

4.5 lose cubic yards times point eight gives us 3.6 bank cubic

00:06:47 --> 00:06:52

yards. So the capacity per cycle is 3.6 bank cubic yards. The next

00:06:52 --> 00:06:56

part is, how many cycles can we have per hour? Number of cycles

00:06:56 --> 00:07:02

per hour is 60 minutes divided by the cycle time in minutes, but we

00:07:02 --> 00:07:07

were given the cycle times in minutes, in seconds, which is 90

00:07:07 --> 00:07:11

seconds, or in minutes, which is 1.5 minutes. So 60 divided by 1.5

00:07:12 --> 00:07:16

gives 40 cycles per hour. However, that's assuming that we're working

00:07:16 --> 00:07:19

60 minutes per hour. We know that we're not going to be working 60

00:07:19 --> 00:07:23

minutes per hour, but only 48 so we have to multiply by the

00:07:23 --> 00:07:27

efficiency, which is point eight, and that gives us a total of 115.2

00:07:29 --> 00:07:34

bank cubic yards per hour. Now remember that this point nine came

00:07:34 --> 00:07:35

from

00:07:36 --> 00:07:42

a table like this. We were looking at Sand and Gravel. It's anywhere

00:07:42 --> 00:07:43

between point nine and 1.0

00:07:44 --> 00:07:46

and here we are told that,

00:07:51 --> 00:07:55

what type of soil do we have? The soil is sand, so that's why we use

00:07:55 --> 00:07:56

the point nine.

00:08:01 --> 00:08:06

Okay, so here's the the table that we used, which is the point nine

00:08:06 --> 00:08:11

to get that point nine here at the top. So the total production per

00:08:11 --> 00:08:17

hour is going to be 115 bank cubic yards per hour. If the question

00:08:17 --> 00:08:21

was to calculate that hourly production in loose cubic yards.

00:08:22 --> 00:08:26

We wouldn't have to multiply by the load factor in this case, so

00:08:26 --> 00:08:28

it's going to be 4.5

00:08:29 --> 00:08:31

loose cubic yards instead of 3.6

00:08:32 --> 00:08:36

times 40 cycles, times point eight. And that would give a

00:08:36 --> 00:08:39

different number that's going to be in loose cubic yards per hour.

00:08:40 --> 00:08:43

So always make sure what the question is asking about. Is it

00:08:43 --> 00:08:47

asking about bank cubic yards or loose cubic yards

00:08:50 --> 00:08:54

for the hydraulic excavators, also, we have something called a

00:08:54 --> 00:08:58

hydraulic hoe or hydraulic excavator backhoe, depending on

00:08:58 --> 00:09:02

whether the bucket is lifting forward, or is it lifting

00:09:02 --> 00:09:02

backward?

00:09:04 --> 00:09:08

It digs by pulling the dipper back towards the machine. If it's a

00:09:08 --> 00:09:08

backhoe,

00:09:10 --> 00:09:14

when the dipper is filled, it's curled, curled up to reduce the

00:09:14 --> 00:09:18

spillage so that it can maintain the maximum volume of soil inside

00:09:18 --> 00:09:21

that bucket. And here's the example. This is the dipper or the

00:09:21 --> 00:09:27

bucket. So you extend the arm you dig, and then you drag the arm

00:09:27 --> 00:09:30

backwards and lift the bucket to maintain the soil in the bucket.

00:09:32 --> 00:09:35

This, of course, is hydraulically driven. So all of these are

00:09:35 --> 00:09:37

hydraulic pumps

00:09:39 --> 00:09:39

or cylinders. So

00:09:43 --> 00:09:46

what is it used for? It's used for trenching work, if you want to dig

00:09:46 --> 00:09:50

a trench, and the best production is going to be if the trench has

00:09:50 --> 00:09:55

the same width as the width of the bucket itself. It can also lay

00:09:55 --> 00:09:59

pipes, pull trench shields or sheet piles and backfill.

00:10:00 --> 00:10:03

The Trench by placing the soil back after laying the pipes,

00:10:05 --> 00:10:08

the dipping width of the bucket should match the trench width to

00:10:08 --> 00:10:09

maximize the production.

