Ihab Saad – Excavators

Ihab Saad
Share Page

AI: Summary ©

The efficiency of a hydraulic excavator is discussed, using a table to estimate the output and using booms to extend the excavator's reach. The machine uses a crane to hold dirt in the bucket and prevent spillage, while also using a dipper to hold dirt in the bucket and prevent it from getting out of the soil. The speakers discuss proper construction practices, maneuvering, and optimal productivity, as well as factors affecting productivity and cycle times. The cost of construction is estimated and productivity is estimated at around 180,000 cubic yards per hour.

AI: Summary ©

00:05:00 --> 00:05:04
			Five, 2.95 it's going to be lumped
into larger particles. For wet
		
00:05:04 --> 00:05:07
			clay, it's going to be anywhere
between point five and point nine.
		
00:05:08 --> 00:05:11
			Rock well blasted, relatively
graded, is going to be point
		
00:05:11 --> 00:05:12
			seven, 2.9
		
00:05:13 --> 00:05:17
			and rock poorly blasted is going
to be point four to point seven.
		
00:05:17 --> 00:05:21
			So we're going to use only about
half of the capacity of that
		
00:05:21 --> 00:05:22
			bucket.
		
00:05:25 --> 00:05:28
			Here we have an example estimate
the hourly production for a loader
		
00:05:28 --> 00:05:33
			with the bucket heaped capacity of
five cubic yards. The soil is sand
		
00:05:33 --> 00:05:37
			and the load factor. And the load
factor is basically to convert
		
00:05:37 --> 00:05:41
			from loose to bank volume, because
that soil filling the scoop or
		
00:05:41 --> 00:05:45
			filling the bucket is going to be
in its loose condition. So if we
		
00:05:45 --> 00:05:48
			want to convert it and get the
production in bank, cubic yards
		
00:05:48 --> 00:05:52
			per hour, we need to convert to
bank volume. That load factor is
		
00:05:52 --> 00:05:56
			point eight. The Cycle Time for
the loader is one minute and 30
		
00:05:56 --> 00:06:02
			seconds, which is 90 seconds, and
the job efficiency is 80% so let's
		
00:06:02 --> 00:06:05
			see how we're going to solve this.
First of all, the bucket load is
		
00:06:05 --> 00:06:08
			going to be equal to the fill
factor times the bucket heat
		
00:06:08 --> 00:06:13
			capacity. The fill factor for that
type of soil based on this
		
00:06:15 --> 00:06:19
			equation at this table here, we
mentioned that it's going to be
		
00:06:20 --> 00:06:25
			sand. So for sand is going to be
around point nine to 1.0 we can
		
00:06:25 --> 00:06:30
			choose either one or any range in
between an average. So we're going
		
00:06:30 --> 00:06:33
			to take, in this case, point nine
times the bucket capacity, which
		
00:06:33 --> 00:06:37
			is five, which means we're going
to have soil volume inside the
		
00:06:37 --> 00:06:42
			bucket of 4.5 loose cubic yards.
Then we need to convert these
		
00:06:42 --> 00:06:46
			loose cubic yards into bank cubic
yards. So we're going to multiply
		
00:06:46 --> 00:06:49
			by the load factor. So that's
going to reduce the volume.
		
00:06:49 --> 00:06:55
			Therefore each bucket is going to
carry 3.6 bank cubic yards for
		
00:06:55 --> 00:06:59
			each cycle. Number of cycles per
hour is going to be one hour,
		
00:06:59 --> 00:07:03
			which is 60 minutes divided by the
cycle time. Now the cycle time was
		
00:07:03 --> 00:07:07
			given into minutes and seconds, so
we need to make sure that we are
		
00:07:07 --> 00:07:12
			using the same unit, so 60 divided
by one and a half, which is going
		
00:07:12 --> 00:07:16
			to give us 40 cycles per hour.
That is with the assumption that
		
00:07:16 --> 00:07:20
			we're going to use 60 minutes per
hour as production. But this is
		
00:07:20 --> 00:07:23
			not always true. We're going to
have to look at the efficiency.
		
