Ihab Saad – Example on Earned Value Analysis

Ihab Saad
Share Page

AI: Summary ©

The speaker explains that they will use certain numbers to calculate the cost of work performed by the end of week nine. They will use the AC (a cost analysis) and the earned value ( BC or budgeted cost and visible value) to calculate the actual cost. They will also use the network and a line to measure the activity of the project. The speaker discusses how they can calculate the actual cost and the actual value for each segment of the network, and how they can solve the cost variance problem by solving the problem.

AI: Summary ©

00:05:00 --> 00:05:03
			Calculate that number, and we are
given these numbers so but just by
		
00:05:03 --> 00:05:09
			adding these values, we are going
to get the total actual cost. Now
		
00:05:09 --> 00:05:12
			this is by the end of week nine.
This is not at the end of the
		
00:05:12 --> 00:05:15
			project, because these were
collected at the end of week nine.
		
00:05:15 --> 00:05:20
			So this is the AC or AC WP by the
end of week nine. And that's the
		
00:05:20 --> 00:05:24
			first of three numbers that we're
going to need remember to solve
		
00:05:24 --> 00:05:28
			this problem we're going to need
initially, the main ingredients
		
00:05:28 --> 00:05:34
			are going to be the AC or acwp,
the bcwp or earned value, and the
		
00:05:34 --> 00:05:38
			BCWS or planned value. These are
the three numbers that can be
		
00:05:38 --> 00:05:44
			manipulated to reach the variances
and the indices and get all the
		
00:05:44 --> 00:05:47
			analysis done. So. Step number
two, just add the numbers to
		
00:05:47 --> 00:05:50
			calculate the AC, or actual cost
for work performed.
		
00:05:54 --> 00:05:57
			Step number three, we need to
calculate now the earned value,
		
00:05:58 --> 00:06:04
			the earned value or BC, WP, what
are the two ingredients of bcwp?
		
00:06:04 --> 00:06:09
			It's BC, budgeted cost and WP were
performed. Do we have these two
		
00:06:09 --> 00:06:13
			ingredients? Yes, we do. In the
first step, we calculated BC or
		
00:06:13 --> 00:06:18
			the budgeted cost and were
performed, or WP was already given
		
00:06:18 --> 00:06:22
			to us at the end of week nine,
which is this column here, the
		
00:06:22 --> 00:06:26
			percent complete. Percent Complete
represents the work performed by
		
00:06:26 --> 00:06:30
			the end of week nine. So all we
need to do now is basically
		
00:06:30 --> 00:06:34
			multiply these two columns. So
we're going to take the budgeted
		
00:06:34 --> 00:06:39
			cost, total budget, times the work
performed for each activity, and
		
00:06:39 --> 00:06:43
			that's going to give us the earned
value, or budgeted cost for work
		
00:06:43 --> 00:06:46
			performed so for activity, a, 690
times 100%
		
00:06:47 --> 00:06:49
			B, 1680, times 100%
		
00:06:50 --> 00:06:54
			C, 2700 times 75% and that gives
2020, 5d
		
00:06:56 --> 00:07:01
			2880 times 0% that gives zero and
so On. So by adding these numbers
		
00:07:02 --> 00:07:03
			now we get 6717
		
00:07:04 --> 00:07:10
			which is the budgeted cost for
work performed by the end of week
		
00:07:10 --> 00:07:15
			nine. So so far, we calculated
budgeted cost, we calculated
		
00:07:15 --> 00:07:20
			actual cost, and we calculated the
earned value, or budgeted cost for
		
00:07:20 --> 00:07:24
			work performed. As you can see
here, we have an empty column for
		
00:07:24 --> 00:07:28
			BCWS, or the planned value. This
is something that we have not
		
00:07:28 --> 00:07:31
			calculated yet, and we need to
calculate in order to reach the
		
00:07:31 --> 00:07:35
			three ingredients that are going
to be used to solve this problem.
		
00:07:35 --> 00:07:39
			But from the initial an initial
look here, just looking at these
		
00:07:39 --> 00:07:44
			numbers, we have here earned
value, bcwp, and we have here
		
00:07:44 --> 00:07:48
			acwp, or actual cost. What do you
think about these two numbers?
		
00:07:48 --> 00:07:52
			What do they say? It shows
initially, so far, that the actual
		
00:07:52 --> 00:07:56
			cost for work performed exceeds
the budgeted cost for work
		
00:07:56 --> 00:07:59
			performed for the same amount of
work, which is work performed,
		
00:07:59 --> 00:08:04
			which can be removed, set aside.
Now we have actual cost versus
		
00:08:04 --> 00:08:08
			budgeted cost. It seems apparent
here that the actual cost is
		
00:08:08 --> 00:08:11
			greater than the budgeted cost. So
it seems that this project, at
		
00:08:11 --> 00:08:15
			least when it comes to cost, is
over budget. But how is it doing?
		
