Ihab Saad – Developing the schedule

Ihab Saad
AI: Summary ©
The speakers discuss the importance of identifying and breaking down a project to determine the activities needed to achieve the project. They stress the need for clear distinction in order to avoid delays and consider resource and technology constraints when scheduling a project. The process of identifying and breaking down the project involves identifying and breaking down each activity and identifying and breaking down the project for each classifications. The speakers also discuss the use of technology and the constraints surrounding the project, including logistical, political, and cultural constraints. They outline the process of breaking down the project for each activity and identifying and breaking down the project for each classifications. The importance of finding the right duration for each activity and using productivity tables to estimate the work test duration is emphasized.
AI: Transcript ©
00:00:06 --> 00:00:10

Hello. Today, we're going to learn about building the schedule. What

00:00:10 --> 00:00:13

do we mean by building the schedule, and how to break down a

00:00:13 --> 00:00:17

big project into smaller components, along which lines and

00:00:17 --> 00:00:20

how many activities should a project have, and so on and so

00:00:20 --> 00:00:24

forth. So basically, what we're going to discuss is how to

00:00:24 --> 00:00:28

identify the activities in a project, how to determine the

00:00:28 --> 00:00:32

activity durations and the relationships among the activities

00:00:32 --> 00:00:35

and linking them and so on. This is going to be a review of what we

00:00:35 --> 00:00:38

learned before about the different types of relationships and so on.

00:00:38 --> 00:00:43

But we're going to talk primarily about the first task in schedule

00:00:43 --> 00:00:47

development, which is activity definition, how to break down the

00:00:47 --> 00:00:49

project into activities.

00:00:51 --> 00:00:55

So construction planning can be either cost oriented or schedule

00:00:55 --> 00:00:59

oriented. And to give an example on that, the cost oriented is

00:00:59 --> 00:01:02

going to look at the direct costs and the indirect costs. The direct

00:01:02 --> 00:01:06

costs are basically costs involved directly in the construction

00:01:06 --> 00:01:10

operation on site, whereas indirect costs are going to be

00:01:10 --> 00:01:13

costs needed to be spent on the project, but not necessarily

00:01:13 --> 00:01:18

related to any particular activity. So for example, if you

00:01:18 --> 00:01:19

have

00:01:21 --> 00:01:24

a central purchasing department at the headquarters of the company.

00:01:25 --> 00:01:28

This purchasing department is working on all projects or any

00:01:28 --> 00:01:31

scheduling department, or any Central Department, the legal

00:01:31 --> 00:01:35

department, for example, you cannot pinpoint and say they work

00:01:35 --> 00:01:39

that long on this particular project or that project. So it's

00:01:39 --> 00:01:43

going to be a general overhead for the head office, whereas direct

00:01:43 --> 00:01:45

costs are going to be the cost of the people assigned to the

00:01:45 --> 00:01:49

construction site, field engineers, Superintendent, project

00:01:49 --> 00:01:53

manager, etc. When we look at the time aspect of the project, the

00:01:53 --> 00:01:59

schedule oriented idea, we have time oriented, which is going to

00:01:59 --> 00:02:03

be developing the critical path of the project and resource oriented

00:02:03 --> 00:02:07

which is going to be, what kind of resources do we need? When are we

00:02:07 --> 00:02:10

going to need them in what amount, and so on and so forth.

00:02:11 --> 00:02:15

This resource oriented planning is going to be sort of joint between

00:02:16 --> 00:02:19

the schedule oriented planning and the cost oriented planning,

00:02:19 --> 00:02:23

because, again, every resource has its own cost, so we need to

00:02:23 --> 00:02:26

calculate the cost of these resources as well.

00:02:29 --> 00:02:33

Before starting our scheduling effort, we have to read the

00:02:33 --> 00:02:36

specifications and the plans, because, for example, the general

00:02:36 --> 00:02:40

conditions of the contract are going to have an effect on the

00:02:40 --> 00:02:44

selection of the activity and the sequencing of the activities and

00:02:44 --> 00:02:47

the responsibilities and so on and so forth. The staffing of the

00:02:47 --> 00:02:52

project, of course, is going to be also contingent upon, upon these

00:02:53 --> 00:02:56

plans and specs, choosing the appropriate technology, what kind

00:02:56 --> 00:02:59

of technology is going to be available in the project, location

00:03:00 --> 00:03:03

and affordable to the company that's going to be undertaking

00:03:03 --> 00:03:07

that project, identifying and listing activities. How are we

00:03:07 --> 00:03:12

going to break down a huge elephant like the project into

00:03:12 --> 00:03:17

more manageable tasks or activities the size of an ant

00:03:17 --> 00:03:21

compared to that elephant, and then calculating the activity

00:03:21 --> 00:03:24

durations based on the resources that are going to be identified

00:03:24 --> 00:03:28

for each activity and the resource availability, whether it's whether

00:03:28 --> 00:03:33

it's money or materials, equipment, subcontractors, etc,

00:03:33 --> 00:03:37

and labor, identifying the relationships between activities.