00:07:23 --> 00:07:28
			The efficiency was given to us as
point eight or 80% therefore the
		
00:07:28 --> 00:07:32
			volume, the total Audi production,
is going to be the volume per
		
00:07:32 --> 00:07:36
			cycle, times the number, number of
cycles per hour, times the
		
00:07:36 --> 00:07:39
			efficiency. And that gives the
total production of 115.2
		
00:07:40 --> 00:07:42
			bank cubic yards per hour.
		
00:07:46 --> 00:07:50
			Again, here's the table that we
use to get the factor for the
		
00:07:50 --> 00:07:51
			sand.
		
00:07:54 --> 00:07:58
			The hydraulic excavator, also
called hydraulic hoe or hydraulic
		
00:07:58 --> 00:08:01
			excavator backhoe, depending on
the way the bucket is facing if
		
00:08:01 --> 00:08:05
			it's facing forward, it's a hoe or
a shovel. If it's facing backward,
		
00:08:05 --> 00:08:09
			it's a backhoe. It digs by pulling
the dipper back towards the
		
00:08:09 --> 00:08:12
			machine. So there's going to be a
hydraulic force
		
00:08:13 --> 00:08:19
			pushing that bucket into the soil
and then pulling it to get out of
		
00:08:19 --> 00:08:22
			the soil, with a breakout force to
take the soil and to be scooped
		
00:08:22 --> 00:08:27
			away. When the dipper is filled,
it's curled up to reduce the
		
00:08:27 --> 00:08:30
			spinach through the hydraulic arm
of the equipment,
		
00:08:31 --> 00:08:34
			and that's basically what it looks
like. So here's the articulated
		
00:08:34 --> 00:08:35
			hydraulic arm
		
00:08:37 --> 00:08:41
			with pistons, and here's the
digger or the bucket or the
		
00:08:41 --> 00:08:47
			dipper, so it has some teeth at
the edge to help loosen and break
		
00:08:47 --> 00:08:51
			the soil. And once it's full, it's
going to be tilted upwards to
		
00:08:51 --> 00:08:53
			avoid or to reduce the spillage.
		
00:08:57 --> 00:09:02
			It's used for trenching work, as
it can also lay pipes, pull trench
		
00:09:02 --> 00:09:06
			shields or sheet piles, and
backfill the trench. After the
		
00:09:06 --> 00:09:08
			operation of laying the pipe is
complete,
		
00:09:09 --> 00:09:13
			the dipping width of the bucket
should match the trench width to
		
00:09:13 --> 00:09:17
			maximize production. So if we're
going to use, for example, a
		
00:09:18 --> 00:09:22
			the width of the bucket is three
feet, then the the width of the
		
00:09:22 --> 00:09:26
			trench should be around that these
buckets are movable. We can
		
00:09:26 --> 00:09:29
			exchange these buckets and change
the bucket size depending on the
		
00:09:29 --> 00:09:32
			operation that we're going to be
using it for.
		
00:09:33 --> 00:09:36
			Telescoping booms may replace
articulated booms. So instead of
		
00:09:36 --> 00:09:40
			the articulation, we may have
telescoping booms to extend the
		
00:09:40 --> 00:09:43
			reach of that of that hydraulic
excavator,
		
00:09:45 --> 00:09:47
			the generic equation for
estimating the excavator
		
00:09:47 --> 00:09:51
			production is going to be pretty
much the same thing, by the way,
		
00:09:51 --> 00:09:54
			which is number of cycles per hour
times the volume per cycle. But
		
00:09:54 --> 00:09:57
			here we are basically
		
00:09:58 --> 00:09:59
			adding some other factors.
		
00:10:00 --> 00:10:05
			That affect the production rate.
So it's equal to c times s times v
		
00:10:05 --> 00:10:11
			times B times e. Let's look at
what each one of these means. C is
		
00:10:11 --> 00:10:16
			the number of cycles per hour. S
is the swing depth factor. Now
		
00:10:16 --> 00:10:21
			imagine the cycle is going to
include digging, swinging,
		
00:10:21 --> 00:10:25
			dumping, swinging again and
starting to dig. The wider that
		
00:10:25 --> 00:10:29
			angle of swing, the slower the
operation is going to be, because
		
00:10:29 --> 00:10:32
			you have to move farther distance.
Therefore, if that angle of swing
		
00:10:32 --> 00:10:36
			is relatively narrow, that's going
to expedite the excavation, which
		
00:10:36 --> 00:10:40
			means reducing the cycle time,
which means more cycles per hour,
		
00:10:40 --> 00:10:42
			which means more production per
hour.
		
