Ihab Saad – Developing the schedule

Ihab Saad
Share Page

AI: Summary ©

The speakers discuss the importance of identifying and breaking down a project to determine the activities needed to achieve the project. They stress the need for clear distinction in order to avoid delays and consider resource and technology constraints when scheduling a project. The process of identifying and breaking down the project involves identifying and breaking down each activity and identifying and breaking down the project for each classifications. The speakers also discuss the use of technology and the constraints surrounding the project, including logistical, political, and cultural constraints. They outline the process of breaking down the project for each activity and identifying and breaking down the project for each classifications. The importance of finding the right duration for each activity and using productivity tables to estimate the work test duration is emphasized.

AI: Summary ©

00:00:06 --> 00:00:10
			Hello. Today, we're going to learn
about building the schedule. What
		
00:00:10 --> 00:00:13
			do we mean by building the
schedule, and how to break down a
		
00:00:13 --> 00:00:17
			big project into smaller
components, along which lines and
		
00:00:17 --> 00:00:20
			how many activities should a
project have, and so on and so
		
00:00:20 --> 00:00:24
			forth. So basically, what we're
going to discuss is how to
		
00:00:24 --> 00:00:28
			identify the activities in a
project, how to determine the
		
00:00:28 --> 00:00:32
			activity durations and the
relationships among the activities
		
00:00:32 --> 00:00:35
			and linking them and so on. This
is going to be a review of what we
		
00:00:35 --> 00:00:38
			learned before about the different
types of relationships and so on.
		
00:00:38 --> 00:00:43
			But we're going to talk primarily
about the first task in schedule
		
00:00:43 --> 00:00:47
			development, which is activity
definition, how to break down the
		
00:00:47 --> 00:00:49
			project into activities.
		
00:00:51 --> 00:00:55
			So construction planning can be
either cost oriented or schedule
		
00:00:55 --> 00:00:59
			oriented. And to give an example
on that, the cost oriented is
		
00:00:59 --> 00:01:02
			going to look at the direct costs
and the indirect costs. The direct
		
00:01:02 --> 00:01:06
			costs are basically costs involved
directly in the construction
		
00:01:06 --> 00:01:10
			operation on site, whereas
indirect costs are going to be
		
00:01:10 --> 00:01:13
			costs needed to be spent on the
project, but not necessarily
		
00:01:13 --> 00:01:18
			related to any particular
activity. So for example, if you
		
00:01:18 --> 00:01:19
			have
		
00:01:21 --> 00:01:24
			a central purchasing department at
the headquarters of the company.
		
00:01:25 --> 00:01:28
			This purchasing department is
working on all projects or any
		
00:01:28 --> 00:01:31
			scheduling department, or any
Central Department, the legal
		
00:01:31 --> 00:01:35
			department, for example, you
cannot pinpoint and say they work
		
00:01:35 --> 00:01:39
			that long on this particular
project or that project. So it's
		
00:01:39 --> 00:01:43
			going to be a general overhead for
the head office, whereas direct
		
00:01:43 --> 00:01:45
			costs are going to be the cost of
the people assigned to the
		
00:01:45 --> 00:01:49
			construction site, field
engineers, Superintendent, project
		
00:01:49 --> 00:01:53
			manager, etc. When we look at the
time aspect of the project, the
		
00:01:53 --> 00:01:59
			schedule oriented idea, we have
time oriented, which is going to
		
00:01:59 --> 00:02:03
			be developing the critical path of
the project and resource oriented
		
00:02:03 --> 00:02:07
			which is going to be, what kind of
resources do we need? When are we
		
00:02:07 --> 00:02:10
			going to need them in what amount,
and so on and so forth.
		
00:02:11 --> 00:02:15
			This resource oriented planning is
going to be sort of joint between
		
00:02:16 --> 00:02:19
			the schedule oriented planning and
the cost oriented planning,
		
00:02:19 --> 00:02:23
			because, again, every resource has
its own cost, so we need to
		
00:02:23 --> 00:02:26
			calculate the cost of these
resources as well.
		
00:02:29 --> 00:02:33
			Before starting our scheduling
effort, we have to read the
		
00:02:33 --> 00:02:36
			specifications and the plans,
because, for example, the general
		
00:02:36 --> 00:02:40
			conditions of the contract are
going to have an effect on the
		
00:02:40 --> 00:02:44
			selection of the activity and the
sequencing of the activities and
		
00:02:44 --> 00:02:47
			the responsibilities and so on and
so forth. The staffing of the
		
00:02:47 --> 00:02:52
			project, of course, is going to be
also contingent upon, upon these
		
00:02:53 --> 00:02:56
			plans and specs, choosing the
appropriate technology, what kind
		
00:02:56 --> 00:02:59
			of technology is going to be
available in the project, location
		
00:03:00 --> 00:03:03
			and affordable to the company
that's going to be undertaking
		
00:03:03 --> 00:03:07
			that project, identifying and
listing activities. How are we
		
00:03:07 --> 00:03:12
			going to break down a huge
elephant like the project into
		
00:03:12 --> 00:03:17
			more manageable tasks or
activities the size of an ant
		
00:03:17 --> 00:03:21
			compared to that elephant, and
then calculating the activity
		
00:03:21 --> 00:03:24
			durations based on the resources
that are going to be identified
		
00:03:24 --> 00:03:28
			for each activity and the resource
availability, whether it's whether
		
00:03:28 --> 00:03:33
			it's money or materials,
equipment, subcontractors, etc,
		
00:03:33 --> 00:03:37
			and labor, identifying the
relationships between activities.
		