00:03:37 --> 00:03:41

So which activity comes first, what's going to be the predecessor

00:03:41 --> 00:03:44

to what, what's going to be a successor to what, which two

00:03:44 --> 00:03:49

activities can be done at the same time, and what kinds of lags and

00:03:49 --> 00:03:52

overlaps, what's what kinds of constraints are going to govern

00:03:52 --> 00:03:55

the relationship between activities? All of that has to be

00:03:55 --> 00:03:59

involved. And then, once we identify the relationships, after

00:04:00 --> 00:04:03

breaking down the project into activities. We have to link these

00:04:03 --> 00:04:07

activities, and once we have linked them, now we're going to

00:04:07 --> 00:04:10

add the durations that we have already calculated to calculate

00:04:10 --> 00:04:15

the activity times and the project duration based on the algorithm of

00:04:15 --> 00:04:18

the critical path that we have already learned about, early

00:04:18 --> 00:04:22

start, early finish, late start, late finish, total and free float,

00:04:22 --> 00:04:25

which are going to be calculated from the forward pass, the

00:04:25 --> 00:04:29

backward pass and determining the critical path of the project.

00:04:32 --> 00:04:36

When we talk about the choice of technology, it's the choices of

00:04:36 --> 00:04:39

appropriate of appropriate technology and methods for

00:04:39 --> 00:04:44

construction which sometimes are often ill structured yet critical

00:04:44 --> 00:04:48

ingredients in the success of the project. So if we do not have a

00:04:48 --> 00:04:52

clear structuring of when are we going to need this piece of

00:04:52 --> 00:04:56

equipment, we might end up acquiring it too early, which is

00:04:56 --> 00:04:59

going to result in additional cost, or too late, which might

00:04:59 --> 00:04:59

result.

00:05:00 --> 00:05:04

In a delay to the project. Same thing applies to the materials. If

00:05:04 --> 00:05:06

there's a shortage of that material, we have to order it in

00:05:06 --> 00:05:10

advance. It might be a long lead item that needs a long time to

00:05:10 --> 00:05:14

manufacture or to get ready for delivery to the construction site.

00:05:14 --> 00:05:18

So we have to plan for the cost of storage and storage conditions and

00:05:18 --> 00:05:22

so on and so forth. Or are we going to the to rely on just in

00:05:22 --> 00:05:26

time delivery to the construction site at the time when the activity

00:05:26 --> 00:05:30

is going to be performed, therefore not needing any storage.