00:10:10 --> 00:10:14

We can also have telescoping booms, which are going to replace

00:10:14 --> 00:10:17

the articulated booms. In the previous picture, we had an

00:10:17 --> 00:10:21

articulated boom. But you can also have telescoping booms that can

00:10:21 --> 00:10:23

extend hydraulically as well.

00:10:26 --> 00:10:29

The production rate for that excavator is going to be the

00:10:29 --> 00:10:33

generic equation is going to be production in loose cubic yards

00:10:33 --> 00:10:36

per hour. Notice now, now that this is in loose cubic yards per

00:10:36 --> 00:10:43

hour is equal to C times s times v, times b, times E. Let's learn

00:10:43 --> 00:10:45

about each one of these symbols.

00:10:46 --> 00:10:50

C is the number of cycles per hour. Basically, the production is

00:10:50 --> 00:10:54

going to be volume per cycle times number of cycles per hour. This is

00:10:54 --> 00:10:57

the in a nutshell, how we calculate the production. But what

00:10:57 --> 00:11:01

are the details? Now the C is the number of cycles per hour.

00:11:02 --> 00:11:06

S is the swing depth factor. We're going to see that in a table in

00:11:06 --> 00:11:12

just a second. V is the heat bucket volume. B is the bucket

00:11:12 --> 00:11:17

fill factor, which would vary from one type of soil to another. And E

00:11:17 --> 00:11:21

is the job efficiency. How many minutes can we work per hour? If

00:11:21 --> 00:11:26

that efficiency is 80% then it's 48 minutes. If it's 75% that is 45

00:11:26 --> 00:11:29

minutes and so on. How do we get the number of minutes by

00:11:29 --> 00:11:35

multiplying that factor times 60. So 80% is 80 times 60, which gives

00:11:35 --> 00:11:39

48 minutes. 75% 75.75

00:11:41 --> 00:11:44

times 60, which gives the 45 minutes.

00:11:47 --> 00:11:50

So the effect of job conditions. Now this is something that you as

00:11:50 --> 00:11:55

a project manager can control on site to improve the production

00:11:55 --> 00:12:02

rate of that equipment. So we have different job conditions, varying

00:12:02 --> 00:12:07

from accident to severe, which is extremely poor, depending on the

00:12:07 --> 00:12:12

backhoe bucket side size, we can estimate the cycle time.

00:12:14 --> 00:12:19

So under excellent conditions, let's say we have a two cubic yard

00:12:19 --> 00:12:23

bucket. The two cubic yards going to be somewhere in between these

00:12:23 --> 00:12:26

two. So under excellent conditions, the cycle time is

00:12:26 --> 00:12:31

going to be anywhere between 15 to 16 seconds. So 15 and a half would

00:12:31 --> 00:12:35

be fine. 15 would be fine. 16 would be fine. Above Average,

00:12:35 --> 00:12:39

which is not excellent. A little bit longer it's going to take 17

00:12:39 --> 00:12:43

instead of 15 seconds, severe, that's the worst type of

00:12:43 --> 00:12:47

conditions. Is going to take 25 seconds instead of 15 Now imagine

00:12:47 --> 00:12:51

if every cycle is extended by 10 seconds. That means that you're

00:12:51 --> 00:12:55

going to have a total reduced number of cycles per hour, which

00:12:55 --> 00:12:58

is going to reduce the total production rate. Here is an

00:12:58 --> 00:13:02

example of what do we mean by excellent and and so on. So

00:13:02 --> 00:13:05

excellent conditions are characterized as easy digging,

00:13:06 --> 00:13:11

unpacked Earth, including sand ditch cleaning, etc, some loose

00:13:11 --> 00:13:16

soil digging to less than 40% of the machines maximum digging

00:13:16 --> 00:13:20

depth. So again, you're not going to extend the boom to the ex to

00:13:20 --> 00:13:27

the maximum swing angles less than 30% when you swing the piece of

00:13:27 --> 00:13:31

equipment to dump the soil into a truck or somewhere else,

00:13:32 --> 00:13:38

dump into a soil spoiled pile, so not into a truck, for example,

00:13:38 --> 00:13:40

because if you're dumping into a truck, you have To adjust to make

00:13:40 --> 00:13:45

sure that your your topic exactly in the in a proper location. But

00:13:45 --> 00:13:49

if you're dumping into spoiled pile, you have more latitude, no

00:13:49 --> 00:13:53

obstruction, so there's no fence, and you can see clearly the area

00:13:53 --> 00:13:56

where you're going to be dumping. The soil that would be excellent

00:13:56 --> 00:14:00

conditions. With any change of these conditions, it's going to

00:14:00 --> 00:14:06

reduce the the the efficiency and increase the cycle time above

00:14:06 --> 00:14:09

average. Conditions are characterized as medium digging.

