Ihab Saad – Example on Schedule Compression

Ihab Saad
AI: Summary ©
The speakers discuss the maximum compressible time for a network, using a table and calculations based on various variables. They explain the process of compressing a network and identifying critical and effective activities, emphasizing the importance of starting with the lowest cost activity and compressing all critical paths by the same amount to achieve maximum savings. The speakers also discuss reducing duration by two days while still saving some money, compressing all paths by the same amount, and being still critical. The projects are designed to compress all paths by the same amount, and the projects are still critical.
AI: Transcript ©
00:00:05 --> 00:00:09

Music. Hello again. Now we start talking about an example on

00:00:10 --> 00:00:13

network compression based on what we have learned so far about which

00:00:13 --> 00:00:17

activities to compress and how to achieve time reduction or time

00:00:17 --> 00:00:22

acceleration. So here we have an example calculate the normal least

00:00:22 --> 00:00:26

cost and crash durations for the following project, and calculate

00:00:26 --> 00:00:30

the cost associated with each duration, whereas indirect costs

00:00:30 --> 00:00:35

are $120 per day. So the costs given here in this table are

00:00:35 --> 00:00:38

basically direct cost for each activity. It shows the activity,

00:00:38 --> 00:00:42

its immediate predecessor, normal duration and crash duration, which

00:00:42 --> 00:00:46

which shows the amount of compressibility that the activity

00:00:46 --> 00:00:51

has, in addition to the cost, normal cost and crash cost, how

00:00:51 --> 00:00:54

much would it cost to compress this activity by that amount of

00:00:54 --> 00:00:57

time? So for example, activity A can be compressed by one day,

00:00:57 --> 00:01:01

which is the difference between the normal and the crash duration

00:01:01 --> 00:01:05

at an extra cost of $100 which is the difference between the crash

00:01:05 --> 00:01:09

cost and the normal cost. And we have that for all the activities.

00:01:09 --> 00:01:13

Notice here, for example, that activity f has a normal duration

00:01:13 --> 00:01:17

of four days and a crash duration of also four days, which makes

00:01:17 --> 00:01:21

delta T for activity f equal to zero. Therefore activity f is

00:01:21 --> 00:01:26

incompressible. If activity f ends up being a critical activity, it

00:01:26 --> 00:01:30

would be excluded from our efforts to compress that activity, because

00:01:30 --> 00:01:34

it is, it is incompressible in the first place. Same thing applies

00:01:34 --> 00:01:38

here to the delta C. It doesn't have any delta cost because,

00:01:38 --> 00:01:42

again, it cannot be compressed. So our first step is looking at this

00:01:42 --> 00:01:47

table, first of all, building the network, and then looking at the

00:01:47 --> 00:01:50

delta t and delta c and the cost slope for the different

00:01:50 --> 00:01:51

activities.

00:01:53 --> 00:01:56

The total direct cost for this project can be obtained by adding

00:01:56 --> 00:01:59

the normal cost for all activities, which is equal to

00:01:59 --> 00:01:59

$4,950

00:02:01 --> 00:02:05

which is basically the sum of these costs here normal adding

00:02:05 --> 00:02:08

these costs, that's going to add up to 4950,

00:02:10 --> 00:02:13

the total indirect costs can be obtained only by solving the

00:02:13 --> 00:02:17

network and multiplying the total duration by the indirect cost per

00:02:17 --> 00:02:18

day, which again is $120

00:02:19 --> 00:02:22

per day. Therefore we have to perform the forward pass, backward

00:02:22 --> 00:02:27

pass, and determine the expected early finish of that network.

00:02:27 --> 00:02:31

Multiply that time, the number of days by 120 and that will give us

00:02:31 --> 00:02:34

the total indirect cost for this project before compression.

00:02:36 --> 00:02:39

So here's our network that we have drawn based on the information

00:02:39 --> 00:02:44

with the IPAS and so on, and it shows basically

00:02:45 --> 00:02:49

several paths. Here's one path, here's a second path, here's a

00:02:49 --> 00:02:53

third path, and here's the fourth path. So we have four paths to

00:02:53 --> 00:03:01

this network, A, B, E, H, A, C, E, H, A, C, F, G, and ADG. These are

00:03:01 --> 00:03:03

the four different paths to this network.

00:03:05 --> 00:03:07

So the next step is to perform our calculations.