00:10:43 --> 00:10:48
			V is the heaped bucket volume. B
is the bucket fill factor, which
		
00:10:48 --> 00:10:51
			we have seen depending on the type
of soil. And E is the job
		
00:10:51 --> 00:10:55
			efficiency, which is how many
productive minutes per hour can
		
00:10:55 --> 00:10:57
			you get out of this piece of
equipment?
		
00:11:01 --> 00:11:06
			We have some effect from the job
conditions. Depending on the job
		
00:11:06 --> 00:11:09
			conditions, we can have either
excellent job conditions, above
		
00:11:09 --> 00:11:13
			average, average, below average
and severe. And for different
		
00:11:13 --> 00:11:19
			sizes of buckets, we can have
estimated cycle times. So for
		
00:11:19 --> 00:11:22
			example, the excellent conditions
are characterized as easy digging.
		
00:11:22 --> 00:11:27
			We're digging through easy soil to
break into unpacked Earth, sand,
		
00:11:27 --> 00:11:32
			ditch, cleaning, etc, digging to
less than 40% of the machines
		
00:11:32 --> 00:11:37
			maximum digging depth. So the arm
is not going to be extended to the
		
00:11:37 --> 00:11:37
			maximum.
		
00:11:38 --> 00:11:42
			And the swing angle is less than
30 degrees. Again, the amount of
		
00:11:42 --> 00:11:46
			swing is relatively limited. You
dump into a spoil pile, so you
		
00:11:46 --> 00:11:51
			don't have to maneuver and to
adjust to dump into a truck, no
		
00:11:51 --> 00:11:54
			obstructions. You can see the
dumping area. You can see the
		
00:11:54 --> 00:11:59
			digging area. So that's going to
be excellent conditions for a less
		
00:11:59 --> 00:12:03
			than a one cubic yard bucket, the
cycle time is going to be about 13
		
00:12:03 --> 00:12:08
			seconds. One to two cubic yard
buckets going to be about 15. Two
		
00:12:08 --> 00:12:11
			to three cubic yards, it's going
to be 16 and so on. The larger the
		
00:12:11 --> 00:12:15
			bucket, of course, the longer the
cycle time.
		
00:12:18 --> 00:12:21
			Above average conditions are
characterized as medium digging.
		
00:12:21 --> 00:12:25
			Now it's not as easy as the
previous one, but packed Earth,
		
00:12:25 --> 00:12:29
			relatively more consolidated and
compacted, dry clay soil was less
		
00:12:29 --> 00:12:35
			than 25% rock content. Now the
depth, instead of being 40% is
		
00:12:35 --> 00:12:40
			going to increase to about 50% so
more reaching out with the arm and
		
00:12:40 --> 00:12:45
			the swing angles less than 60
degrees. So still here, in the
		
00:12:45 --> 00:12:49
			first case, we have 30 degrees.
Now we have about 60 degrees. It's
		
00:12:49 --> 00:12:53
			still large dump target, so it
could be a large truck or an open
		
00:12:53 --> 00:12:58
			area and few obstructions, as you
can see, that's going to extend
		
00:12:58 --> 00:13:03
			the cycle time by about two
seconds, two out of 13. That's
		
00:13:03 --> 00:13:08
			about almost 1/7 so almost 14%
reduction
		
00:13:10 --> 00:13:13
			and so on. If we keep going down,
we're going to see that the
		
00:13:13 --> 00:13:18
			average conditions, for example,
more hard packed soil depth even
		
00:13:18 --> 00:13:23
			more 70% and the angle of swing up
to 90 degrees and loading into
		
00:13:23 --> 00:13:26
			trucks, so you have to spot and
you have to adjust, you have to
		
00:13:26 --> 00:13:30
			maneuver, which, again, is going
to slow down the operation up to
		
00:13:30 --> 00:13:34
			when we reach the severe
conditions we have digging through
		
00:13:35 --> 00:13:38
			tough and hard soil
		
00:13:39 --> 00:13:43
			depth over 90% of the maximum
digging depth. So we are almost
		
00:13:43 --> 00:13:48
			extended to the maximum and a
swing angle of over 120 degrees.
		