00:14:09 --> 00:14:14

Here it was easy. Now it's medium, packed Earth, dry clay, soiled

00:14:14 --> 00:14:19

with less than 25% truck content. The depth also, instead of being

00:14:19 --> 00:14:24

only 40% of the maximum being depth. Now it's 50, up to 50% of

00:14:24 --> 00:14:25

the maximum big depth.

00:14:26 --> 00:14:29

The angle the swing ended here was only 30% here it has increased to

00:14:29 --> 00:14:30

60%

00:14:31 --> 00:14:35

large dump target and a few obstructions. So that's going to

00:14:35 --> 00:14:39

increase the cycle time and reduce production rate and so on. You can

00:14:39 --> 00:14:45

see, with the average, we're gonna have hard packed soil that 70% is

00:14:45 --> 00:14:50

instead of 50 swing angle 90 degrees, instead of 30 or 60 and

00:14:50 --> 00:14:54

so on, under severe conditions characterized as tough digging,

00:14:54 --> 00:14:59

sandstone, shale, limestone, hard thrust, depth over 90%

00:20:00 --> 00:20:04

Is going to affect the cycle time with a factor so if the angle of

00:20:04 --> 00:20:05

swing,

00:20:06 --> 00:20:08

and if the optimum depth is 40%

00:20:09 --> 00:20:15

of the maximum, and the swing angle is 90 degrees, then that's

00:20:15 --> 00:20:18

going to have a factor of point eight. It's going to reduce your

00:20:18 --> 00:20:22

production rate by a factor of point eight. If the angle is is 45

00:20:22 --> 00:20:27

degrees, the reduction is going to be only 7% this is a reduction of

00:20:27 --> 00:20:29

20% this is only 7%

00:20:30 --> 00:20:32

if the maximum depth,

00:20:33 --> 00:20:34

if the optimum depth, is 160%

00:20:37 --> 00:20:39

as you can see, we're going to have here

00:20:40 --> 00:20:41

different production rates

00:20:43 --> 00:20:47

on the job conditions, which is, which is, again, something that

00:20:47 --> 00:20:50

you can control, like, for example, cleaning the site, having

00:20:50 --> 00:20:54

no obstacles, having a clear line of sight or line of view for the

00:20:54 --> 00:20:59

operator, having the equipment close to the to to your Excavator

00:20:59 --> 00:21:04

or your your shovel, so that to minimize any travel time. So if

00:21:04 --> 00:21:07

it's excellent, you get point eight, 4%

00:21:08 --> 00:21:11

if it's poor, you get point seven, 2%

00:21:12 --> 00:21:15

and so on. So these are the job conditions, and these are the

00:21:15 --> 00:21:19

management conditions. The management conditions, again,

00:21:19 --> 00:21:22

these are, these are something that you can control as a project

00:21:22 --> 00:21:22

manager. Let's

00:21:23 --> 00:21:27

look at an example again. To make things much clearer, a contractor

00:21:27 --> 00:21:32

has a project to excavate an apartment complex and must

00:21:32 --> 00:21:37

construct a three foot compacted fill to support a parking garage.

00:21:37 --> 00:21:42

The borrow site where you're going to get your soil is three miles

00:21:42 --> 00:21:44

from the construction site.

00:21:45 --> 00:21:50

A 10 cubic yard dump truck will be used, and 10 cubic yard dump

00:21:50 --> 00:21:52

trucks will be used to haul the needed fill.

00:21:54 --> 00:21:58

A two cubic yard shovel would be used to load the dump trucks. So

00:21:58 --> 00:22:02

how many cycles is it going to take for the shovel to fill the

00:22:02 --> 00:22:05

truck. This is two cubic yards. This is 10 cubic yards. We're

00:22:05 --> 00:22:07

talking about five cycles to fill one truck.

