Ihab Saad – Concrete and Masonry Operations I

Ihab Saad
AI: Summary ©
The speakers discuss various safety measures and construction practices for workers in construction context, including protection measures and hazards such as post-tensioning work, workers near equipment, and potential damage to infrastructure. The use of shoring and sills is recommended for maximum load and regular inspections and repairs are required. The importance of proper safety measures and proper construction practices is emphasized.
AI: Transcript ©
00:00:00 --> 00:00:00

Steve,

00:00:01 --> 00:00:05

hello and welcome to another lecture on integrity, on

00:00:06 --> 00:00:10

construction safety. Today we talk about concrete and masonry safety.

00:00:11 --> 00:00:14

This is a long lecture, so we're going to divide it into two parts.

00:00:14 --> 00:00:17

One part is going to talk about concrete and the other part is

00:00:17 --> 00:00:20

going to talk about masonry. So what do we need to know about

00:00:20 --> 00:00:23

concrete and masonry, a lot of activities take place in concrete

00:00:23 --> 00:00:26

and masonry construction, and these can be very hazardous if

00:00:27 --> 00:00:30

attention and care are not taken into consideration.

00:00:31 --> 00:00:34

So what are some of the most frequently cited series

00:00:34 --> 00:00:38

violations, failure to protect employees from impalement, which

00:00:38 --> 00:00:41

is basically rebar not being kept or covered, as we're going to talk

00:00:41 --> 00:00:46

about it in a minute, failure to establish a limited access zone,

00:00:46 --> 00:00:49

to limit the number of workers in the danger zone where a masonry

00:00:49 --> 00:00:53

wall is under construction. We're going to talk about what say,

00:00:53 --> 00:00:57

limited access zone, failure to brace unsupported section of

00:00:57 --> 00:01:00

masonry wall over eight feet in height. When the wall is still

00:01:00 --> 00:01:04

under construction, it's not strong enough yet. So if it's not

00:01:04 --> 00:01:08

properly supported, it can collapse with strong wind or heavy

00:01:08 --> 00:01:12

equipment passing next to it and so on. Failure to have drawings or

00:01:12 --> 00:01:15

plans at the job site to indicate Jack layout and formwork

00:01:15 --> 00:01:19

placement, especially for certain types of concrete operations that

00:01:19 --> 00:01:23

require a lot of coordination, as regard to see on the next slides.

00:01:26 --> 00:01:30

So the first issue is protection from impalement. Impalement,

00:01:30 --> 00:01:35

basically is when something sharp can penetrate the body of a

00:01:35 --> 00:01:39

worker. So what are some effective control measures that can be used

00:01:39 --> 00:01:43

to guard your bar so employees cannot fall into or onto the rebar

00:01:43 --> 00:01:47

and becoming built. We can either prevent the employees from working

00:01:47 --> 00:01:51

in an area where there's they may fall into or onto unprotected

00:01:51 --> 00:01:55

rebar. In some cases, that's not the easiest solution, so we have

00:01:55 --> 00:01:59

to look for other solutions as well. So if this is not possible,

00:01:59 --> 00:02:03

use guard rails or other fall protection measures, as outlined,

00:02:03 --> 00:02:05

as we're going to discuss later in subpart M that deals with fall

00:02:05 --> 00:02:06

protection.

00:02:07 --> 00:02:13

And third, with that second option available, we're going to rebar.

00:02:13 --> 00:02:17

The rebar is going to be capped with special protective rebar

00:02:17 --> 00:02:21

covers, as you can see in the picture, to keep employees from

00:02:21 --> 00:02:27

being impaled. We do not use plastic or paper cups or tape as

00:02:27 --> 00:02:30

rebar cover, as a rebar cover, because they do not protect

00:02:30 --> 00:02:33

workers from impalement. So it has to be sturdy enough, according to

00:02:33 --> 00:02:37

specifications, to prevent even if someone falls on top of it, it

00:02:37 --> 00:02:42

would not be broken or torn and allow for impalement as well. The

00:02:42 --> 00:02:46

rebar also can be banned, but only when an engineer has approved this

00:02:46 --> 00:02:49

practice, or the rebar can be covered with lumber. So if you

00:02:49 --> 00:02:53

have multiple bars next to each other, you can extend a two by

00:02:53 --> 00:02:57

four board, for example, on top of them, and that would prevent the

00:02:57 --> 00:02:58

hazard of impalement

00:03:00 --> 00:03:04

here, as we can see, the mushroom cap, which is the one that shows

00:03:04 --> 00:03:08

here in this picture, this is not allowed because it's ineffective.