00:13:48 --> 00:13:52
			So basically we are moving more
than 90 degrees. It's basically
		
00:13:52 --> 00:13:56
			almost facing backward, and it's a
small dump target requiring
		
00:13:56 --> 00:13:59
			maximum reach, so you have to
maneuver to make sure that you
		
00:13:59 --> 00:14:03
			don't spill that soil out of the
dump truck, so it requires
		
00:14:03 --> 00:14:08
			additional maneuvering. Now,
comparing between the excellent
		
00:14:08 --> 00:14:11
			job conditions and the severe
conditions we find that we have
		
00:14:11 --> 00:14:16
			here, for example, difference of
eight seconds, eight out of 13.
		
00:14:16 --> 00:14:20
			That's almost 60% which means that
the production is going to be
		
00:14:20 --> 00:14:21
			reduced considerably.
		
00:14:25 --> 00:14:28
			Shovels similar to the backhoe,
but in this case, is going to be
		
00:14:29 --> 00:14:32
			facing forward. The bucket is
going to be facing forward. Is
		
00:14:32 --> 00:14:36
			going to use two kinds of forces
to break down the soil. Is going
		
00:14:36 --> 00:14:40
			to have something called crowding
force, which moves downwards and
		
00:14:40 --> 00:14:44
			then break out force, which is
gonna lift that soil and dump it
		
00:14:44 --> 00:14:48
			into into the truck. So dig with a
combination of crowding or
		
00:14:48 --> 00:14:52
			downforce and breakout or forward
forces. It has a limited ability
		
00:14:52 --> 00:14:55
			to dig below the track level,
because, again, it's gonna be a
		
00:14:55 --> 00:14:59
			risk of over tipping, tipping
forward. So we're gonna try to
		
00:14:59 --> 00:14:59
			have.
		
00:15:00 --> 00:15:00
			With that,
		
00:15:05 --> 00:15:08
			the shovel production, like the
backhoe, is going to be exactly
		
00:15:08 --> 00:15:14
			the same, C times s times v times
B times E, and the production is
		
00:15:14 --> 00:15:17
			mainly affected by the swing angle
and the loss time during the
		
00:15:18 --> 00:15:21
			production cycle, depending on the
type of soil and the different job
		
00:15:21 --> 00:15:25
			conditions, as we have seen the
previous day, the angle of swing
		
00:15:25 --> 00:15:28
			between digging and dumping should
be kept to a minimum to improve
		
00:15:28 --> 00:15:31
			production, as we have seen again,
difference between 30 degrees and
		
00:15:31 --> 00:15:32
			120 degrees. So
		
00:15:33 --> 00:15:37
			looking at an example here, for
example, other factors to improve
		
00:15:37 --> 00:15:41
			the production having a level
floor of cut that's going to help
		
00:15:41 --> 00:15:44
			with the stability, moving
frequently to be closer to the
		
00:15:44 --> 00:15:47
			working phase, instead of
extending the arm, moving on the
		
00:15:47 --> 00:15:49
			tracks to get closer,
		
00:15:50 --> 00:15:54
			keeping digger teeth sharp, which
is going to help with the crowding
		
00:15:54 --> 00:15:58
			force and better training for the
operator, a skilled operator can
		
00:15:58 --> 00:16:02
			definitely achieve more than an
unskilled operator. So the ideal
		
00:16:02 --> 00:16:07
			production is going to be equal to
the bucket, bucket capacity times
		
00:16:07 --> 00:16:11
			the fill factor divided by the
ideal cycle time. That's going to
		
00:16:11 --> 00:16:16
			give us the ideal production in
again, bank cubic yards per hour.
		
00:16:17 --> 00:16:19
			And here's some again,
		
00:16:20 --> 00:16:25
			fill factors for moist loam or
sandy clay, one to 1.1 sand and
		
00:16:25 --> 00:16:28
			gravel point nine, five to 1.1 and
so on.
		