00:03:09 --> 00:03:13

And here's a very simple display of these calculations. It shows

00:03:13 --> 00:03:17

the early start for activity is zero, duration five days, so the

00:03:17 --> 00:03:21

early finish is zero, is five and so on. So it's a very simple

00:03:21 --> 00:03:25

calculation of the network time which shows that this project is

00:03:25 --> 00:03:26

going to end on day 25

00:03:27 --> 00:03:31

therefore this this network expected to finish on day 25 has

00:03:31 --> 00:03:37

one critical path which is going to be A, C, E, H, as it appears

00:03:37 --> 00:03:41

from The identical numbers on the early and late sites,

00:03:42 --> 00:03:46

and the total indirect cost is 25 times 120

00:03:47 --> 00:03:51

25 days times 125 $20 per day. With a total of $3,000

00:03:52 --> 00:03:56

we had already calculated the direct cost to be 4950 so the

00:03:56 --> 00:04:01

total cost for this project before compression is 79 $50

00:04:05 --> 00:04:08

and here it shows the critical path that we talked about.

00:04:11 --> 00:04:16

So the next step is to draw the table to show the delta t, the

00:04:16 --> 00:04:20

delta c, the cost slope for the different activities.

00:04:21 --> 00:04:25

And here's the duration for each path, A, B, E, h. Now the duration

00:04:25 --> 00:04:30

for each path is assuming that the other paths do not exist. So if,

00:04:30 --> 00:04:35

for example, C did not exist, activity c did not exist, then the

00:04:35 --> 00:04:39

start date for activity e would have been 12. The start date for

00:04:39 --> 00:04:42

activity h would have been 18, and the completion date would have

00:04:42 --> 00:04:48

been 24 Same thing here, if the two top paths did not exist, or

00:04:48 --> 00:04:53

three top paths did not exist, and we had on the ADG, then activity G

00:04:53 --> 00:04:58

would start on day 16 and end on day 23 and the project would end

00:04:58 --> 00:04:59

on day 23 that's how we.

00:05:00 --> 00:05:01

Determine the length of each path.

00:05:06 --> 00:05:11

Here's the table. Based on the calculations of the crash and

00:05:11 --> 00:05:14

normal durations and crash and normal costs, we obtain the cost

00:05:14 --> 00:05:17

slope, which is the difference in cost divided by the difference in

00:05:17 --> 00:05:22

time. So for the first activity, 100 divided by one for B, 150

00:05:22 --> 00:05:26

divided by two and so on. And we find, again, we remind that

00:05:26 --> 00:05:30

activity f is incompressible. Now the ones in red are the critical

00:05:30 --> 00:05:33

activities. So these are our primary candidates for

00:05:33 --> 00:05:39

compression. They have to be critical compressible effective

00:05:39 --> 00:05:42

and among the critical, compressive and effective

00:05:42 --> 00:05:46

activities, we will select the one with the lowest cost low going

00:05:46 --> 00:05:49

back to this network here, we find that we do not have any start to

00:05:49 --> 00:05:52

start or any finish to finish relationships. It's a very simple

00:05:52 --> 00:05:56

network with all finish to start relationships. Therefore all the

00:05:56 --> 00:06:00

critical activities are effective in compressing the project

00:06:00 --> 00:06:05

duration, none of the critical activities are not none is

00:06:05 --> 00:06:08

incompressible. Therefore, again, all the critical activities are

00:06:08 --> 00:06:12

candidates. So the main criteria in determining which activity to

00:06:12 --> 00:06:14

start with is going to be the cost slope.

00:06:15 --> 00:06:18

So looking at this table here, we look at the critical activities

00:06:18 --> 00:06:22

and the cost slopes. Activity A has 100 day, $100 per day.

00:06:23 --> 00:06:28

Activity C, $40 per day. E, $50 per day and age, $120

00:06:29 --> 00:06:33

per day. Therefore, looking at this, we found out, find out that

00:06:33 --> 00:06:38

activity c is the least expensive to compress, so this is going to

00:06:38 --> 00:06:39

be our primary candidate for compression.

00:06:42 --> 00:06:45

And that is compression cycle number one, we're going to conduct

00:06:45 --> 00:06:48

these compressions in different cycles, as I mentioned several

00:06:48 --> 00:06:53

times before, the time compression or network compression problem is

00:06:53 --> 00:06:56

not a hard problem at all. The concept is very simple. It's just

00:06:56 --> 00:06:59

a repetitive calculation of the forward and the backward paths

00:06:59 --> 00:07:03

after each cycle of compression, compressing each activity by one

00:07:03 --> 00:07:07

day at a time, and then recalculating the dates for the

00:07:07 --> 00:07:12

network. So in cycle one compress activity c by one day. Now we

00:07:12 --> 00:07:14

notice that looking at the network again,

00:07:16 --> 00:07:18

look at the total float on activity B,

00:07:19 --> 00:07:24

13 and 12. So the total float for this activity is only one day,

00:07:24 --> 00:07:28

which means if I reduce the duration of this activity by one

00:07:28 --> 00:07:32

day, if I end this activity on day 12,

00:07:33 --> 00:07:36

going in the backward pass, we're going to find out that the late

00:07:36 --> 00:07:40

finish for activity B is going to become 12, which means activity B

00:07:40 --> 00:07:44

is going to lose its first day, or its only day of total float, which

00:07:44 --> 00:07:47

is going to make it a critical activity. So we're going to create

00:07:47 --> 00:07:52

a new critical path going through A, B, E, H.