00:03:09 --> 00:03:10

The square cap with reinforced

00:03:11 --> 00:03:16

base here at the top is the one that's accepted, and that's the

00:03:16 --> 00:03:19

one that's affected. So here on the next picture, we see examples

00:03:19 --> 00:03:24

of that. So here, for example, we can see that the rebar here is

00:03:24 --> 00:03:29

capped with concrete, small concrete blocks. Here you can have

00:03:29 --> 00:03:34

also a two by four. Here we have these mushroom caps in some cases,

00:03:34 --> 00:03:38

again, as we mentioned, unless they are reinforced, they're not

00:03:38 --> 00:03:41

going to be allowed. Here we have a clear violation, because you

00:03:41 --> 00:03:44

have an opening and it's not showing whether they're kept or

00:03:44 --> 00:03:47

not. So I guess they're not kept. That's an impairment hazard. So

00:03:47 --> 00:03:49

this is a violation.

00:03:50 --> 00:03:55

Here we have the rebar has been bent again, following instructions

00:03:55 --> 00:04:00

from the structural engineer, and here we have either caps or the

00:04:00 --> 00:04:04

two by four covering the rebar. So both of these are acceptable

00:04:04 --> 00:04:04

options.

00:04:08 --> 00:04:10

Another hazard that comes with construction

00:04:11 --> 00:04:14

of concrete work is when we have

00:04:15 --> 00:04:19

post tensioning work for prestressed concrete, basically

00:04:19 --> 00:04:22

for the pre stressed concrete, you induce stresses in the concrete

00:04:22 --> 00:04:26

tendons, which are the rebar. But concrete tendons tend to have

00:04:26 --> 00:04:30

stress into them. So when you load the concrete element, it

00:04:30 --> 00:04:35

counterbalances these stresses, yielding a smaller size and

00:04:35 --> 00:04:39

lighter in weight concrete element. So for post tensioning

00:04:39 --> 00:04:42

work, the following precautions have to be followed. Access shall

00:04:42 --> 00:04:46

be limited behind the jack to those performing the work. The

00:04:46 --> 00:04:50

jack is going to be used to tension these tendons, signs and

00:04:50 --> 00:04:53

barricades are required to limit access as well, so that people who

00:04:53 --> 00:04:57

are not who should not be working in this area are not going to be

00:04:57 --> 00:04:59

performing any work. So on this.

00:05:00 --> 00:05:04

Light on the picture here we can see that these are the tendons.

00:05:04 --> 00:05:09

And here they are capped, and here's the jack tensioning these

00:05:10 --> 00:05:12

tensioning these tendons.