00:16:32 --> 00:16:37
			Now, based on the the idea shovel
productivity in bank cubic yards
		
00:16:37 --> 00:16:40
			per hour, this is sort of the
theoretical production rate as
		
00:16:40 --> 00:16:44
			given in the manual of that piece
of equipment for different types
		
00:16:44 --> 00:16:48
			of soils, for different bucket
capacities. So for example, for
		
00:16:48 --> 00:16:54
			tough clay and a one and a half
cubic yard bucket is going to be
		
00:16:54 --> 00:16:54
			tough clay
		
00:16:55 --> 00:16:58
			and one and a half, that's going
to give us 210
		
00:16:59 --> 00:17:04
			bank cubic yards per hour. Again,
this is the ideal production, not
		
00:17:04 --> 00:17:06
			the actual production. Therefore,
the ideal production can be
		
00:17:06 --> 00:17:10
			obtained in one of two ways,
either through a table like this,
		
00:17:10 --> 00:17:14
			or through an equation like this,
one with the bucket capacity times
		
00:17:14 --> 00:17:16
			field factor divided by the ideal
cycle time.
		
00:17:19 --> 00:17:25
			The angle of swing is going to
give us a modifying factor, with
		
00:17:25 --> 00:17:30
			the 1.0 being represented by 90
degrees and 100% of the optimum
		
00:17:30 --> 00:17:35
			depth, we're going to see that in
an example in just a minute. If
		
00:17:35 --> 00:17:39
			you dig less than the optimum
depth or much more than the
		
00:17:39 --> 00:17:42
			optimal depth, that's going to
affect the production. If the
		
00:17:42 --> 00:17:46
			angle of swing increases or
decreases again, that's going to
		
00:17:46 --> 00:17:47
			affect the production.
		
00:17:48 --> 00:17:52
			Job conditions. We have both job
conditions and management
		
00:17:52 --> 00:17:56
			conditions. Management conditions
basically something like having a
		
00:17:56 --> 00:18:00
			good operator, a good observer, a
good superintendent, good
		
00:18:00 --> 00:18:07
			monitoring of the operation, you
have the the trucks lined up very
		
00:18:07 --> 00:18:11
			close to where the soil is going
to be done, so that the shovel
		
00:18:11 --> 00:18:16
			doesn't have to move much. Job
conditions, depending on how
		
00:18:16 --> 00:18:20
			graded the site is, if you don't
have too many obstacles,
		
00:18:21 --> 00:18:24
			the equipment is in good condition
and so on. These are things that
		
00:18:24 --> 00:18:30
			also we can't control. So we have
another modifying factor based on
		
00:18:30 --> 00:18:33
			the management conditions and the
job conditions. For Good job
		
00:18:33 --> 00:18:37
			conditions, good management
conditions, we get, for example, a
		
00:18:37 --> 00:18:38
			factor of 75%
		
00:18:42 --> 00:18:45
			Let's now look at another example.
A contractor has a project to
		
00:18:45 --> 00:18:49
			excavate an apartment complex and
must construct a three foot
		
00:18:49 --> 00:18:53
			compacted fill to support the
parking garage. The borrow site
		
00:18:53 --> 00:18:57
			where we're going to be borrowing
the soil is three miles from the
		
00:18:57 --> 00:19:01
			construction site, so there's
going to be a shovel over there,
		
00:19:01 --> 00:19:04
			or a backhoe, or whatever piece of
equipment, and that's going to
		
00:19:04 --> 00:19:07
			dump into trucks, and the trucks
are going to bring that soil to
		
00:19:07 --> 00:19:11
			the site for utilization. The
borrow site is three miles from
		
00:19:11 --> 00:19:15
			the construction construction
site, and 10 cubic yard. 10 cubic
		
00:19:15 --> 00:19:16
			yard dump trucks
		
00:19:19 --> 00:19:24
			will be used to haul the kneaded
fill a two cubic yard shovel would
		
00:19:24 --> 00:19:28
			be used to load the dump trucks.
The material is tough, dry clay
		
00:19:28 --> 00:19:30
			with a swell factor of 35%
		
00:19:31 --> 00:19:36
			the height of the cut at the
borrow site is 11.6 feet, and the
		
00:19:36 --> 00:19:41
			angle of swing of the shovel is
150 degrees. So estimate the ideal
		
00:19:41 --> 00:19:44
			production using the table and
using the equation, we're going to
		
00:19:44 --> 00:19:48
			do that and then estimate the
actual production for good job and
		
00:19:48 --> 00:19:52
			management conditions. The optimum
digging depth of the shovel is 9.8
		
00:19:53 --> 00:19:58
			feet. This is the optimum, and
this is the actual so let's see
		
00:19:58 --> 00:19:59
			this equation. This this row.
		