00:05:31 --> 00:05:35

Of course, the danger with just in time planning is that if you need

00:05:35 --> 00:05:38

it right now and it's not delivered right now, that means

00:05:38 --> 00:05:41

that you're going to have a delay. We need to consider the

00:05:41 --> 00:05:44

constraints of the site and the influence of selected technology

00:05:44 --> 00:05:49

on schedule and cost. So again, constraints of the site could be

00:05:49 --> 00:05:53

either logistical constraints like access to the site, for example,

00:05:53 --> 00:05:56

it could be political constraints. It could be other

00:05:57 --> 00:06:01

other constraints that might affect the site. So weather

00:06:01 --> 00:06:04

constraints, for example, maybe there are some activities that

00:06:04 --> 00:06:09

have to be done in a dry environment. So if it rains, we

00:06:09 --> 00:06:13

cannot perform them. The tower train should not be working when

00:06:13 --> 00:06:16

the wind speed exceeds a certain speed, and things like that. So

00:06:16 --> 00:06:19

we're going to look at the meteorological reports from

00:06:19 --> 00:06:23

previous years to try to identify what are the constraints that are

00:06:23 --> 00:06:26

going to be imposed on our construction activities,

00:06:28 --> 00:06:32

to identify the list activities. Activities represent the necessary

00:06:32 --> 00:06:36

framework to permit scheduling, along with estimating the

00:06:36 --> 00:06:39

resources required by the individual activities. So we

00:06:39 --> 00:06:43

again, that's why we need to have clear distinction. What is this

00:06:43 --> 00:06:47

activity, what amount of work is going to be associated with that

00:06:47 --> 00:06:51

activity? What kind of resources are going to be needed in what

00:06:51 --> 00:06:54

amount and what's the cost of these resources, what's the

00:06:54 --> 00:06:57

production rate of these resources? All of these details

00:06:57 --> 00:07:01

are got to be required for each activity that's gone. That's why

00:07:01 --> 00:07:05

we might end up having having something like a an activity form

00:07:05 --> 00:07:07

that shows the name of the activity, its location, who's

00:07:07 --> 00:07:10

responsible for it, what kind of resources are going to be

00:07:10 --> 00:07:14

involved? What are the rates of application, or rates or for

00:07:14 --> 00:07:18

performance of these resources? And that leads, at the end to the

00:07:18 --> 00:07:21

duration of the activity and the cost of the activity.

00:07:25 --> 00:07:28

The set of activities defined for a project should be comprehensive,

00:07:28 --> 00:07:31

but not too refined, because, again, there's a very high

00:07:31 --> 00:07:36

likelihood that we might end up adding activities or consolidating

00:07:36 --> 00:07:40

some other activities. So basically, we're going to think

00:07:40 --> 00:07:44

creatively based on our experience. How did we do it in

00:07:44 --> 00:07:47

the past? And we're gonna develop a set of activities. But again,

00:07:47 --> 00:07:51

have an open mind for the possibility of adding additional

00:07:51 --> 00:07:55

activities if, for example, the activity duration exceeds, let's

00:07:55 --> 00:07:59

say, a couple of weeks, maybe we need to break it down into two. Or

00:07:59 --> 00:08:03

if the duration of the activity is less than one day. Maybe we need

00:08:03 --> 00:08:07

to consolidate it with another activity to be more meaningful.

00:08:08 --> 00:08:11

Construction plans can easily range between less than 100

00:08:13 --> 00:08:18

activities to several 1000 defined tasks. And again, we are usually

00:08:18 --> 00:08:24

going to start with a very summarized schedule, or collapsed

00:08:24 --> 00:08:28

schedule, that's going to have the main milestones. When do I need to

00:08:28 --> 00:08:31

start work, the notice to proceed. When do I need to finish the

00:08:31 --> 00:08:35

underground work? When do I need to finish the skeleton, the

00:08:35 --> 00:08:38

topping off of a steel structure, or the completion of the concrete

00:08:38 --> 00:08:43

structure, for example? When do I need to have enclosed the building

00:08:43 --> 00:08:46

to start the dry work inside the building and so on and so forth?

00:08:46 --> 00:08:50

When is going to be my substantial completion? When it's going to be

00:08:50 --> 00:08:54

my final completion? So we are identifying major milestones in

00:08:54 --> 00:08:57

the project, and that's going to be my main initial schedule. And

00:08:57 --> 00:09:00

then I'm going to fill in the blanks, so this is like a

00:09:00 --> 00:09:04

skeleton, and then I'm going to add the flesh and the skin and all

00:09:04 --> 00:09:06

the other details to that schedule.

00:09:10 --> 00:09:14

Typically, each design element in the plant facility will have one

00:09:14 --> 00:09:18

or more associated project activities. So the foundations are

00:09:18 --> 00:09:21

going to have probably more than one activity. The walls are going

00:09:21 --> 00:09:26

to have more than one activity. The HVAC AC system is going to

00:09:26 --> 00:09:29

have more than one activity, and so on and so forth. Those

00:09:29 --> 00:09:32

activities will involve different resources, or those activities

00:09:32 --> 00:09:37

that do not require continuous the two types, two major types here,

00:09:37 --> 00:09:41

activities that involve different resources, like any production

00:09:41 --> 00:09:45

activity, for example, or any procurement activity, and those

00:09:45 --> 00:09:48

activities that do not require any continuous performance, like

00:09:48 --> 00:09:52

submittals, one of the activities is to submit a sample to the

00:09:52 --> 00:09:55

Arctic engineer for review and approval or reviews. We're going

00:09:55 --> 00:09:59

to have a review of a certain document, or we're going to have

00:09:59 --> 00:09:59

an inspection.

00:10:00 --> 00:10:01

Or something like that.