00:05:13 --> 00:05:17

So again, we're going to try to limit access within this area to

00:05:17 --> 00:05:19

only people who have to be there. You

00:05:23 --> 00:05:25

a third hazard this area, when it comes to concrete, is concrete

00:05:25 --> 00:05:29

placing. We have multiple ways of concrete placing, whether it's

00:05:29 --> 00:05:31

through a pump, whether it's through buggies, whether it's

00:05:31 --> 00:05:35

through a tower crane and buckets. So here we're going to talk about

00:05:35 --> 00:05:38

tower cranes and buckets. Employees are not allowed to work

00:05:38 --> 00:05:41

under concrete buckets being lowered or elevated into position,

00:05:42 --> 00:05:45

because just in case something goes wrong with the bucket itself

00:05:45 --> 00:05:48

and it opens concrete. Dropping from that bucket can kill someone,

00:05:48 --> 00:05:51

if someone's standing underneath it, and as much as practical,

00:05:51 --> 00:05:54

bucket should be routed to minimize the number of employees

00:05:54 --> 00:05:58

exposed to overhead buckets. So in the design of the operation

00:05:58 --> 00:06:01

itself, we're going to take that into consideration with the motion

00:06:02 --> 00:06:05

of the tower crane and of the buckets. Here on this picture, it

00:06:05 --> 00:06:09

shows multiple people standing next to a concrete bucket. No one

00:06:09 --> 00:06:12

standing underneath it. They opened the chute for that bucket,

00:06:12 --> 00:06:16

and we can see concrete flowing out of the bucket to the place

00:06:16 --> 00:06:18

where it's where it's supposed to be,

00:06:21 --> 00:06:25

another area of hazard also is with concrete mixers with capacity

00:06:25 --> 00:06:29

greater than one cubic yard, they must have a mechanical device to

00:06:29 --> 00:06:33

clear the skip of materials, so that no one would be tempted to go

00:06:33 --> 00:06:38

inside and try to clean that skip. Guard rates should be used on each

00:06:38 --> 00:06:41

should be on each side of the skip again, preventing anyone from

00:06:41 --> 00:06:46

falling in compressed air hoses on concrete pumping systems must have

00:06:46 --> 00:06:50

failed safe connectors, because, again, compressed air at a very

00:06:50 --> 00:06:56

strong force can can cause injuries. Masonry saws must have

00:06:56 --> 00:06:59

semicircular guard enclosure. If you remember, when we talked about

00:06:59 --> 00:07:04

theories of accident causation, we mentioned that improper use of

00:07:04 --> 00:07:06

equipment, this is one of the common ones. People sometimes

00:07:07 --> 00:07:11

remove the guard, thinking that's got to expedite the operation, but

00:07:11 --> 00:07:15

that, again, that's a violation by itself. Do not remove that guard

00:07:15 --> 00:07:19

because it has a protective role and function.

00:07:22 --> 00:07:27

So here we have the guard rails so that no one can fall, and here we

00:07:27 --> 00:07:30

have the guard enclosure around that saw

00:07:33 --> 00:07:37

concrete buggies again, if you are, if someone's pushing that

00:07:37 --> 00:07:41

buggy and they trip, they may be impaled by the impact with the

00:07:41 --> 00:07:46

handles of the buggy. So concrete buggy handles cannot extend past

00:07:46 --> 00:07:49

wheels on either side, to prevent that impalement and prevent anyone

00:07:49 --> 00:07:52

working around again by being affected by it.

00:07:55 --> 00:07:58

Concrete pump poses must have connectors to prevent separation

00:07:58 --> 00:08:02

under load, because again, you may risk having the concrete fall

00:08:02 --> 00:08:06

under pressure from that hose and concrete buckets with hydraulic

00:08:06 --> 00:08:09

release must have a device to prevent accidental dumping, and

00:08:09 --> 00:08:13

that's why, basically, we do not allow people to stand underneath a

00:08:14 --> 00:08:16

concrete bucket while it's being lifted or lowered.

00:08:20 --> 00:08:24

Power concrete trowels must have dead man switch. So basically, as

00:08:24 --> 00:08:28

long as they are held by the laborer, by the employee who is

00:08:28 --> 00:08:32

pushing it, they are in operation. As soon as they release their

00:08:32 --> 00:08:32

handle from

00:08:33 --> 00:08:37

from that switch, it stops automatically. So if someone trips

00:08:37 --> 00:08:42

again, the blades of that concrete travel would not cause any

00:08:42 --> 00:08:43

injuries.

00:08:47 --> 00:08:53

Here, what we have is a bull float which has a long handle. Now, the

00:08:53 --> 00:08:56

problem here is that we're working close to power lines and power

00:08:56 --> 00:09:01

equipment which can cause a hazard of electrocution. So the wood

00:09:01 --> 00:09:05

floor handles must be non conductive if electrical contact

00:09:05 --> 00:09:08

is possible. So it can be of a non conductive material, whether wood

00:09:08 --> 00:09:10

or fiberglass or something like that.

00:09:14 --> 00:09:18

Okay, so this is basically talking, in brief, about some of

00:09:18 --> 00:09:21

the hazards that can come with concrete operations. What about

00:09:21 --> 00:09:25

some hazards that can come? Can come with Mason reconstruction

00:09:25 --> 00:09:29

operations as well. So here we're going to talk about the major one,

00:09:29 --> 00:09:33

which is wall collapses, especially when the wall is still

00:09:33 --> 00:09:36

under construction. As we mentioned, the cut, the mortar has

00:09:36 --> 00:09:40

not set yet, so the wall has not gained its permanent strength yet.