00:03:37 --> 00:03:41
			So which activity comes first,
what's going to be the predecessor
		
00:03:41 --> 00:03:44
			to what, what's going to be a
successor to what, which two
		
00:03:44 --> 00:03:49
			activities can be done at the same
time, and what kinds of lags and
		
00:03:49 --> 00:03:52
			overlaps, what's what kinds of
constraints are going to govern
		
00:03:52 --> 00:03:55
			the relationship between
activities? All of that has to be
		
00:03:55 --> 00:03:59
			involved. And then, once we
identify the relationships, after
		
00:04:00 --> 00:04:03
			breaking down the project into
activities. We have to link these
		
00:04:03 --> 00:04:07
			activities, and once we have
linked them, now we're going to
		
00:04:07 --> 00:04:10
			add the durations that we have
already calculated to calculate
		
00:04:10 --> 00:04:15
			the activity times and the project
duration based on the algorithm of
		
00:04:15 --> 00:04:18
			the critical path that we have
already learned about, early
		
00:04:18 --> 00:04:22
			start, early finish, late start,
late finish, total and free float,
		
00:04:22 --> 00:04:25
			which are going to be calculated
from the forward pass, the
		
00:04:25 --> 00:04:29
			backward pass and determining the
critical path of the project.
		
00:04:32 --> 00:04:36
			When we talk about the choice of
technology, it's the choices of
		
00:04:36 --> 00:04:39
			appropriate of appropriate
technology and methods for
		
00:04:39 --> 00:04:44
			construction which sometimes are
often ill structured yet critical
		
00:04:44 --> 00:04:48
			ingredients in the success of the
project. So if we do not have a
		
00:04:48 --> 00:04:52
			clear structuring of when are we
going to need this piece of
		
00:04:52 --> 00:04:56
			equipment, we might end up
acquiring it too early, which is
		
00:04:56 --> 00:04:59
			going to result in additional
cost, or too late, which might
		
00:04:59 --> 00:04:59
			result.
		
00:05:00 --> 00:05:04
			In a delay to the project. Same
thing applies to the materials. If
		
00:05:04 --> 00:05:06
			there's a shortage of that
material, we have to order it in
		
00:05:06 --> 00:05:10
			advance. It might be a long lead
item that needs a long time to
		
00:05:10 --> 00:05:14
			manufacture or to get ready for
delivery to the construction site.
		
00:05:14 --> 00:05:18
			So we have to plan for the cost of
storage and storage conditions and
		
00:05:18 --> 00:05:22
			so on and so forth. Or are we
going to the to rely on just in
		
00:05:22 --> 00:05:26
			time delivery to the construction
site at the time when the activity
		
00:05:26 --> 00:05:30
			is going to be performed,
therefore not needing any storage.
		
00:05:31 --> 00:05:35
			Of course, the danger with just in
time planning is that if you need
		
00:05:35 --> 00:05:38
			it right now and it's not
delivered right now, that means
		
00:05:38 --> 00:05:41
			that you're going to have a delay.
We need to consider the
		
00:05:41 --> 00:05:44
			constraints of the site and the
influence of selected technology
		
00:05:44 --> 00:05:49
			on schedule and cost. So again,
constraints of the site could be
		
00:05:49 --> 00:05:53
			either logistical constraints like
access to the site, for example,
		
00:05:53 --> 00:05:56
			it could be political constraints.
It could be other
		
00:05:57 --> 00:06:01
			other constraints that might
affect the site. So weather
		
00:06:01 --> 00:06:04
			constraints, for example, maybe
there are some activities that
		
00:06:04 --> 00:06:09
			have to be done in a dry
environment. So if it rains, we
		
00:06:09 --> 00:06:13
			cannot perform them. The tower
train should not be working when
		
00:06:13 --> 00:06:16
			the wind speed exceeds a certain
speed, and things like that. So
		
00:06:16 --> 00:06:19
			we're going to look at the
meteorological reports from
		
00:06:19 --> 00:06:23
			previous years to try to identify
what are the constraints that are
		
00:06:23 --> 00:06:26
			going to be imposed on our
construction activities,
		
00:06:28 --> 00:06:32
			to identify the list activities.
Activities represent the necessary
		
00:06:32 --> 00:06:36
			framework to permit scheduling,
along with estimating the
		