00:10:03 --> 00:10:07

Building Element Classification can be used as a guidance to list

00:10:08 --> 00:10:12

group major building activities. So we're going to have

00:10:12 --> 00:10:17

foundations, superstructure, mechanical system, electrical

00:10:17 --> 00:10:22

system, etc. These could be major classifications under which I'm

00:10:22 --> 00:10:25

going to break them down into smaller entities until I reach the

00:10:25 --> 00:10:29

level of activities. So here, for example, is one of the formats.

00:10:29 --> 00:10:33

It's called the Uniformat, and it's sometimes used in estimating

00:10:33 --> 00:10:36

and embedding as well as in scheduling. So here, for example,

00:10:36 --> 00:10:41

we have the structure, the substructure, the shell interiors,

00:10:41 --> 00:10:44

services, etc, and each one of them shows

00:10:46 --> 00:10:49

little bit more level of detail. So the substructure is going to

00:10:49 --> 00:10:53

have foundations and basement construction. It could also

00:10:53 --> 00:10:58

include any infrastructure, utilities, pipes, cables, etc. And

00:10:58 --> 00:11:02

then we can break it down even further into standard Foundation,

00:11:02 --> 00:11:06

special foundations, slab on grade, basement excavation,

00:11:06 --> 00:11:10

basement walls and so on. Each one of these can be further broken

00:11:10 --> 00:11:14

down so standard foundations we're going to have basically maybe form

00:11:14 --> 00:11:15

work, rebar,

00:11:17 --> 00:11:20

concrete, and then back filling and

00:11:22 --> 00:11:26

beams connecting these different foundations, or pile caps for

00:11:26 --> 00:11:29

piles and things like that. All of these are going to be different

00:11:29 --> 00:11:31

details for each one of these activities.

00:11:32 --> 00:11:36

Another method, which most of you are probably more familiar with is

00:11:36 --> 00:11:40

the master format. The Master format used to be known as 16

00:11:40 --> 00:11:44

divisions in the past, that is what most contractors are familiar

00:11:44 --> 00:11:47

with. And then the construction specifications Institute, or the

00:11:47 --> 00:11:51

CSI, which is the body that developed both the Uniformat and

00:11:51 --> 00:11:55

the master format, came up with a newer format in 2004

00:11:56 --> 00:12:00

instead of the 16 divisions. Now it's anywhere between 48 and 49

00:12:01 --> 00:12:04

divisions. So they broke down these divisions into more details,

00:12:05 --> 00:12:08

and there are some divisions that are still blank, reserved for

00:12:08 --> 00:12:10

further addition, like 3637 3839

00:12:11 --> 00:12:15

there is nothing in there, but something can be added in the

00:12:15 --> 00:12:18

future to this set of specification,

00:12:21 --> 00:12:27

our vehicle to convert the big project into the major tasks until

00:12:27 --> 00:12:30

we reach the level of details, is called the work breakdown

00:12:30 --> 00:12:35

structure, or WBS. This is a very important tool to dissect the

00:12:35 --> 00:12:39

project until we reach the level of work packages, which can be

00:12:39 --> 00:12:43

broken down later on into activities. So a project work

00:12:43 --> 00:12:47

breakdown structure is a deliverable or product oriented

00:12:47 --> 00:12:51

grouping of project work elements showing shown in graphical display

00:12:52 --> 00:12:56

to organize and subdivide the total work scope of the project.

00:12:56 --> 00:12:59

So basically, what we're saying here is that the work breakdown

00:12:59 --> 00:13:03

structure is a graphical translation of the scope of work

00:13:03 --> 00:13:07

of the project. It can be used as a planning tool and as a control

00:13:07 --> 00:13:11

tool as well, to make sure that we did not skip anything or forget

00:13:11 --> 00:13:15

anything in our planning for the project. It is not an activity

00:13:15 --> 00:13:19

listing. It stops one step short, or maybe two steps short of

00:13:19 --> 00:13:23

activity listing. So we stop at what's called a work package,

00:13:23 --> 00:13:28

which later on, can be broken down into activities. And it usually

00:13:28 --> 00:13:29

follows what's called the 15555,

00:13:31 --> 00:13:36

model, which means each entity is going to be broken down into five

00:13:36 --> 00:13:39

sub entities, and each one of these five, in turn, is going to

00:13:39 --> 00:13:42

be broken down in five. And which one of these is going to be broken

00:13:42 --> 00:13:47

down in five until we reach a comfortable level of detail.