00:08:16 --> 00:08:19
			Schedule wise, we are still gonna
find that in a couple of minutes.
		
00:08:20 --> 00:08:23
			So this is the end of step number
three. Step number four. We're
		
00:08:23 --> 00:08:28
			going to draw that network. So we
are given activities, as we have
		
00:08:28 --> 00:08:32
			here in this slide. We are given
the durations. We're giving the
		
00:08:32 --> 00:08:35
			present, the precedence. So what
we're going to do is we're going
		
00:08:35 --> 00:08:38
			to draw this network, and then
we're going to draw a vertical
		
00:08:38 --> 00:08:42
			line at the end of week nine, and
measure by the end of week nine,
		
00:08:42 --> 00:08:47
			what amount of work should have
been complete? So what should have
		
00:08:47 --> 00:08:49
			been scheduled by the end of week
nine?
		
00:08:51 --> 00:08:54
			So we're going to find that
activity. A starts on Week Zero,
		
00:08:54 --> 00:09:02
			ends on week 3b. Starts on zero
ends on 6c. Follows a, d follow C,
		
00:09:02 --> 00:09:08
			E and F, both of them follow B. So
this is basically the durations
		
00:09:08 --> 00:09:12
			that were given. We just plotted
them on the time and activity
		
00:09:12 --> 00:09:16
			axes, which is a regular Gantt
chart, and then we drew a vertical
		
00:09:16 --> 00:09:19
			line at the end of week nine. So
the cutoff date is the end of week
		
00:09:19 --> 00:09:24
			nine, and it shows here that
activity B has not started yet.
		
00:09:25 --> 00:09:31
			Activity C, activity e has three
weeks already expired from a total
		
00:09:31 --> 00:09:36
			duration of six weeks, so it
should have been 50% complete.
		
00:09:38 --> 00:09:39
			Activity f
		
00:09:40 --> 00:09:43
			has already should have been
completed by the end of week nine.
		
00:09:44 --> 00:09:49
			So it shows here that the Percent
Complete for activities A and B
		
00:09:49 --> 00:09:50
			should have been 100%
		
00:09:51 --> 00:09:53
			for activity C, it should also be
100%
		
00:09:54 --> 00:09:59
			for activity D, 0% has not started
yet. Activity e should be 50.
		
00:10:00 --> 00:10:04
			Percent three weeks out of six,
and activity f should be 100%
		
00:10:04 --> 00:10:08
			complete. So we're going to take
these percentages. These represent
		
00:10:09 --> 00:10:13
			the percentages of work scheduled.
We already had the work performed.
		
00:10:14 --> 00:10:17
			Now we have the work scheduled.
Think about this for a second.
		
00:10:17 --> 00:10:20
			Now, what do we have? We have the
budgeted cost from the very first
		
00:10:20 --> 00:10:20
			step,
		
00:10:22 --> 00:10:26
			we calculated the earned value, we
calculated the actual cost, and
		
00:10:26 --> 00:10:29
			now we have the amount or the
percentage of work scheduled. If
		
00:10:29 --> 00:10:32
			we multiply that work scheduled
times
		
00:10:33 --> 00:10:38
			the budgeted cost, what do we get?
We get the budgeted cost for work
		
00:10:38 --> 00:10:41
			scheduled, or what we call the
planned value.
		
00:10:43 --> 00:10:49
			So this is basically what that
slides slide does us that at the
		
00:10:49 --> 00:10:54
			end of of week nine activities, A,
B, C and F should be 100%
		
00:10:54 --> 00:10:59
			complete, e should be 50% done,
and D should be 0% complete. So
		
00:10:59 --> 00:11:02
			we're going to take these values,
we are going to put them in a
		
00:11:02 --> 00:11:06
			table like this, and then now we
need to calculate the budgeted
		
00:11:06 --> 00:11:09
			cost for scheduled or PV and that
is going to be basically
		
00:11:10 --> 00:11:14
			multiplying the total budget times
the percentages that we have in
		
00:11:14 --> 00:11:18
			this table. And that is going to
give us the budgeted cost for
		
00:11:18 --> 00:11:23
			scheduled or planned value. Now
again, looking at these numbers,
		
00:11:23 --> 00:11:24
			the planned value,
		
00:11:26 --> 00:11:26
			7530
		
00:11:27 --> 00:11:30
			by the end of week nine, it should
have been 7530
		
00:11:31 --> 00:11:32
			the earned value is 6717
		
00:11:34 --> 00:11:38
			so budgeted costs for work
scheduled at the end of week 975,
		
00:11:39 --> 00:11:42
			30. Budgeted cost, forward
performed at the end of week 967,
		
00:11:43 --> 00:11:48
			17, remove the common term, which
is, in this case, budgeted cost,
		
00:11:49 --> 00:11:53
			we end up with work scheduled
versus work performed. It seems
		
00:11:53 --> 00:11:56
			that the work scheduled is greater
than the work performed, which
		
00:11:56 --> 00:12:00
			means the work performed is less
than the work scheduled, which
		
00:12:00 --> 00:12:04
			means we are behind schedule. So
from the first comparison here, we
		
00:12:04 --> 00:12:09
			concluded that we are about
budget. From the second
		
00:12:09 --> 00:12:13
			comparison, it shows that we are
behind schedule. So basically,
		
00:12:13 --> 00:12:18
			this is the double whammy, bad on
cost and bad on time as well.
		