00:09:41 --> 00:09:46

Therefore it needs to be supported or protected from collapse. What

00:09:46 --> 00:09:48

are some of the effective control measures that can be used to

00:09:48 --> 00:09:52

eliminate the hazard of being in danger in the danger zone, to

00:09:52 --> 00:09:56

protect employees from being struck by flying brick or block in

00:09:56 --> 00:09:59

the event of a wall collapse, so until the wall.

00:10:00 --> 00:10:01

Has gained sufficient strength

00:10:02 --> 00:10:06

that overturning is no longer a hazard. Overturning again, which

00:10:06 --> 00:10:09

is sort of a collapse due to strong wind or

00:10:10 --> 00:10:13

vibration around it, keep employees out of the area where

00:10:13 --> 00:10:17

the wall is being constructed unless they are actually engaged

00:10:17 --> 00:10:20

in constructing the wall. Of course, if they are engaged in

00:10:20 --> 00:10:22

constructing the wall, they have to be in close proximity to it.

00:10:23 --> 00:10:28

But if once the wall is complete, until it gains its strength, then

00:10:28 --> 00:10:31

no one should be close to it, working close to it, the most

00:10:31 --> 00:10:35

effective control measure is to follow the standard by marking off

00:10:35 --> 00:10:39

an area with tape, rope or chain or any other material that will

00:10:39 --> 00:10:43

indicate to employees that they are not to enter that zone or area

00:10:43 --> 00:10:47

that has been marked. This is what we call limited access zone. In

00:10:47 --> 00:10:51

this case, only the Masons who are working on constructing that wall

00:10:51 --> 00:10:54

are going to be allowed in this area. Out of that marked area,

00:10:55 --> 00:10:59

people can work, but inside it only the masonry crew that's

00:10:59 --> 00:11:03

working on constructing this wall, the zone should be equal to the

00:11:03 --> 00:11:06

length of the wall under construction and extend out a

00:11:06 --> 00:11:09

distance equal to the height of the wall to be constructed, plus

00:11:09 --> 00:11:13

four feet, because again, if it collapses, debris is going to fly

00:11:13 --> 00:11:17

everywhere. So you're adding four feet of buffer zone beyond the

00:11:17 --> 00:11:21

height of the wall. So if the wall, for example, is eight feet,

00:11:21 --> 00:11:25

then that horizontal extent is going to be 12 feet. If the wall

00:11:25 --> 00:11:29

to be constructed is 10 feet high and 30 feet long, the zone is

00:11:29 --> 00:11:31

going to be 14 feet

00:11:32 --> 00:11:35

by 30 feet, which is the length of the wall.