00:07:57 --> 00:08:02

So this is the first cycle activity c is compressed, and B

00:08:02 --> 00:08:07

will become critical with the cost of compression is going to be $40

00:08:07 --> 00:08:11

therefore, to proceed with the second cycle, we have to check the

00:08:11 --> 00:08:14

cost slopes of activities to be compressed. Remember that in order

00:08:14 --> 00:08:17

to achieve an effective compression of more than one

00:08:17 --> 00:08:20

critical path, we must compress all critical paths by the same

00:08:20 --> 00:08:24

amount. So if we have multiple critical paths that need to be

00:08:24 --> 00:08:25

compressed, it's

00:08:26 --> 00:08:29

not enough to compress only one of them, because if you compress one

00:08:29 --> 00:08:32

and leave the others incompressed or uncompressed, that would make

00:08:32 --> 00:08:35

them longer, and they would remain critical, whereas the one that has

00:08:35 --> 00:08:38

been compressed is not critical anymore. So in order to achieve

00:08:38 --> 00:08:42

that compression, we have to compress all the critical paths by

00:08:42 --> 00:08:45

exactly the same amount, and this can be achieved either by

00:08:45 --> 00:08:49

compressing one activity on each one of these paths by the same

00:08:49 --> 00:08:53

amount, or looking for a common activity that is shared by all of

00:08:53 --> 00:08:56

these critical paths, and compressing this activity, which

00:08:56 --> 00:09:01

is going to result in a complete In a compression for all the

00:09:01 --> 00:09:02

existing critical paths,

00:09:05 --> 00:09:10

the net cost of compression here is savings of $80 why? Because we

00:09:10 --> 00:09:14

have spent an extra 80 $40 to compress activity C, but at the

00:09:14 --> 00:09:18

same time, we reduced the total project duration by one day, which

00:09:18 --> 00:09:21

saved us $120 in indirect costs.

00:09:23 --> 00:09:27

And here's the calculation after the first cycle of compression.

00:09:27 --> 00:09:32

Notice that each cycle is going to be done in a different color, so

00:09:32 --> 00:09:36

that we can identify which activities have been affected and

00:09:36 --> 00:09:37

which dates have changed.

00:09:40 --> 00:09:44

So here, when we compress activity C from eight to seven, perform the

00:09:44 --> 00:09:50

calculations in the backward pass here I have activity B with zero

00:09:50 --> 00:09:51

total float.

00:09:55 --> 00:09:58

Therefore now we have a new critical path in addition to the

00:09:58 --> 00:09:59

old one. So AC.

00:10:00 --> 00:10:04

Eh is still critical and now a, b, eh has become another critical

00:10:04 --> 00:10:04

path.

00:10:14 --> 00:10:19

Now let's look at the other paths. We notice here that activity G has

00:10:19 --> 00:10:24

a total float of only one day, so does activity f and also so does

00:10:24 --> 00:10:26

activity D. Therefore,

00:10:27 --> 00:10:31

any additional compression to this path more likely is going to

00:10:31 --> 00:10:36

result in these activities becoming critical, except if we

00:10:36 --> 00:10:39

compress activity A, because compressing activity A is going to

00:10:39 --> 00:10:43

affect all the paths so the non critical activities are going to

00:10:43 --> 00:10:47

keep their total float. So now let's look again at the cost of

00:10:47 --> 00:10:52

compression. In order to compress this path, these two paths at the

00:10:52 --> 00:10:55

same time by the same amount, we can either compress activity A by

00:10:55 --> 00:10:58

itself because it's joined between the two, or we can compress

00:10:58 --> 00:11:03

activity e by itself, or we can compress activity h by itself,

00:11:03 --> 00:11:10

therefore A or B and C together, or H by itself, or or E by itself,

00:11:10 --> 00:11:13

or H by itself. Let's look at the cost for this compression.

00:11:16 --> 00:11:19

So we find that activity c is still the least expensive,

00:11:20 --> 00:11:26

followed by E, followed by a, followed by h. Now if I want to

00:11:26 --> 00:11:30

compress C, I have also to compress B at the same time.