00:06:36 --> 00:06:39
			resources required by the
individual activities. So we
		
00:06:39 --> 00:06:43
			again, that's why we need to have
clear distinction. What is this
		
00:06:43 --> 00:06:47
			activity, what amount of work is
going to be associated with that
		
00:06:47 --> 00:06:51
			activity? What kind of resources
are going to be needed in what
		
00:06:51 --> 00:06:54
			amount and what's the cost of
these resources, what's the
		
00:06:54 --> 00:06:57
			production rate of these
resources? All of these details
		
00:06:57 --> 00:07:01
			are got to be required for each
activity that's gone. That's why
		
00:07:01 --> 00:07:05
			we might end up having having
something like a an activity form
		
00:07:05 --> 00:07:07
			that shows the name of the
activity, its location, who's
		
00:07:07 --> 00:07:10
			responsible for it, what kind of
resources are going to be
		
00:07:10 --> 00:07:14
			involved? What are the rates of
application, or rates or for
		
00:07:14 --> 00:07:18
			performance of these resources?
And that leads, at the end to the
		
00:07:18 --> 00:07:21
			duration of the activity and the
cost of the activity.
		
00:07:25 --> 00:07:28
			The set of activities defined for
a project should be comprehensive,
		
00:07:28 --> 00:07:31
			but not too refined, because,
again, there's a very high
		
00:07:31 --> 00:07:36
			likelihood that we might end up
adding activities or consolidating
		
00:07:36 --> 00:07:40
			some other activities. So
basically, we're going to think
		
00:07:40 --> 00:07:44
			creatively based on our
experience. How did we do it in
		
00:07:44 --> 00:07:47
			the past? And we're gonna develop
a set of activities. But again,
		
00:07:47 --> 00:07:51
			have an open mind for the
possibility of adding additional
		
00:07:51 --> 00:07:55
			activities if, for example, the
activity duration exceeds, let's
		
00:07:55 --> 00:07:59
			say, a couple of weeks, maybe we
need to break it down into two. Or
		
00:07:59 --> 00:08:03
			if the duration of the activity is
less than one day. Maybe we need
		
00:08:03 --> 00:08:07
			to consolidate it with another
activity to be more meaningful.
		
00:08:08 --> 00:08:11
			Construction plans can easily
range between less than 100
		
00:08:13 --> 00:08:18
			activities to several 1000 defined
tasks. And again, we are usually
		
00:08:18 --> 00:08:24
			going to start with a very
summarized schedule, or collapsed
		
00:08:24 --> 00:08:28
			schedule, that's going to have the
main milestones. When do I need to
		
00:08:28 --> 00:08:31
			start work, the notice to proceed.
When do I need to finish the
		
00:08:31 --> 00:08:35
			underground work? When do I need
to finish the skeleton, the
		
00:08:35 --> 00:08:38
			topping off of a steel structure,
or the completion of the concrete
		
00:08:38 --> 00:08:43
			structure, for example? When do I
need to have enclosed the building
		
00:08:43 --> 00:08:46
			to start the dry work inside the
building and so on and so forth?
		
00:08:46 --> 00:08:50
			When is going to be my substantial
completion? When it's going to be
		
00:08:50 --> 00:08:54
			my final completion? So we are
identifying major milestones in
		
00:08:54 --> 00:08:57
			the project, and that's going to
be my main initial schedule. And
		
00:08:57 --> 00:09:00
			then I'm going to fill in the
blanks, so this is like a
		
00:09:00 --> 00:09:04
			skeleton, and then I'm going to
add the flesh and the skin and all
		
00:09:04 --> 00:09:06
			the other details to that
schedule.
		
00:09:10 --> 00:09:14
			Typically, each design element in
the plant facility will have one
		
00:09:14 --> 00:09:18
			or more associated project
activities. So the foundations are
		
00:09:18 --> 00:09:21
			going to have probably more than
one activity. The walls are going
		
00:09:21 --> 00:09:26
			to have more than one activity.
The HVAC AC system is going to
		
00:09:26 --> 00:09:29
			have more than one activity, and
so on and so forth. Those
		
00:09:29 --> 00:09:32
			activities will involve different
resources, or those activities
		
00:09:32 --> 00:09:37
			that do not require continuous the
two types, two major types here,
		
00:09:37 --> 00:09:41
			activities that involve different
resources, like any production
		
00:09:41 --> 00:09:45
			activity, for example, or any
procurement activity, and those
		
00:09:45 --> 00:09:48
			activities that do not require any
continuous performance, like
		
00:09:48 --> 00:09:52
			submittals, one of the activities
is to submit a sample to the
		
00:09:52 --> 00:09:55
			Arctic engineer for review and
approval or reviews. We're going
		
00:09:55 --> 00:09:59
			to have a review of a certain
document, or we're going to have
		
00:09:59 --> 00:09:59
			an inspection.
		
00:10:00 --> 00:10:01
			Or something like that.
		