00:11:39 --> 00:11:43

If a wall is over eight feet in height. What are some of the ways

00:11:43 --> 00:11:46

to brace a wall over eight feet to provide protection against the

00:11:46 --> 00:11:50

hazard of collapse, the project engineer or competent person

00:11:50 --> 00:11:53

should determine how best to brace the wall. According to the

00:11:53 --> 00:11:57

magazine of masonry construction, a typical masonry wall brace

00:11:57 --> 00:12:02

includes a vertical member, an inclined strut, stakes, and, if

00:12:02 --> 00:12:05

necessary, a strut brace. We're going to see a picture that

00:12:05 --> 00:12:10

illustrates this concept. What kind of material is going to be

00:12:10 --> 00:12:14

used for the support, scaffold planks, two by 10s are typically

00:12:14 --> 00:12:18

used as the vertical member and the inclined strut, and two by

00:12:18 --> 00:12:24

fours for stakes and strut braces, two by fours and two by sixes are

00:12:24 --> 00:12:28

considered by most expert to be inadequate for vertical member or

00:12:28 --> 00:12:33

inclined struts. That's why we're using the scaffold planks. All

00:12:33 --> 00:12:36

lumber must be in serviceable conditions. So it must be in good

00:12:36 --> 00:12:41

condition, not rotting or not suffering from any damage. The

00:12:41 --> 00:12:46

American National Standards Institute, which is called NC, has

00:12:46 --> 00:12:49

a standard for concrete and masonry work, which is NCA one,

00:12:49 --> 00:12:50

10.9 1983

00:12:52 --> 00:12:55

recommends that the support for bracing, the support or brazing,

00:12:55 --> 00:12:59

shall be designed by or under the supervision of a qualified person

00:13:00 --> 00:13:04

to withstand a minimum of 15 pounds per square foot. Remember

00:13:04 --> 00:13:08

that number, 15 pounds per square foot. Local environmental

00:13:08 --> 00:13:12

conditions such as strong wind, for example, need to be considered

00:13:12 --> 00:13:16

in determining the bracing design. Braces or shores should be secured

00:13:16 --> 00:13:20

in position to prevent them from moving, thus losing this their

00:13:20 --> 00:13:21

effectiveness,

00:13:25 --> 00:13:29

if you're going to be placing concrete inside that wall, in this

00:13:29 --> 00:13:33

case, tremies, which is the hose that's going to be used to convey

00:13:33 --> 00:13:36

that concrete must be secured with wire rope or equivalent, to

00:13:36 --> 00:13:40

prevent them from moving. And again, concrete might start

00:13:40 --> 00:13:44

spreading around, Lockout and tag out is required for work on

00:13:44 --> 00:13:47

equipment used for concrete and masonry. If they are defective,

00:13:48 --> 00:13:50

they need to be locked out or tagged out, so no one would use

00:13:50 --> 00:13:54

them until they are being properly maintained or repaired.

00:13:56 --> 00:13:58

So here we have the picture of a tremie

00:13:59 --> 00:14:02

that's being used to convey the concrete. In this case, we are

00:14:02 --> 00:14:06

using a conveyor belt to drive the concrete to the place and then it

00:14:06 --> 00:14:12

falls through the tremie to try to minimize the scattering and

00:14:12 --> 00:14:13

sputtering of concrete all around

00:14:17 --> 00:14:21

forecast in place, concrete, which is also called Concrete test in

00:14:21 --> 00:14:26

situ. Formwork must be designed, fabricated, erected, supported,

00:14:26 --> 00:14:30

braced and maintained, so that it will be capable of supporting

00:14:30 --> 00:14:34

without failure all vertical and lateral loads. That's why, for

00:14:34 --> 00:14:39

example, we have a code for not removing the formwork until a

00:14:39 --> 00:14:42

certain number of days have passed after placing the concrete is

00:14:42 --> 00:14:45

determined by the quality of the concrete, by the weather, by the

00:14:45 --> 00:14:49

span, by the design and so on. Several factors involved in the

00:14:49 --> 00:14:54

duration before we can remove the formwork drawings or plans and any

00:14:54 --> 00:14:57

revisions for Jack layout formwork, etc, must be available

00:14:57 --> 00:14:59

at the job site, especially if we have.

00:15:00 --> 00:15:03

Certain types of concrete being placed, like slip form, for

00:15:03 --> 00:15:08

example, or lift slab. We're going to talk about that in a moment.

00:15:09 --> 00:15:12

We must also include four more scaffolding and any shoring

00:15:12 --> 00:15:16

equipment in these drawings, so they have to show the spacing, for

00:15:16 --> 00:15:19

example, between the different elements of the scaffold and the

00:15:19 --> 00:15:20

props and so on. To

00:15:23 --> 00:15:27

give you an example of how hazardous this operation can be,

00:15:27 --> 00:15:32

there's a very famous sad accident in Willow island in West Virginia

00:15:32 --> 00:15:33

on april 1978

00:15:34 --> 00:15:38

51 workers were killed in the collapse of scaffolding used to

00:15:38 --> 00:15:42

pour concrete for a cooling tower under construction, 45 workers

00:15:42 --> 00:15:47

fell more than 150 feet, and six were crushed to death on the

00:15:47 --> 00:15:51

ground. So basically we're talking about the scaffolding itself

00:15:51 --> 00:15:53

collapsed. There was the weight of the concrete, there was the weight

00:15:53 --> 00:15:56

of the people on top of it, the weight of rebar. It could not

00:15:56 --> 00:16:01

support all of that weight. So there's the static weight of the

00:16:01 --> 00:16:05

formwork and the rebar, and the dynamic load by the people walking

00:16:05 --> 00:16:09

on top of it, and the dynamic load of the concrete being placed, all

00:16:09 --> 00:16:12

of that resulted in the collapse of the formwork. And as you can

00:16:12 --> 00:16:16

see, a very large number of people lost their lives.