00:11:30 --> 00:11:33

Therefore the cost of compressing one extra day is going to be 40

00:11:33 --> 00:11:38

plus 75 that would be 115 to achieve that compression. Or

00:11:38 --> 00:11:42

another option is to compress activity e by itself, or to

00:11:42 --> 00:11:46

compress activity A by itself, or activity h by itself. So

00:11:52 --> 00:11:55

based on the information from cycle one, the least expensive

00:11:55 --> 00:11:59

activity to compress is activity e, again, from here, from this

00:11:59 --> 00:12:03

table, this activity, this expensive activity to compress, is

00:12:03 --> 00:12:08

activity e, with a cost of $50 this result in converting all the

00:12:08 --> 00:12:11

activities on the network into critical activities, because,

00:12:11 --> 00:12:14

again, all their meaning activities had only one day of

00:12:14 --> 00:12:17

total float. Once we compressed activity e, all of these non

00:12:17 --> 00:12:20

critical activities will lose that total float, thus becoming

00:12:20 --> 00:12:24

critical. And the net cost of this compression is a saving of $70

00:12:25 --> 00:12:30

because again, we spent an extra $50 we saved 120 so the net is

00:12:30 --> 00:12:32

savings of $70

00:12:36 --> 00:12:39

and now we can see the new numbers, and it shows clearly that

00:12:39 --> 00:12:41

all the other activities have become critical.

00:12:43 --> 00:12:45

So here's the original critical path,

00:12:46 --> 00:12:48

here's the second critical path,

00:12:49 --> 00:12:54

and here's the third critical path, each one shown in a

00:12:54 --> 00:12:58

different color that shows when did these activities become

00:12:58 --> 00:13:01

critical? That's very important, again, as we mentioned before, to

00:13:01 --> 00:13:05

use different colors, so that we do not lose track of these changes

00:13:05 --> 00:13:10

and which activity was changed at which cycle and so on and so

00:13:10 --> 00:13:10

forth.

00:13:11 --> 00:13:16

Now the project ends on day 23 so we have managed to reduce the

00:13:16 --> 00:13:20

duration by two days while still saving some money, which is good.

00:13:24 --> 00:13:25

Our next step,

00:13:26 --> 00:13:28

again, all the activities now are critical,

00:13:29 --> 00:13:32

so we need to look at which activities need to be compressed.

00:13:33 --> 00:13:38

In order to compress this network, again, the options are, I have to

00:13:38 --> 00:13:39

compress

00:13:40 --> 00:13:44

all the paths by the same amount. So it's either compressing, for

00:13:44 --> 00:13:53

example, H with G or E with G, or B and C together with D and G,

00:13:53 --> 00:13:57

because D is on the separate path from G. So remember that we have

00:13:57 --> 00:14:03

three paths. So it's either B, C, G and D together, or

00:14:04 --> 00:14:10

E, G and D together, or H, G and D together, because f is

00:14:10 --> 00:14:15

incompressible. Or maybe looking at activity A, which is the common

00:14:15 --> 00:14:18

activity in all paths, if we compress activity A, that might

00:14:18 --> 00:14:20

end up being less expensive.

00:14:21 --> 00:14:23

So looking at the cost A by itself, is 100

00:14:24 --> 00:14:28

B, C, with any other activity, that activity that already exceeds

00:14:28 --> 00:14:30

the 100. So that's not our choice.

00:14:32 --> 00:14:36

Therefore, we find out that the cheapest activity to be compressed

00:14:36 --> 00:14:37

is going to be activity A.

00:14:40 --> 00:14:44

Since we now have four critical paths, compressing the network

00:14:44 --> 00:14:48

requires compressing all the paths by the same amount. This can be

00:14:48 --> 00:14:51

achieved by compressing at least one activity on each path. And

00:14:51 --> 00:14:56

again, here it shows the analysis of the costs together. So by

00:14:56 --> 00:14:59

compressing activity a one day, the net cost would.

00:15:00 --> 00:15:04

Be a savings of $20 because the extra cost is $100 and the savings

00:15:04 --> 00:15:05

of $120

00:15:07 --> 00:15:13

now look at these numbers, 165, 202 70 and so on. That is more

00:15:13 --> 00:15:18

than the 120 that I'm going to be ending up saving. Therefore, if I

00:15:18 --> 00:15:23

compress, after compressing activity A, if I try to compress

00:15:23 --> 00:15:26

any other activities, that's going to be on the more expensive side,

00:15:26 --> 00:15:29

because that's going to end up costing me more money. So I'm not

00:15:29 --> 00:15:32

saving any money by reducing the duration. I'm actually spending

00:15:32 --> 00:15:33

more money.