00:25:00 --> 00:25:00
			Again,
		
00:25:08 --> 00:25:12
			with the optimum depth of cut of
various sizes of Jetline buckets.
		
00:25:12 --> 00:25:16
			So here is going to give us four
different types of soil. What
		
00:25:16 --> 00:25:19
			would be the optimum depth of cut
for a three hot three quarters
		
00:25:19 --> 00:25:24
			cubic yard, for one and a quarter
cubic yards and so on. And also
		
00:25:24 --> 00:25:28
			here we have the operating
factors, the job conditions and
		
00:25:28 --> 00:25:31
			the management conditions, exactly
the same table as we have seen
		
00:25:31 --> 00:25:35
			before. And then we have also the
drag line productivity correction
		
00:25:35 --> 00:25:40
			factor based on the percentage of
the optimum depth of cut and the
		
00:25:40 --> 00:25:45
			angle of swing, as we have seen
with the shovel, and ideal
		
00:25:45 --> 00:25:47
			productivity based on
		
00:25:48 --> 00:25:52
			the bucket size in bank, cubic
yards per hour. Let's
		
00:25:58 --> 00:26:01
			look at an example. The contractor
has a project to construct a large
		
00:26:01 --> 00:26:05
			parking lot for a shopping center.
The contractor decided to use a
		
00:26:05 --> 00:26:10
			crawler drag line. Crawler drag
line, which means it's gonna be on
		
00:26:10 --> 00:26:14
			tracks with one and three quarters
cubic yard bucket to excavate a
		
00:26:14 --> 00:26:18
			large drainage ditch to collect
and remove storm water runoff.
		
00:26:19 --> 00:26:23
			The excavated soil is common
earth, and the average depth of
		
00:26:23 --> 00:26:25
			cut is 7.6 feet.
		
00:26:26 --> 00:26:29
			The excavated material will be
loaded in dump trucks for removal
		
00:26:29 --> 00:26:34
			from site. The angle of swing is
120 degrees. Job conditions are
		
00:26:34 --> 00:26:37
			good and management conditions are
excellent. So it's not good and
		
00:26:37 --> 00:26:41
			good job conditions, good
management conditions Excellent.
		
00:26:41 --> 00:26:45
			What is the estimated dragline
productivity in bank cubic yards
		
00:26:45 --> 00:26:49
			per hour? And then we're going to
add a couple of other layers. If
		
00:26:49 --> 00:26:53
			the volume to be removed is 3200
bank cubic yards and the rental
		
00:26:53 --> 00:26:55
			cost per day for that dragline is
$1,800
		
00:26:56 --> 00:27:01
			how long would the operation take,
and how much will it cost? So now
		
00:27:01 --> 00:27:06
			we are also looking at durations
and cost estimating for that piece
		
00:27:06 --> 00:27:06
			of equipment.
		
00:27:07 --> 00:27:10
			So from the table, the ideal
production for one and three
		
00:27:10 --> 00:27:15
			quarters bank cubic cubic yard
bucket and Common Earth is 210
		
00:27:16 --> 00:27:19
			bank cubic yards per hour. We're
just going to look at the table.
		
00:27:20 --> 00:27:25
			The optimum depth of cut is nine
and a half feet. The percent of
		
00:27:25 --> 00:27:29
			the optimum depth of cut is
because the actual depth is 7.6 so
		
00:27:29 --> 00:27:36
			it's 7.6 times 100% divided by 9.5
which gives 80% now using the 80%
		
00:27:37 --> 00:27:42
			factor with 120 degrees the angle
of swing gives us a modification
		
00:27:42 --> 00:27:45
			factor of point nine for good job
and excellent management
		
00:27:45 --> 00:27:49
			conditions, the factor is going to
be point seven eight. Therefore
		
00:27:49 --> 00:27:52
			the actual dragline production is
going to be the ideal 210
		
00:27:53 --> 00:27:59
			times. The factor due to the swing
angle and the depth of cut times
		
00:27:59 --> 00:28:04
			the other factor due to the job
and management conditions, which
		
00:28:04 --> 00:28:04
			gives 147.42
		
00:28:06 --> 00:28:07
			bank cubic yards per hour.
		