00:10:03 --> 00:10:07
			Building Element Classification
can be used as a guidance to list
		
00:10:08 --> 00:10:12
			group major building activities.
So we're going to have
		
00:10:12 --> 00:10:17
			foundations, superstructure,
mechanical system, electrical
		
00:10:17 --> 00:10:22
			system, etc. These could be major
classifications under which I'm
		
00:10:22 --> 00:10:25
			going to break them down into
smaller entities until I reach the
		
00:10:25 --> 00:10:29
			level of activities. So here, for
example, is one of the formats.
		
00:10:29 --> 00:10:33
			It's called the Uniformat, and
it's sometimes used in estimating
		
00:10:33 --> 00:10:36
			and embedding as well as in
scheduling. So here, for example,
		
00:10:36 --> 00:10:41
			we have the structure, the
substructure, the shell interiors,
		
00:10:41 --> 00:10:44
			services, etc, and each one of
them shows
		
00:10:46 --> 00:10:49
			little bit more level of detail.
So the substructure is going to
		
00:10:49 --> 00:10:53
			have foundations and basement
construction. It could also
		
00:10:53 --> 00:10:58
			include any infrastructure,
utilities, pipes, cables, etc. And
		
00:10:58 --> 00:11:02
			then we can break it down even
further into standard Foundation,
		
00:11:02 --> 00:11:06
			special foundations, slab on
grade, basement excavation,
		
00:11:06 --> 00:11:10
			basement walls and so on. Each one
of these can be further broken
		
00:11:10 --> 00:11:14
			down so standard foundations we're
going to have basically maybe form
		
00:11:14 --> 00:11:15
			work, rebar,
		
00:11:17 --> 00:11:20
			concrete, and then back filling
and
		
00:11:22 --> 00:11:26
			beams connecting these different
foundations, or pile caps for
		
00:11:26 --> 00:11:29
			piles and things like that. All of
these are going to be different
		
00:11:29 --> 00:11:31
			details for each one of these
activities.
		
00:11:32 --> 00:11:36
			Another method, which most of you
are probably more familiar with is
		
00:11:36 --> 00:11:40
			the master format. The Master
format used to be known as 16
		
00:11:40 --> 00:11:44
			divisions in the past, that is
what most contractors are familiar
		
00:11:44 --> 00:11:47
			with. And then the construction
specifications Institute, or the
		
00:11:47 --> 00:11:51
			CSI, which is the body that
developed both the Uniformat and
		
00:11:51 --> 00:11:55
			the master format, came up with a
newer format in 2004
		
00:11:56 --> 00:12:00
			instead of the 16 divisions. Now
it's anywhere between 48 and 49
		
00:12:01 --> 00:12:04
			divisions. So they broke down
these divisions into more details,
		
00:12:05 --> 00:12:08
			and there are some divisions that
are still blank, reserved for
		
00:12:08 --> 00:12:10
			further addition, like 3637 3839
		
00:12:11 --> 00:12:15
			there is nothing in there, but
something can be added in the
		
00:12:15 --> 00:12:18
			future to this set of
specification,
		
00:12:21 --> 00:12:27
			our vehicle to convert the big
project into the major tasks until
		
00:12:27 --> 00:12:30
			we reach the level of details, is
called the work breakdown
		
00:12:30 --> 00:12:35
			structure, or WBS. This is a very
important tool to dissect the
		
00:12:35 --> 00:12:39
			project until we reach the level
of work packages, which can be
		
00:12:39 --> 00:12:43
			broken down later on into
activities. So a project work
		
00:12:43 --> 00:12:47
			breakdown structure is a
deliverable or product oriented
		
00:12:47 --> 00:12:51
			grouping of project work elements
showing shown in graphical display
		
00:12:52 --> 00:12:56
			to organize and subdivide the
total work scope of the project.
		
00:12:56 --> 00:12:59
			So basically, what we're saying
here is that the work breakdown
		
00:12:59 --> 00:13:03
			structure is a graphical
translation of the scope of work
		
00:13:03 --> 00:13:07
			of the project. It can be used as
a planning tool and as a control
		
00:13:07 --> 00:13:11
			tool as well, to make sure that we
did not skip anything or forget
		
00:13:11 --> 00:13:15
			anything in our planning for the
project. It is not an activity
		
00:13:15 --> 00:13:19
			listing. It stops one step short,
or maybe two steps short of
		
00:13:19 --> 00:13:23
			activity listing. So we stop at
what's called a work package,
		
00:13:23 --> 00:13:28
			which later on, can be broken down
into activities. And it usually
		
00:13:28 --> 00:13:29
			follows what's called the 15555,
		
00:13:31 --> 00:13:36
			model, which means each entity is
going to be broken down into five
		
00:13:36 --> 00:13:39
			sub entities, and each one of
these five, in turn, is going to
		
00:13:39 --> 00:13:42
			be broken down in five. And which
one of these is going to be broken
		
00:13:42 --> 00:13:47
			down in five until we reach a
comfortable level of detail.
		