00:22:08 --> 00:22:13

The material is tough, dry clay with a swell of 35%

00:22:15 --> 00:22:19

the height of the cut at the bottom side is 11.6 feet, and the

00:22:19 --> 00:22:23

angle of swing of the shovel is 150 degrees. That's quite large.

00:22:25 --> 00:22:28

Estimate the ideal production using the table and estimate the

00:22:28 --> 00:22:33

actual production for good job and management conditions. The optimum

00:22:33 --> 00:22:38

digging depth of the soil of the shovel is 9.8 feet. Optimum

00:22:38 --> 00:22:44

digging depth is 9.8 feet, and the actual depth of cut is going to be

00:22:44 --> 00:22:46

11.6 feet.

00:22:49 --> 00:22:52

So the ideal production from the table is 265,

00:22:53 --> 00:22:55

band cubic yards per hour.

00:22:56 --> 00:22:58

Let's see. Look at that table.

00:23:01 --> 00:23:07

So we have two cubic yards bucket and we have tough clay. Therefore

00:23:08 --> 00:23:11

the ideal production rate is going to be 265

00:23:12 --> 00:23:14

bank cubic yards per hour.

00:23:15 --> 00:23:16

The fill factor

00:23:18 --> 00:23:23

is for that tough clay, as we have seen before, in the table, is 1.05

00:23:24 --> 00:23:25

that's an average

00:23:27 --> 00:23:29

the cycle time for

00:23:30 --> 00:23:31

the

00:23:32 --> 00:23:39

average job conditions for two cubic yards, which is going to be

00:23:39 --> 00:23:41

somewhere between one to two and two to three. We're going to take

00:23:41 --> 00:23:45

the average of the two. So between 20 seconds and 22 seconds, we

00:23:45 --> 00:23:49

selected 21 seconds, which is average. Therefore the production

00:23:49 --> 00:23:53

is going to be equal to the bucket capacity times the field factor

00:23:55 --> 00:24:00

divided by the ideal cycle time. The Bucket capacity two cubic

00:24:00 --> 00:24:04

yards, the feed factor 1.05 depending on the type of soil,

00:24:05 --> 00:24:12

and divided by the cycle time, which is 21 seconds that we

00:24:12 --> 00:24:13

obtained from here.

00:24:14 --> 00:24:22

And we basically 21 divided by 33 3600 to convert from seconds to

00:24:22 --> 00:24:25

hours. So we put the 3600 above here,

00:24:27 --> 00:24:29

divided also by the

00:24:30 --> 00:24:36

load factor to convert from loose to bank cubic yards, based on the

00:24:37 --> 00:24:48

swell factor that we already had, which is 35% so the percent of

00:24:48 --> 00:24:54

optimum depth for this excavating operation is now we have the

00:24:54 --> 00:24:59

optimum is 9.8 the actual is 11.8 so that's equivalent to 120% of

00:24:59 --> 00:24:59

the optimum.

00:30:01 --> 00:30:04

Are capable of digging at higher depth. So you can,

00:30:06 --> 00:30:10

you can descend it into a well, for example, or a shaft, and you

00:30:10 --> 00:30:12

can grab the soil and lift it vertically.

00:30:15 --> 00:30:19

It lacks positive digging action and lateral control of the shovel

00:30:19 --> 00:30:23

or backhoe. So the backhoe and the shovel are much better for lateral

00:30:23 --> 00:30:27

control and positive digging action, which means hitting with a

00:30:27 --> 00:30:32

certain force. This relies primarily on the weight of the

00:30:32 --> 00:30:33

clamshell itself,

00:30:35 --> 00:30:40

used for excavating vertical shafts and footings. So again,

00:30:40 --> 00:30:45

same machine as we had with the drag line. The only difference

00:30:45 --> 00:30:48

here is that we're going to drop this vertically, which is the clam

00:30:48 --> 00:30:52

shell, and it's going to grab the soil. You're going to lift it,

00:30:52 --> 00:30:55

turn and dump it wherever you need to.

00:30:58 --> 00:31:02

And that's, again, is a magnified view of the clamshell itself.

00:31:05 --> 00:31:07

Here it shows that it can

00:31:08 --> 00:31:12

dig, especially in marine conditions and in wet conditions,

00:31:12 --> 00:31:14

a clamshell would be a very good

00:31:15 --> 00:31:16

machine to use.