00:28:09 --> 00:28:14
			The total volume that needs to be
excavated is 3200 bank cubic
		
00:28:14 --> 00:28:19
			yards. So dividing that by the
production per hour is going to
		
00:28:19 --> 00:28:25
			give us 21.7 hours, which is
basically assuming eight hours of
		
00:28:25 --> 00:28:28
			work per day is going to be almost
three days. We're not going to pay
		
00:28:28 --> 00:28:31
			for a fraction of a day. So we're
going to pay for the third day,
		
00:28:31 --> 00:28:35
			whole day. Therefore the cost of
operation is going to be three
		
00:28:35 --> 00:28:39
			days times $1,800 per day, which
gives $5,400
		
00:28:40 --> 00:28:41
			that's the cost of that operation.
		
00:28:45 --> 00:28:47
			Another piece of equipment,
similar to the drag line, is going
		
00:28:47 --> 00:28:48
			to be the clam shell. So
		
00:28:49 --> 00:28:53
			it's going to be the same machine,
but the attachment at the edge of
		
00:28:53 --> 00:28:55
			the boom of the crane is going to
be different. In this case, it's
		
00:28:55 --> 00:28:59
			going to be a drag line. It's
capable of digging at higher
		
00:28:59 --> 00:29:04
			depths. That's one of the benefits
of the clamshell. It lacks
		
00:29:04 --> 00:29:08
			positive digging action and
lateral control of the shovel or
		
00:29:08 --> 00:29:12
			the backhoe. Again, positive
digging, which means the
		
00:29:12 --> 00:29:16
			articulated hydraulic arm is going
to give that hydraulic force, that
		
00:29:16 --> 00:29:20
			crowding force, but in this case,
it's going to rely, like the drag
		
00:29:20 --> 00:29:23
			line on its own weight and on
gravity.
		
00:29:25 --> 00:29:28
			It's used for excavating vertical
shafts and footings for
		
00:29:28 --> 00:29:31
			foundations. So this is what it
looks like.
		
00:29:34 --> 00:29:37
			And as you can see, we have here
the lines that are used to open
		
00:29:37 --> 00:29:40
			and close that clamshell, which
has some teeth, again, to cut
		
00:29:40 --> 00:29:42
			through the soil as possible.
		
00:29:44 --> 00:29:49
			It's also used sometimes for
grains and in Marine Operations
		
00:29:49 --> 00:29:49
			and so on.
		
00:29:53 --> 00:29:57
			The production is based on the
equation, same generic equation,
		
00:29:57 --> 00:29:59
			volume per cycle, time, cycles per
hour, and.
		
00:30:00 --> 00:30:04
			So the maximum load should be
limited to 80% of safe lifting
		
00:30:04 --> 00:30:07
			capacity for rubber tired
equipment and 90% for crawler
		
00:30:07 --> 00:30:11
			mounted equipment. This is a
relative factor of safety, just to
		
00:30:11 --> 00:30:14
			make sure that we're not going to
have any over tipping or any
		
00:30:15 --> 00:30:18
			stability issues with the with the
equipment.
		
00:30:19 --> 00:30:23
			And again, here we have a table
that shows the different cranes
		
00:30:24 --> 00:30:27
			and at the different boom lengths,
what's going to be the operating
		
00:30:27 --> 00:30:31
			radius, and what's going to be the
total load that it that it can
		
00:30:31 --> 00:30:37
			carry at that the tip of that
boom. And this shows basically the
		
00:30:37 --> 00:30:43
			capacity of the clamshell bucket
itself, the rated capacity is
		
00:30:43 --> 00:30:48
			equal to VS which is this bottom
half plus Ve, the top half, which
		
00:30:48 --> 00:30:53
			is the heaping minus Vm, which is
at the joint where it opens and
		
00:30:53 --> 00:30:55
			closes the clamshell.
		