00:13:47 --> 00:13:52
			Again, it's not yet the activity
level of detail one step higher,
		
00:13:52 --> 00:13:54
			which we call the work package.
		
00:13:57 --> 00:14:01
			So the decomposition of the total
project work identifies the
		
00:14:01 --> 00:14:04
			deliverables and the related work,
and it follows a structure and
		
00:14:04 --> 00:14:10
			organization, which is the WBS
decomposes the dub the upper WBS
		
00:14:10 --> 00:14:14
			levels into lower level, detailed
components. One becomes five,
		
00:14:14 --> 00:14:18
			developing and assigning
identification codes to the WBS
		
00:14:18 --> 00:14:22
			components because we're going to
use these for scheduling later on,
		
00:14:22 --> 00:14:27
			or with some modification, we can
use them as cost accounts for our
		
00:14:27 --> 00:14:30
			cost accounting for the project.
In this case, instead of being
		
00:14:30 --> 00:14:35
			called WBS, it's going to be
called CBS, or the cost breakdown
		
00:14:35 --> 00:14:39
			structure similar to that as well.
If you can imagine something like
		
00:14:39 --> 00:14:43
			an organization chart that shows
at the top the president of the
		
00:14:43 --> 00:14:47
			CEO and the vice presidents, and
then the directors and going going
		
00:14:47 --> 00:14:50
			down until you reach the field
personnel. This is called an
		
00:14:50 --> 00:14:56
			organizational breakdown
structure, or OBS. So these three,
		
00:14:56 --> 00:14:59
			the WBS, the CBS and the OBS.
		
00:15:00 --> 00:15:05
			Us break down one big idea into
smaller levels that are even more
		
00:15:05 --> 00:15:09
			manageable and controllable,
verifying that the degree of the
		
00:15:09 --> 00:15:10
			composition is
		
00:15:11 --> 00:15:16
			necessary and sufficient. So
again, this is a tool for review
		
00:15:16 --> 00:15:20
			and for control, to make sure that
everything in the scope of work
		
00:15:20 --> 00:15:24
			has been adequately covered in
that work breakdown structure.
		
00:15:26 --> 00:15:30
			The work breakdown structure
includes 100% of the work defined
		
00:15:30 --> 00:15:35
			by the project scope and captures
all deliverables. It focuses on
		
00:15:35 --> 00:15:38
			deliverables, not activities, as
we just mentioned, that's why it
		
00:15:38 --> 00:15:43
			stops at a work package activities
can be created based on these work
		
00:15:43 --> 00:15:46
			packages or based on these
deliverables.
		
00:15:47 --> 00:15:51
			To show you the flow of that work
breakdown structure, we started
		
00:15:51 --> 00:15:56
			with level one house. That's the
project that I want to build. I
		
00:15:56 --> 00:16:01
			broke down that house into a
following layer. Again, we call it
		
00:16:01 --> 00:16:01
			15555,
		
00:16:02 --> 00:16:04
			but that's not carved in stone. It
could be 14736,
		
00:16:08 --> 00:16:11
			and so on, but it's not going to
be 120,
		
00:16:12 --> 00:16:17
			100 so it's going to be a gradual
transition from one level to
		
00:16:18 --> 00:16:22
			another layer to a third layer,
etc. So we have here the site
		
00:16:22 --> 00:16:27
			preparation, footings and
foundations, land design, etc.
		
00:16:27 --> 00:16:30
			Framing the footings and
foundations going to include
		
00:16:30 --> 00:16:36
			framing, roofing, utilities, etc.
So again, you can break down each
		
00:16:36 --> 00:16:41
			one of these levels into further
details until we reach a work
		
00:16:42 --> 00:16:43
			package level.
		
00:16:45 --> 00:16:48
			Now we can see here, for example,
coding system,
		
00:16:50 --> 00:16:55
			Acme motors expansion. The name is
am Acme motors, and then the
		
00:16:55 --> 00:17:02
			automated system is am 01 conveyor
system, am 02 office building, am
		
00:17:02 --> 00:17:06
			03 and then you can break that
down, design on engineering of the
		
00:17:06 --> 00:17:11
			office building. So it's going to
be am o3 1am, o3 four, and so on.
		
00:17:11 --> 00:17:15
			Each one of these can be broken
down, so it's going to be am 03401
		
00:17:17 --> 00:17:18
			and so on.
		
00:17:21 --> 00:17:25
			That's another example of how a
work breakdown structure is going
		
00:17:25 --> 00:17:26
			to look like.
		
00:17:28 --> 00:17:33
			And we're going to finish here at
the end, at the work tasks, which
		
00:17:33 --> 00:17:36
			can be broken down into activities
that usually do not show on the
		
00:17:36 --> 00:17:38
			work breakdown structure.
		
00:17:40 --> 00:17:43
			Now from these works, work
packages, we're going to break
		
00:17:43 --> 00:17:47
			that them down into activities.
And each activity is going to be
		
00:17:47 --> 00:17:49
			represented by a verb and a noun,
		
00:17:50 --> 00:17:55
			installed carpet, paint wall,
place or pour concrete and so on.
		