00:31:19 --> 00:31:22

Production is based on the equation, again, same generic

00:31:22 --> 00:31:25

equation, volume per cycle, time, cycles per hour.

00:31:26 --> 00:31:31

The maximum load should be limited to 80% of safe lifting capacity

00:31:32 --> 00:31:36

for rubber tired equipment and 90% for crawler mounted equipment.

00:31:36 --> 00:31:39

Just because of issues of stability of the equipment itself,

00:31:39 --> 00:31:41

we don't want it to again, tip over.

00:31:45 --> 00:31:48

Other factors to improve the production rate for the clam shell

00:31:48 --> 00:31:53

include having the dumping radius same as the digging radius. So

00:31:53 --> 00:31:57

again, you're not going to move the clamshell along the boom.

00:31:57 --> 00:32:03

You're gonna lift the soil, turn and dump the soil in a truck or a

00:32:03 --> 00:32:08

soil pile, kicking, keeping the machine level to avoid swinging

00:32:08 --> 00:32:12

uphill or downhill, which is going to affect issues of stability and

00:32:12 --> 00:32:14

issues of production rate as well.

00:32:16 --> 00:32:21

So based on the angle of swing, as you can see, if it's a 90 degree,

00:32:21 --> 00:32:22

that's going to give you the optimum

00:32:24 --> 00:32:28

swing. If it's less than that, it's going to increase the

00:32:28 --> 00:32:32

production rate because of a shorter swing cycle.

00:32:36 --> 00:32:40

And again, similar to what we have seen before, depending on

00:32:41 --> 00:32:44

the ideal production rate is going to depend on the bucket size and

00:32:44 --> 00:32:46

the type of soil that you are digging.

00:32:50 --> 00:32:53

So let's look at an example one more time, a contractor has

00:32:53 --> 00:32:57

decided to use a two cubic yard clamshell mounted on a crawler

00:32:57 --> 00:33:01

crane to excavate for the foundations of three concrete

00:33:01 --> 00:33:06

piers for a highway bridge. The excavated material will be dumped

00:33:06 --> 00:33:10

in stockpiles for later use in backfilling. The material is

00:33:10 --> 00:33:14

common earth, and the average angle of swing is 120, degrees.

00:33:15 --> 00:33:19

Job and management conditions are good. What's the estimated

00:33:19 --> 00:33:23

productivity of the clamshell in bank cubic yards per hour.

00:33:26 --> 00:33:30

So the estimated ideal productivity for a two cubic yard,

00:33:31 --> 00:33:35

two cubic yard for Common Earth is 160

00:33:37 --> 00:33:38

bank cubic yards per hour.

00:33:40 --> 00:33:45

The angle of swing for is 120 degrees. So the correction factor

00:33:45 --> 00:33:48

for the angle of swing is point nine, one,

00:33:50 --> 00:33:55

and the good job and management conditions from the previous

00:33:55 --> 00:33:59

tables is point seven, five. Therefore the production rate is

00:33:59 --> 00:34:03

going to be 160 band cubic yards per hour times point nine, one

00:34:04 --> 00:34:09

times point seven, five, and that gives 109 bank cubic yards per

00:34:09 --> 00:34:09

hour.

00:34:14 --> 00:34:15

So

00:34:16 --> 00:34:19

in this lecture, we have learned about what are the different types

00:34:19 --> 00:34:19

of

00:34:21 --> 00:34:25

excavation equipment, earth moving equipment for excavation,

00:34:25 --> 00:34:29

primarily, we talked about the shovel, the backhoe, the dragline

00:34:29 --> 00:34:32

and the clamshell. We looked at the different factors affecting

00:34:32 --> 00:34:35

their production rate, and how many of these factors can be

00:34:35 --> 00:34:39

controlled by the project manager, by improving the site layout and

00:34:39 --> 00:34:42

improving the location of the equipment and the dumping

00:34:42 --> 00:34:46

equipment and so on and so forth. So all of this is within your

00:34:46 --> 00:34:46

control,

00:34:48 --> 00:34:51

and I'll be glad to answer any questions related to that in

00:34:51 --> 00:34:56

class. Well, thank you and see you next time in another lecture. You.

Share Page