00:13:47 --> 00:13:52

Again, it's not yet the activity level of detail one step higher,

00:13:52 --> 00:13:54

which we call the work package.

00:13:57 --> 00:14:01

So the decomposition of the total project work identifies the

00:14:01 --> 00:14:04

deliverables and the related work, and it follows a structure and

00:14:04 --> 00:14:10

organization, which is the WBS decomposes the dub the upper WBS

00:14:10 --> 00:14:14

levels into lower level, detailed components. One becomes five,

00:14:14 --> 00:14:18

developing and assigning identification codes to the WBS

00:14:18 --> 00:14:22

components because we're going to use these for scheduling later on,

00:14:22 --> 00:14:27

or with some modification, we can use them as cost accounts for our

00:14:27 --> 00:14:30

cost accounting for the project. In this case, instead of being

00:14:30 --> 00:14:35

called WBS, it's going to be called CBS, or the cost breakdown

00:14:35 --> 00:14:39

structure similar to that as well. If you can imagine something like

00:14:39 --> 00:14:43

an organization chart that shows at the top the president of the

00:14:43 --> 00:14:47

CEO and the vice presidents, and then the directors and going going

00:14:47 --> 00:14:50

down until you reach the field personnel. This is called an

00:14:50 --> 00:14:56

organizational breakdown structure, or OBS. So these three,

00:14:56 --> 00:14:59

the WBS, the CBS and the OBS.

00:15:00 --> 00:15:05

Us break down one big idea into smaller levels that are even more

00:15:05 --> 00:15:09

manageable and controllable, verifying that the degree of the

00:15:09 --> 00:15:10

composition is

00:15:11 --> 00:15:16

necessary and sufficient. So again, this is a tool for review

00:15:16 --> 00:15:20

and for control, to make sure that everything in the scope of work

00:15:20 --> 00:15:24

has been adequately covered in that work breakdown structure.

00:15:26 --> 00:15:30

The work breakdown structure includes 100% of the work defined

00:15:30 --> 00:15:35

by the project scope and captures all deliverables. It focuses on

00:15:35 --> 00:15:38

deliverables, not activities, as we just mentioned, that's why it

00:15:38 --> 00:15:43

stops at a work package activities can be created based on these work

00:15:43 --> 00:15:46

packages or based on these deliverables.

00:15:47 --> 00:15:51

To show you the flow of that work breakdown structure, we started

00:15:51 --> 00:15:56

with level one house. That's the project that I want to build. I

00:15:56 --> 00:16:01

broke down that house into a following layer. Again, we call it

00:16:01 --> 00:16:01

15555,

00:16:02 --> 00:16:04

but that's not carved in stone. It could be 14736,

00:16:08 --> 00:16:11

and so on, but it's not going to be 120,

00:16:12 --> 00:16:17

100 so it's going to be a gradual transition from one level to

00:16:18 --> 00:16:22

another layer to a third layer, etc. So we have here the site

00:16:22 --> 00:16:27

preparation, footings and foundations, land design, etc.

00:16:27 --> 00:16:30

Framing the footings and foundations going to include

00:16:30 --> 00:16:36

framing, roofing, utilities, etc. So again, you can break down each

00:16:36 --> 00:16:41

one of these levels into further details until we reach a work

00:16:42 --> 00:16:43

package level.

00:16:45 --> 00:16:48

Now we can see here, for example, coding system,

00:16:50 --> 00:16:55

Acme motors expansion. The name is am Acme motors, and then the

00:16:55 --> 00:17:02

automated system is am 01 conveyor system, am 02 office building, am

00:17:02 --> 00:17:06

03 and then you can break that down, design on engineering of the

00:17:06 --> 00:17:11

office building. So it's going to be am o3 1am, o3 four, and so on.

00:17:11 --> 00:17:15

Each one of these can be broken down, so it's going to be am 03401

00:17:17 --> 00:17:18

and so on.

00:17:21 --> 00:17:25

That's another example of how a work breakdown structure is going

00:17:25 --> 00:17:26

to look like.

00:17:28 --> 00:17:33

And we're going to finish here at the end, at the work tasks, which

00:17:33 --> 00:17:36

can be broken down into activities that usually do not show on the

00:17:36 --> 00:17:38

work breakdown structure.

00:17:40 --> 00:17:43

Now from these works, work packages, we're going to break

00:17:43 --> 00:17:47

that them down into activities. And each activity is going to be

00:17:47 --> 00:17:49

represented by a verb and a noun,

00:17:50 --> 00:17:55

installed carpet, paint wall, place or pour concrete and so on.