00:12:20 --> 00:12:26
			This shows the numbers that we
have that we were given BCWS.
		
00:12:26 --> 00:12:31
			That's our S curve. And it shows
here the weekly expenditures.
		
00:12:35 --> 00:12:38
			And now we need to start
calculating the variances and the
		
00:12:38 --> 00:12:42
			indices from the numbers. The
scheduled variance is equal to
		
00:12:42 --> 00:12:45
			earned value minus planned value.
The Earned Value is 6717
		
00:12:46 --> 00:12:47
			the planned value is 7530
		
00:12:48 --> 00:12:54
			so we have a negative 813,
variance. Negative number means
		
00:12:54 --> 00:12:57
			that we are behind schedule by an
amount of work worth $813
		
00:12:59 --> 00:13:00
			as the earned value is
		
00:13:02 --> 00:13:05
			the earned value is less than the
planned value.
		
00:13:07 --> 00:13:11
			The cost variance equals earned
value minus actual cost.
		
00:13:12 --> 00:13:15
			So 6717 minus 8205
		
00:13:17 --> 00:13:21
			so here again, we have a negative
value which is bad. Negative
		
00:13:21 --> 00:13:24
			number means that we are over
budget by 1488, as the earned
		
00:13:24 --> 00:13:29
			value is less than the actual
cost. Now notice that we have a
		
00:13:29 --> 00:13:32
			typo here. This should be less
than, not greater than.
		
00:13:33 --> 00:13:34
			So this number has,
		
00:13:36 --> 00:13:39
			that's the that's the cost
variance,
		
00:13:42 --> 00:13:43
			the accounting variance
		
00:13:44 --> 00:13:49
			is equal to actual cost minus
planned value. And again, this
		
00:13:49 --> 00:13:52
			number does not have any
significance whatsoever, as it
		
00:13:52 --> 00:13:54
			compares apples and oranges,
		
00:13:55 --> 00:14:00
			the SPI or SPR is earned value
divided by plant value. We have
		
00:14:00 --> 00:14:04
			here a number that's less than
one, which, again, is bad. So
		
00:14:04 --> 00:14:06
			indicates that we are 11.8%
		
00:14:07 --> 00:14:12
			which is the difference between
one and point 892, 11.8% behind
		
00:14:12 --> 00:14:16
			schedule, the cost performance
ratio, or index earned value
		
00:14:16 --> 00:14:18
			divided by actual cost. Again,
it's less than 1.818
		
00:14:20 --> 00:14:22
			which indicates that we are 18.2%
		
00:14:23 --> 00:14:27
			over budget. So this is basically
the summary of how this project is
		
00:14:27 --> 00:14:31
			performing. Is not doing very
well. Currently, we can reflect
		
00:14:31 --> 00:14:33
			all of this information in a
graphical way.
		
00:14:35 --> 00:14:39
			So again, this is the curve that
we had drawn before, and it shows
		
00:14:39 --> 00:14:43
			the final number here at the BAC.
And now we draw a vertical line at
		
00:14:43 --> 00:14:48
			the end of week nine, and it shows
that the earned value is below the
		
00:14:48 --> 00:14:50
			other two points, the planned
value and the actual cost.
		
00:14:50 --> 00:14:54
			Remember, just by looking at this
curve, if the earned value is the
		
00:14:54 --> 00:14:58
			highest point, that would be
great. It would be good and good
		
00:14:59 --> 00:14:59
			if the earned value.
		
00:15:00 --> 00:15:05
			Is the lowest point, it would be
bad and bad if it's in between. So
		
00:15:05 --> 00:15:10
			if, for example, it's below the AC
and above the PV, it means that we
		
00:15:10 --> 00:15:13
			are bad on cost, but good on
schedule. And if they reverse
		
00:15:13 --> 00:15:18
			their order, if the PV is the
highest one, the EV is in the
		
00:15:18 --> 00:15:21
			middle and the actual cost is at
the bottom, it means that we're
		
00:15:21 --> 00:15:24
			doing well on cost, but we're not
doing very well on schedule. But
		
00:15:24 --> 00:15:28
			in this case, unfortunately, it's
a bad bad since the EV is the
		
00:15:28 --> 00:15:29
			lowest point,
		
00:15:32 --> 00:15:37
			that's basically the the answer to
that earned value problem. I hope
		
00:15:37 --> 00:15:40
			you you do understand now how to
solve this problem. You