00:15:37 --> 00:15:41

And here, once we have compressed activity A, all the activities are

00:15:41 --> 00:15:43

still critical,

00:15:49 --> 00:15:51

and now we end the project on day 22

00:15:55 --> 00:15:58

so here it shows the different compression cycles that We have

00:15:58 --> 00:16:01

done and which activities became critical when

00:16:08 --> 00:16:10

now the question is, where to stop? Are we going to keep

00:16:11 --> 00:16:14

compressing this network? Or should we stop here? And the

00:16:14 --> 00:16:18

answer to this question depends on what's the objective we need to

00:16:18 --> 00:16:22

achieve if we need to compress the network to the maximum. It is

00:16:22 --> 00:16:27

still compressible, because again, we can compress B and C and D and

00:16:27 --> 00:16:30

G, for example, at the same time, and that's going to result in

00:16:30 --> 00:16:31

another day of compression.

00:16:34 --> 00:16:38

So we can do that, but that's going to be, as we have already

00:16:38 --> 00:16:41

noticed, it's going to be on the more expensive side, because we

00:16:41 --> 00:16:43

are not saving any money by doing that, we are spending more money

00:16:44 --> 00:16:47

if we need to compress the network until it's not economically wise,

00:16:47 --> 00:16:51

so compress it any further, then we have to stop here, because

00:16:51 --> 00:16:55

against compressing further is going to result in more expenses,

00:16:55 --> 00:16:59

and that's not economically meaning. If we need to compress

00:16:59 --> 00:17:02

the network by a certain number of days. Let's say we all we wanted

00:17:02 --> 00:17:05

to do is compress the network by three days. We have already

00:17:05 --> 00:17:09

achieved that. So here we can stop. So it depends on how the

00:17:09 --> 00:17:12

question is being asked. So the question can be asked as compress

00:17:12 --> 00:17:16

the network to the maximum regardless of the cost. In this

00:17:16 --> 00:17:19

case, we would keep compressing or compressing it. Compress the

00:17:19 --> 00:17:22

network until it's not economically feasible or

00:17:22 --> 00:17:25

meaningful to compress it any further, which means we're going

00:17:25 --> 00:17:30

to stop as soon as the savings are not achieved, which means the cost

00:17:30 --> 00:17:34

of compression exceeds the savings resulted from reduction in

00:17:34 --> 00:17:39

indirect costs or compressed by a certain number of days. As soon as

00:17:39 --> 00:17:42

we reach that number of days we are going to start, we're going to

00:17:42 --> 00:17:43

stop our conversion.

00:17:45 --> 00:17:48

And this is basically a graphical representation of that concept.

00:17:48 --> 00:17:53

Here we have the direct cost curve, which shows that the

00:17:53 --> 00:17:58

shorter the duration, the higher the cost of direct costs. Here's

00:17:58 --> 00:18:00

the indirect cost, which shows the opposite, the shorter the

00:18:00 --> 00:18:04

duration, the lower the indirect cost. And then here's the sum of

00:18:04 --> 00:18:07

the two curves together. It's adding the numbers from the two

00:18:07 --> 00:18:09

curves together. It shows that for a certain portion,

00:18:11 --> 00:18:12

as you compress,

00:18:13 --> 00:18:16

the total cost goes down, which is what we have been doing so far,

00:18:17 --> 00:18:19

and then you reach a certain point, and the cost starts rising

00:18:19 --> 00:18:20

up again.

00:18:21 --> 00:18:25

So this is where we had stopped originally, right now in this

00:18:25 --> 00:18:30

problem. And this is going to be called the right side of the total

00:18:30 --> 00:18:34

cost curve. And this is the left side of the total cost curve. On

00:18:34 --> 00:18:39

the right side of the total cost curve, the indirect cost is more

00:18:39 --> 00:18:44

effective. So with the reduction, the total curve trend follows the

00:18:44 --> 00:18:47

same trend as the indirect cost, which is reduction as you

00:18:47 --> 00:18:53

compress. On the left hand side, the curve, the total cost follows

00:18:53 --> 00:18:57

the curve or the trend of the direct cost. As we compress, the

00:18:57 --> 00:19:01

total cost goes up so again, until we reach a certain point where we

00:19:01 --> 00:19:06

cannot compress anymore. So this is basically in a nutshell how we

00:19:06 --> 00:19:10

can achieve network compression or time acceleration.

00:19:11 --> 00:19:15

I hope this helps you understand the concept and you can practice

00:19:15 --> 00:19:18

on some additional problems. Thank you and see you later. You.

Share Page