00:17:56 --> 00:17:59

So there are three typical types of activities, either a

00:17:59 --> 00:18:05

procurement activity, which is purchasing or contracting to get

00:18:05 --> 00:18:09

steel or to get mechanical equipment or to get elevators or

00:18:09 --> 00:18:14

electrical supplies or concrete production, which is the heart of

00:18:14 --> 00:18:21

the construction schedule, placing that concrete and management so

00:18:21 --> 00:18:26

the required submittals, owner or engineer approval, testing and

00:18:26 --> 00:18:30

delays, which are not production or procurement activities, but

00:18:30 --> 00:18:34

they still form major milestones and flags and constraints in the

00:18:34 --> 00:18:38

project, therefore, we need to reflect them on the schedule. We

00:18:38 --> 00:18:41

also have something called milestones, which we mentioned

00:18:41 --> 00:18:45

initially. The project start is a major milestone. The project

00:18:45 --> 00:18:49

completion is a major milestone. The building encloses a milestone.

00:18:49 --> 00:18:53

Substantial completion is a milestone. And so on. These are

00:18:53 --> 00:18:58

zero duration activities. It just shows that this is the separation

00:18:58 --> 00:19:00

between the previous phase and the following phase

00:19:01 --> 00:19:04

flags. We have something called the flag, which is half of a

00:19:04 --> 00:19:08

milestone, start flag or finish flag. So if you look at the

00:19:08 --> 00:19:13

milestone, it can be split to two halves. There's going to be start

00:19:14 --> 00:19:19

Task, start flag, like, for example, the notice to proceed.

00:19:19 --> 00:19:23

Notice to proceed, is going to act as a milestone or as a start flag

00:19:23 --> 00:19:25

for the rest of the project and

00:19:27 --> 00:19:31

completion of submittals. This is going to be a finished flag. There

00:19:31 --> 00:19:35

could be a start flag for the submittals and a completion flag

00:19:35 --> 00:19:36

for the submittals and so on.

00:19:39 --> 00:19:43

Activities should include action related words, as we just said,

00:19:43 --> 00:19:46

words announced, procurement is going to include words like,

00:19:46 --> 00:19:50

fabricate, order, deliver. Production is going to include

00:19:50 --> 00:19:56

install, place, erect, paint, clean, demolish. Management is

00:19:56 --> 00:19:59

going to be submit, approve, Review.

00:20:00 --> 00:20:05

Apply for a payment or for a request for inspection or things

00:20:05 --> 00:20:06

like that.

00:20:08 --> 00:20:12

In addition to descriptions, activities usually have activity

00:20:12 --> 00:20:17

identifications or IDs, as we're going to see in the automated or

00:20:17 --> 00:20:22

the computerized schedule, we're gonna have an activity ID and an

00:20:22 --> 00:20:25

activity description separate from that ID. The IDs can show

00:20:25 --> 00:20:30

locations, trades and work types, etc, etc, if you're if we go back

00:20:30 --> 00:20:35

a couple of slides here, this is an activity ID, am 03, it could

00:20:35 --> 00:20:38

something like that. Basically, this is not an activity, but it

00:20:38 --> 00:20:43

can start. It can be the beginning of an activity. So if we go three

00:20:43 --> 00:20:45

levels below that, it's going to be AM, 0301,

00:20:47 --> 00:20:48

1225,

00:20:49 --> 00:20:51

for example, that could be an activity.

00:20:54 --> 00:20:57

And here's an example, the first four digits are going to be a

00:20:57 --> 00:21:00

serial number for a project and

00:21:02 --> 00:21:05

for example here, this is going to be a

00:21:06 --> 00:21:11

a master format, CSI code, heavyweight, structural concrete.

00:21:11 --> 00:21:17

And then 21 is the placement. And then it could be location

00:21:17 --> 00:21:21

responsibility, and then column number 34 at the end. So each one

00:21:21 --> 00:21:25

of these numbers represents something meaningful, and we're

00:21:25 --> 00:21:29

going to have sort of a dictionary for these activity IDs so that

00:21:29 --> 00:21:34

anyone who doesn't really know can follow the explanation and the

00:21:34 --> 00:21:38

description in that dictionary to understand what this activity

00:21:38 --> 00:21:39

stands for.

00:21:40 --> 00:21:41

Here's another example.