00:30:56 --> 00:31:01
			And here it shows again, the
different weights, because we can
		
00:31:01 --> 00:31:04
			have either a general purpose
bucket, a heavy duty bucket or a
		
00:31:04 --> 00:31:07
			light duty bucket. Each one of
them is going to have a different
		
00:31:07 --> 00:31:11
			weight on its own for the
different rated capacities and
		
00:31:11 --> 00:31:12
			different sizes of these buckets.
		
00:31:18 --> 00:31:21
			To improve the clamshell
production, we're going to have
		
00:31:21 --> 00:31:25
			the dumping radius the same as the
digging radius. So the the boom is
		
00:31:25 --> 00:31:29
			going to rotate and is going to
dump at the same distance where
		
00:31:29 --> 00:31:33
			it's digging from keeping the
machine level to avoid swinging
		
00:31:33 --> 00:31:37
			uphill or downhill, because again,
swinging uphill or downhill is
		
00:31:37 --> 00:31:40
			going to affect stability, and
it's going to affect the effective
		
00:31:40 --> 00:31:42
			length of the boom of the crane.
		
00:31:44 --> 00:31:48
			So again, with the larger angle of
swing, we're going to have
		
00:31:48 --> 00:31:52
			different correction factors. The
lower the angle, the better. The
		
00:31:52 --> 00:31:54
			higher the angle, the lower the
production.
		
00:31:57 --> 00:32:01
			And again, for different types of
soils, we are going to have
		
00:32:01 --> 00:32:01
			different
		
00:32:03 --> 00:32:06
			production rates for the different
sizes of the buckets. Let's
		
00:32:09 --> 00:32:13
			look at an example here as well. A
contractor has decided to use a
		
00:32:13 --> 00:32:18
			two cubic yard clam shell mounted
on a crawler crane to excavate for
		
00:32:18 --> 00:32:23
			the foundations of three concrete
piers for a highway bridge. The
		
00:32:23 --> 00:32:26
			excavated material will be dumped
in stockpiles for later use in
		
00:32:26 --> 00:32:31
			backfilling. The material is
common earth, and the average
		
00:32:31 --> 00:32:35
			angle of swing is 120, degrees.
Job and management conditions are
		
00:32:35 --> 00:32:40
			good. What is the estimated
productivity of the clamshell in
		
00:32:40 --> 00:32:42
			bank cubic yards per hour.
		
00:32:43 --> 00:32:48
			So here we're gonna look at the
table. The bucket size is two
		
00:32:48 --> 00:32:52
			cubic yards we are digging into
		
00:32:55 --> 00:32:56
			common Earth.
		
00:32:57 --> 00:33:02
			So two cubic yards with Common
Earth gives us 160 band cubic
		
00:33:02 --> 00:33:03
			yards per hour.
		
00:33:05 --> 00:33:09
			Now the factor due to the swing
angle, we have a swing angle of
		
00:33:09 --> 00:33:13
			120 degrees, which is a factor of
point nine one. Therefore it's
		
00:33:13 --> 00:33:18
			going to reduce our production.
Now, the factor due to good job
		
00:33:18 --> 00:33:21
			and management conditions is point
seven, five from the table that we
		
00:33:21 --> 00:33:24
			have seen before. Therefore the
productivity, the actual
		
00:33:24 --> 00:33:29
			production, is going to be ideal,
times the correction factor one,
		
00:33:29 --> 00:33:33
			times the efficiency or correction
factor two, and that gives 109
		
00:33:34 --> 00:33:35
			bank cubic yards per hour.
		
00:33:41 --> 00:33:46
			Now I hope that would be a good
introduction to the detailed
		
00:33:46 --> 00:33:49
			discussions about different pieces
of equipment. So we have learned
		
00:33:49 --> 00:33:53
			about the cycle time. We learned
how to use the different tables
		
00:33:53 --> 00:33:56
			and the different correction
factors. The equation is always
		
00:33:56 --> 00:34:00
			the same number of cycles per hour
times the volume per cycle. And
		
00:34:00 --> 00:34:04
			there are some factors that affect
that volume per cycle and the
		
00:34:04 --> 00:34:07
			number of cycles per hour, we have
to include these correction
		
00:34:07 --> 00:34:11
			factors to obtain the actual
production from the ideal
		
00:34:11 --> 00:34:15
			production from the tables that
are given to us. I'll see you
		
00:34:15 --> 00:34:17
			later on in another lecture. Bye.
Bye. You.