00:17:56 --> 00:17:59
			So there are three typical types
of activities, either a
		
00:17:59 --> 00:18:05
			procurement activity, which is
purchasing or contracting to get
		
00:18:05 --> 00:18:09
			steel or to get mechanical
equipment or to get elevators or
		
00:18:09 --> 00:18:14
			electrical supplies or concrete
production, which is the heart of
		
00:18:14 --> 00:18:21
			the construction schedule, placing
that concrete and management so
		
00:18:21 --> 00:18:26
			the required submittals, owner or
engineer approval, testing and
		
00:18:26 --> 00:18:30
			delays, which are not production
or procurement activities, but
		
00:18:30 --> 00:18:34
			they still form major milestones
and flags and constraints in the
		
00:18:34 --> 00:18:38
			project, therefore, we need to
reflect them on the schedule. We
		
00:18:38 --> 00:18:41
			also have something called
milestones, which we mentioned
		
00:18:41 --> 00:18:45
			initially. The project start is a
major milestone. The project
		
00:18:45 --> 00:18:49
			completion is a major milestone.
The building encloses a milestone.
		
00:18:49 --> 00:18:53
			Substantial completion is a
milestone. And so on. These are
		
00:18:53 --> 00:18:58
			zero duration activities. It just
shows that this is the separation
		
00:18:58 --> 00:19:00
			between the previous phase and the
following phase
		
00:19:01 --> 00:19:04
			flags. We have something called
the flag, which is half of a
		
00:19:04 --> 00:19:08
			milestone, start flag or finish
flag. So if you look at the
		
00:19:08 --> 00:19:13
			milestone, it can be split to two
halves. There's going to be start
		
00:19:14 --> 00:19:19
			Task, start flag, like, for
example, the notice to proceed.
		
00:19:19 --> 00:19:23
			Notice to proceed, is going to act
as a milestone or as a start flag
		
00:19:23 --> 00:19:25
			for the rest of the project and
		
00:19:27 --> 00:19:31
			completion of submittals. This is
going to be a finished flag. There
		
00:19:31 --> 00:19:35
			could be a start flag for the
submittals and a completion flag
		
00:19:35 --> 00:19:36
			for the submittals and so on.
		
00:19:39 --> 00:19:43
			Activities should include action
related words, as we just said,
		
00:19:43 --> 00:19:46
			words announced, procurement is
going to include words like,
		
00:19:46 --> 00:19:50
			fabricate, order, deliver.
Production is going to include
		
00:19:50 --> 00:19:56
			install, place, erect, paint,
clean, demolish. Management is
		
00:19:56 --> 00:19:59
			going to be submit, approve,
Review.
		
00:20:00 --> 00:20:05
			Apply for a payment or for a
request for inspection or things
		
00:20:05 --> 00:20:06
			like that.
		
00:20:08 --> 00:20:12
			In addition to descriptions,
activities usually have activity
		
00:20:12 --> 00:20:17
			identifications or IDs, as we're
going to see in the automated or
		
00:20:17 --> 00:20:22
			the computerized schedule, we're
gonna have an activity ID and an
		
00:20:22 --> 00:20:25
			activity description separate from
that ID. The IDs can show
		
00:20:25 --> 00:20:30
			locations, trades and work types,
etc, etc, if you're if we go back
		
00:20:30 --> 00:20:35
			a couple of slides here, this is
an activity ID, am 03, it could
		
00:20:35 --> 00:20:38
			something like that. Basically,
this is not an activity, but it
		
00:20:38 --> 00:20:43
			can start. It can be the beginning
of an activity. So if we go three
		
00:20:43 --> 00:20:45
			levels below that, it's going to
be AM, 0301,
		
00:20:47 --> 00:20:48
			1225,
		
00:20:49 --> 00:20:51
			for example, that could be an
activity.
		
00:20:54 --> 00:20:57
			And here's an example, the first
four digits are going to be a
		
00:20:57 --> 00:21:00
			serial number for a project and
		
00:21:02 --> 00:21:05
			for example here, this is going to
be a
		
00:21:06 --> 00:21:11
			a master format, CSI code,
heavyweight, structural concrete.
		
00:21:11 --> 00:21:17
			And then 21 is the placement. And
then it could be location
		
00:21:17 --> 00:21:21
			responsibility, and then column
number 34 at the end. So each one
		
00:21:21 --> 00:21:25
			of these numbers represents
something meaningful, and we're
		
00:21:25 --> 00:21:29
			going to have sort of a dictionary
for these activity IDs so that
		
00:21:29 --> 00:21:34
			anyone who doesn't really know can
follow the explanation and the
		
00:21:34 --> 00:21:38
			description in that dictionary to
understand what this activity
		
00:21:38 --> 00:21:39
			stands for.
		
00:21:40 --> 00:21:41
			Here's another example.
		