00:21:45 --> 00:21:50

So now that we have broken down the project into activities and

00:21:50 --> 00:21:54

identified each activity, we need to start thinking about the

00:21:54 --> 00:21:57

activity duration. The activity duration one more time is going to

00:21:57 --> 00:22:02

be obtained from our famous equation Q over P. So in practice,

00:22:02 --> 00:22:06

work test duration are determined by one or more of the following

00:22:06 --> 00:22:10

methods. Past experience. Either we have done this activity so many

00:22:10 --> 00:22:13

times in the past, so we can expect how long is it going to

00:22:13 --> 00:22:19

take? Estimates based on Q over P. Order, you have to finish this

00:22:19 --> 00:22:24

activity in five days, or something like that, or use of

00:22:24 --> 00:22:29

predictive models. If we do this activity this way, it's going to

00:22:29 --> 00:22:32

take that many days. If we do it that way, it's going to take that

00:22:32 --> 00:22:36

many days again. It's based on both past experience and

00:22:36 --> 00:22:37

estimates,

00:22:39 --> 00:22:43

and the activity duration can either be deterministic or

00:22:43 --> 00:22:46

probabilistic. Deterministic, which means there's only one

00:22:46 --> 00:22:50

duration for the activity obtained again from the equation Q over p,

00:22:50 --> 00:22:55

but probabilistic is there is some probability that we're not going

00:22:55 --> 00:22:58

to finish in that duration based on the conditions, based on the

00:22:58 --> 00:23:03

performance of the resources based on the availability of resources.

00:23:03 --> 00:23:07

So if we're looking at historical data, we may say we've done this

00:23:07 --> 00:23:12

activity 100 times in the past. 20% of the time it took extremely

00:23:12 --> 00:23:18

long. It took 10 days. 20% of the time it was really done in short

00:23:18 --> 00:23:24

time. It took only four days, but most of the time, in 80% or in 60%

00:23:25 --> 00:23:30

of the previous 100 times that we've done this activity, it took

00:23:30 --> 00:23:33

seven days. So now we have three different durations for the

00:23:33 --> 00:23:36

activity, four, which is the shortest, 10, which is the

00:23:36 --> 00:23:41

longest, and six or seven, which is the most repetitive from past

00:23:41 --> 00:23:45

experience. Which one are we gonna use to schedule the project? Now

00:23:45 --> 00:23:48

remember, this applies to every activity. If you have just 200

00:23:48 --> 00:23:51

activities in the schedule, and you keep adding these different

00:23:51 --> 00:23:55

probabilities, you're gonna end up with the lowest estimate, which is

00:23:55 --> 00:23:58

two months, and the longest estimate, which is 18 months. You

00:23:58 --> 00:24:02

definitely cannot go to the owner and say, Mr. Or Mrs. Owner, we're

00:24:02 --> 00:24:04

gonna finish your project in two months, or maybe in 18 that

00:24:05 --> 00:24:09

definitely is not gonna work. Therefore, we need to factor all

00:24:09 --> 00:24:13

of these probabilities to come up with something meaningful with a

00:24:13 --> 00:24:17

certain level of certainty. And this is basically what we're gonna

00:24:17 --> 00:24:21

discuss in a future lecture called probabilistic scheduling. And

00:24:21 --> 00:24:24

we're going to learn about the technique that we can apply to get

00:24:24 --> 00:24:27

one duration out of these three different durations for each

00:24:27 --> 00:24:27

activity

00:24:30 --> 00:24:35

with the deterministic task duration, the activity may have a

00:24:35 --> 00:24:39

fixed duration or a resource entity is to be captured for a

00:24:39 --> 00:24:45

specific time. So I'm gonna have this excavator available for only

00:24:45 --> 00:24:49

three days. Therefore I need to use it for a certain number of

00:24:49 --> 00:24:53

hours each day to finish that task. I have a fixed amount of

00:24:53 --> 00:24:56

work, and I know the production per hour. So how many hours per

00:24:56 --> 00:24:59

day? How many days? That's how I'm going to estimate.