00:21:45 --> 00:21:50
			So now that we have broken down
the project into activities and
		
00:21:50 --> 00:21:54
			identified each activity, we need
to start thinking about the
		
00:21:54 --> 00:21:57
			activity duration. The activity
duration one more time is going to
		
00:21:57 --> 00:22:02
			be obtained from our famous
equation Q over P. So in practice,
		
00:22:02 --> 00:22:06
			work test duration are determined
by one or more of the following
		
00:22:06 --> 00:22:10
			methods. Past experience. Either
we have done this activity so many
		
00:22:10 --> 00:22:13
			times in the past, so we can
expect how long is it going to
		
00:22:13 --> 00:22:19
			take? Estimates based on Q over P.
Order, you have to finish this
		
00:22:19 --> 00:22:24
			activity in five days, or
something like that, or use of
		
00:22:24 --> 00:22:29
			predictive models. If we do this
activity this way, it's going to
		
00:22:29 --> 00:22:32
			take that many days. If we do it
that way, it's going to take that
		
00:22:32 --> 00:22:36
			many days again. It's based on
both past experience and
		
00:22:36 --> 00:22:37
			estimates,
		
00:22:39 --> 00:22:43
			and the activity duration can
either be deterministic or
		
00:22:43 --> 00:22:46
			probabilistic. Deterministic,
which means there's only one
		
00:22:46 --> 00:22:50
			duration for the activity obtained
again from the equation Q over p,
		
00:22:50 --> 00:22:55
			but probabilistic is there is some
probability that we're not going
		
00:22:55 --> 00:22:58
			to finish in that duration based
on the conditions, based on the
		
00:22:58 --> 00:23:03
			performance of the resources based
on the availability of resources.
		
00:23:03 --> 00:23:07
			So if we're looking at historical
data, we may say we've done this
		
00:23:07 --> 00:23:12
			activity 100 times in the past.
20% of the time it took extremely
		
00:23:12 --> 00:23:18
			long. It took 10 days. 20% of the
time it was really done in short
		
00:23:18 --> 00:23:24
			time. It took only four days, but
most of the time, in 80% or in 60%
		
00:23:25 --> 00:23:30
			of the previous 100 times that
we've done this activity, it took
		
00:23:30 --> 00:23:33
			seven days. So now we have three
different durations for the
		
00:23:33 --> 00:23:36
			activity, four, which is the
shortest, 10, which is the
		
00:23:36 --> 00:23:41
			longest, and six or seven, which
is the most repetitive from past
		
00:23:41 --> 00:23:45
			experience. Which one are we gonna
use to schedule the project? Now
		
00:23:45 --> 00:23:48
			remember, this applies to every
activity. If you have just 200
		
00:23:48 --> 00:23:51
			activities in the schedule, and
you keep adding these different
		
00:23:51 --> 00:23:55
			probabilities, you're gonna end up
with the lowest estimate, which is
		
00:23:55 --> 00:23:58
			two months, and the longest
estimate, which is 18 months. You
		
00:23:58 --> 00:24:02
			definitely cannot go to the owner
and say, Mr. Or Mrs. Owner, we're
		
00:24:02 --> 00:24:04
			gonna finish your project in two
months, or maybe in 18 that
		
00:24:05 --> 00:24:09
			definitely is not gonna work.
Therefore, we need to factor all
		
00:24:09 --> 00:24:13
			of these probabilities to come up
with something meaningful with a
		
00:24:13 --> 00:24:17
			certain level of certainty. And
this is basically what we're gonna
		
00:24:17 --> 00:24:21
			discuss in a future lecture called
probabilistic scheduling. And
		
00:24:21 --> 00:24:24
			we're going to learn about the
technique that we can apply to get
		
00:24:24 --> 00:24:27
			one duration out of these three
different durations for each
		
00:24:27 --> 00:24:27
			activity
		
00:24:30 --> 00:24:35
			with the deterministic task
duration, the activity may have a
		
00:24:35 --> 00:24:39
			fixed duration or a resource
entity is to be captured for a
		
00:24:39 --> 00:24:45
			specific time. So I'm gonna have
this excavator available for only
		
00:24:45 --> 00:24:49
			three days. Therefore I need to
use it for a certain number of
		
00:24:49 --> 00:24:53
			hours each day to finish that
task. I have a fixed amount of
		
00:24:53 --> 00:24:56
			work, and I know the production
per hour. So how many hours per
		
00:24:56 --> 00:24:59
			day? How many days? That's how I'm
going to estimate.
		
00:25:00 --> 00:25:03
			It the deterministic duration, the
activity duration may be subject
		
00:25:03 --> 00:25:07
			to small variations about the
specific mean value, so that from
		
00:25:08 --> 00:25:12
			any useful time scale, the work
test duration is constant. The
		
00:25:12 --> 00:25:15
			duration, again, is equal to
quantity divided by production
		
00:25:15 --> 00:25:19
			rate, Q over P that we have
discussed so many times, so fast,
		
00:25:19 --> 00:25:23
			so far. Now when we talk about
probabilistic duration
		
00:25:23 --> 00:25:26
			distributions, we're going to talk
about this in more details, but
		
00:25:26 --> 00:25:29
			you're going to find that we have
something called the mean or the
		
00:25:29 --> 00:25:33
			most likely duration, and we're
going to have something called the
		
00:25:33 --> 00:25:36
			optimistic duration, which is the
shortest possible, and the
		
00:25:36 --> 00:25:39
			pessimistic duration which is the
longest possible. We're going to
		
00:25:39 --> 00:25:43
			see an equation based on
statistics. How can we factor all
		
00:25:43 --> 00:25:47
			of these three into one duration
for the activity? Basically,
		
00:25:47 --> 00:25:51
			basically converting determine
probabilistic into as much
		
00:25:51 --> 00:25:53
			deterministic as possible?
		
00:25:56 --> 00:25:59
			We're going to use something
called production table, or
		
00:25:59 --> 00:26:02
			product productivity tables. You
can find some of these in the
		
00:26:02 --> 00:26:05
			means book, for example, or in the
walker book for estimating. And
		
00:26:05 --> 00:26:10
			definitely, I will always suggest
that each company builds its own
		
00:26:10 --> 00:26:14
			production tables, or productivity
tables based on its own resources,
		
00:26:14 --> 00:26:18
			whether it subcontractors or
equipment or labor or materials,
		
00:26:18 --> 00:26:22
			etc. So the productivity table is
going to show you, for example,
		
00:26:22 --> 00:26:27
			that if the masonry unit size is
eight inch blocks, with no
		
00:26:27 --> 00:26:32
			conditions, then you can produce
up to 400 units per day per Mason.
		
00:26:32 --> 00:26:36
			So knowing what's the total number
of units that we need to place, we
		
00:26:36 --> 00:26:39
			can divide it by the number of
masons and get the number of days
		
00:26:39 --> 00:26:42
			that's going to be needed and so
on. So you can see different
		
00:26:42 --> 00:26:47
			conditions. And if the wall is
long, then definitely we're going
		
00:26:47 --> 00:26:50
			to have more production, because
you're going to have minimum
		
00:26:50 --> 00:26:55
			interruptions. So we can achieve
430 units per day per Mason. If
		
00:26:55 --> 00:26:58
			the wall is not long, if it's a
short wall with corners and a lot
		
00:26:58 --> 00:27:01
			of interruptions and so on, that's
going to reduce our production
		
00:27:01 --> 00:27:05
			rate to 370, units per day, per
meter. So based on these
		
00:27:05 --> 00:27:09
			productivity tables, we can
estimate the duration of the
		
00:27:09 --> 00:27:09
			activity.
		
00:27:11 --> 00:27:14
			This is a quick review of the
durations between activity, the
		
00:27:14 --> 00:27:17
			relationships between activities
we discussed before the finish to
		
00:27:17 --> 00:27:21
			start, which is the most common
relationship, also known as
		
00:27:21 --> 00:27:24
			traditional relationship. And we
may add here between the two
		
00:27:24 --> 00:27:27
			activities a positive number
that's going to be a lag, or a
		
00:27:27 --> 00:27:31
			negative number that's going to be
an overlap. We also have the start
		
00:27:31 --> 00:27:35
			to start relationship where and
again, here we can add a lag
		
00:27:35 --> 00:27:39
			between the two activities. It can
be with or without lag the finish
		
00:27:39 --> 00:27:42
			to finish. Same thing connects the
finishes or the ends of the
		
00:27:42 --> 00:27:46
			activity. It can either have lag
or without lag. And the fourth
		
00:27:46 --> 00:27:51
			one, which is the start to finish,
as we discussed before, very rare
		
00:27:51 --> 00:27:55
			in its use, and usually it might
have either legs or no legs, that
		
00:27:55 --> 00:27:57
			it can go either way
		
00:28:00 --> 00:28:03
			between the activities. Again, we
talked about legs and overlap, so
		
00:28:03 --> 00:28:06
			the legs going to be a positive
number, whereas the overlap is
		
00:28:06 --> 00:28:08
			going to be a negative number.
		
00:28:10 --> 00:28:14
			So basically, this is a quick
introduction about how to build a
		
00:28:14 --> 00:28:19
			schedule. So we're going to see
some exercises that we're going to
		
00:28:19 --> 00:28:23
			be working on taking a project,
how are we going to break it down
		
00:28:23 --> 00:28:28
			into activities or work packages,
and then develop an activity list
		
00:28:28 --> 00:28:33
			based on that, to start our
activity list and then add the
		
00:28:33 --> 00:28:36
			sequencing of the activities, add
the durations of the activities,
		
00:28:36 --> 00:28:40
			and then calculate our schedule
based on the algorithms of the
		
00:28:40 --> 00:28:43
			critical path method. I will see
you in the next lecture. You.