00:25:00 --> 00:25:03

It the deterministic duration, the activity duration may be subject

00:25:03 --> 00:25:07

to small variations about the specific mean value, so that from

00:25:08 --> 00:25:12

any useful time scale, the work test duration is constant. The

00:25:12 --> 00:25:15

duration, again, is equal to quantity divided by production

00:25:15 --> 00:25:19

rate, Q over P that we have discussed so many times, so fast,

00:25:19 --> 00:25:23

so far. Now when we talk about probabilistic duration

00:25:23 --> 00:25:26

distributions, we're going to talk about this in more details, but

00:25:26 --> 00:25:29

you're going to find that we have something called the mean or the

00:25:29 --> 00:25:33

most likely duration, and we're going to have something called the

00:25:33 --> 00:25:36

optimistic duration, which is the shortest possible, and the

00:25:36 --> 00:25:39

pessimistic duration which is the longest possible. We're going to

00:25:39 --> 00:25:43

see an equation based on statistics. How can we factor all

00:25:43 --> 00:25:47

of these three into one duration for the activity? Basically,

00:25:47 --> 00:25:51

basically converting determine probabilistic into as much

00:25:51 --> 00:25:53

deterministic as possible?

00:25:56 --> 00:25:59

We're going to use something called production table, or

00:25:59 --> 00:26:02

product productivity tables. You can find some of these in the

00:26:02 --> 00:26:05

means book, for example, or in the walker book for estimating. And

00:26:05 --> 00:26:10

definitely, I will always suggest that each company builds its own

00:26:10 --> 00:26:14

production tables, or productivity tables based on its own resources,

00:26:14 --> 00:26:18

whether it subcontractors or equipment or labor or materials,

00:26:18 --> 00:26:22

etc. So the productivity table is going to show you, for example,

00:26:22 --> 00:26:27

that if the masonry unit size is eight inch blocks, with no

00:26:27 --> 00:26:32

conditions, then you can produce up to 400 units per day per Mason.

00:26:32 --> 00:26:36

So knowing what's the total number of units that we need to place, we

00:26:36 --> 00:26:39

can divide it by the number of masons and get the number of days

00:26:39 --> 00:26:42

that's going to be needed and so on. So you can see different

00:26:42 --> 00:26:47

conditions. And if the wall is long, then definitely we're going

00:26:47 --> 00:26:50

to have more production, because you're going to have minimum

00:26:50 --> 00:26:55

interruptions. So we can achieve 430 units per day per Mason. If

00:26:55 --> 00:26:58

the wall is not long, if it's a short wall with corners and a lot

00:26:58 --> 00:27:01

of interruptions and so on, that's going to reduce our production

00:27:01 --> 00:27:05

rate to 370, units per day, per meter. So based on these

00:27:05 --> 00:27:09

productivity tables, we can estimate the duration of the

00:27:09 --> 00:27:09

activity.

00:27:11 --> 00:27:14

This is a quick review of the durations between activity, the

00:27:14 --> 00:27:17

relationships between activities we discussed before the finish to

00:27:17 --> 00:27:21

start, which is the most common relationship, also known as

00:27:21 --> 00:27:24

traditional relationship. And we may add here between the two

00:27:24 --> 00:27:27

activities a positive number that's going to be a lag, or a

00:27:27 --> 00:27:31

negative number that's going to be an overlap. We also have the start

00:27:31 --> 00:27:35

to start relationship where and again, here we can add a lag

00:27:35 --> 00:27:39

between the two activities. It can be with or without lag the finish

00:27:39 --> 00:27:42

to finish. Same thing connects the finishes or the ends of the

00:27:42 --> 00:27:46

activity. It can either have lag or without lag. And the fourth

00:27:46 --> 00:27:51

one, which is the start to finish, as we discussed before, very rare

00:27:51 --> 00:27:55

in its use, and usually it might have either legs or no legs, that

00:27:55 --> 00:27:57

it can go either way

00:28:00 --> 00:28:03

between the activities. Again, we talked about legs and overlap, so

00:28:03 --> 00:28:06

the legs going to be a positive number, whereas the overlap is

00:28:06 --> 00:28:08

going to be a negative number.

00:28:10 --> 00:28:14

So basically, this is a quick introduction about how to build a

00:28:14 --> 00:28:19

schedule. So we're going to see some exercises that we're going to

00:28:19 --> 00:28:23

be working on taking a project, how are we going to break it down

00:28:23 --> 00:28:28

into activities or work packages, and then develop an activity list

00:28:28 --> 00:28:33

based on that, to start our activity list and then add the

00:28:33 --> 00:28:36

sequencing of the activities, add the durations of the activities,

00:28:36 --> 00:28:40

and then calculate our schedule based on the algorithms of the

00:28:40 --> 00:28:43

critical path method. I will see you in the next lecture. You.

Share Page