00:16:19 --> 00:16:23

Here. We can see, for example, an example of shoring. Shoring is to

00:16:23 --> 00:16:27

be inspected prior to erection, before and after and during

00:16:27 --> 00:16:30

concrete placement, to make sure that it's still in a good

00:16:30 --> 00:16:34

condition supporting the load of the concrete placed on top of it.

00:16:36 --> 00:16:41

Reshoring also needs to be inspected. So after you remove the

00:16:41 --> 00:16:44

formwork, the bulk of the formwork, and you keep a few

00:16:44 --> 00:16:48

props, these have to be inspected on a regular basis to make sure

00:16:48 --> 00:16:49

that they're doing their job.

00:16:56 --> 00:17:00

These are the concrete. That's a picture of samples of concrete

00:17:00 --> 00:17:03

taking into cylinders. That's going to be tested on a regular

00:17:03 --> 00:17:06

basis, as you remember from your materials class, is going to be

00:17:06 --> 00:17:09

tested after seven days, and it's going to be tested again after 28

00:17:10 --> 00:17:13

days to determine whether this concrete complies with the

00:17:13 --> 00:17:19

expected compressive strength or not. So that's why a random sample

00:17:19 --> 00:17:23

is going to be taken every certain number of cubic yards of concrete

00:17:23 --> 00:17:26

to be placed, we're going to take a sample, and they're going to be

00:17:26 --> 00:17:30

kept in good conditions, according to the standards, until they are

00:17:30 --> 00:17:34

tested again, whether after seven days or after 28 days,

00:17:38 --> 00:17:43

when you are placing concrete on site. Damage shoring is not to be

00:17:43 --> 00:17:46

used because, again, it loses its efficiency and effectiveness, and

00:17:46 --> 00:17:49

therefore it should not be used. Shoring that's found to be damaged

00:17:49 --> 00:17:53

must be immediately reinforced. The sills for shoring must be

00:17:53 --> 00:17:57

sound rigid and capable to carry the maximum intended load. The

00:17:57 --> 00:18:00

sills are going to be used to distribute the load. Instead of

00:18:00 --> 00:18:04

being a point load is going to be a larger area. Load just same idea

00:18:04 --> 00:18:07

of a footing underneath a column. For example,

00:18:10 --> 00:18:13

all base plates, Shore heads, extension devices and adjustment

00:18:13 --> 00:18:17

screws must be in firm contact with the foundation and the form

00:18:17 --> 00:18:21

and secured when necessary to make sure that they do not move from

00:18:21 --> 00:18:24

place under the pressure of the concrete on top of them.

00:18:27 --> 00:18:30

In case you have eccentric loading, which means it's not

00:18:30 --> 00:18:34

axial loading on top of the prop on top of the shore head.

00:18:35 --> 00:18:39

Eccentric loads on shore heads are not allowed unless designed for

00:18:39 --> 00:18:42

this, because this creates, in addition of the load itself, it

00:18:42 --> 00:18:48

creates a moment which may overturn that shore head. It means

00:18:48 --> 00:18:52

loads not centered on the head. Lateral loads can cause failures

00:18:52 --> 00:18:56

because of that, unless the shoring is properly designed to

00:18:56 --> 00:18:57

take these lateral loads.

00:18:59 --> 00:19:02

So for example, here on this slide, we can see that we have

00:19:02 --> 00:19:07

some lateral loads from this this cantilever. So that's why we have

00:19:07 --> 00:19:12

this diagonal or these slanted shoring as additional support for

00:19:12 --> 00:19:13

the formwork,

00:19:19 --> 00:19:22

also with casting case concrete whenever single posture post

00:19:22 --> 00:19:27

shores are tiered, which means, if you have, for example, the the

00:19:27 --> 00:19:31

floor height is 12 feet, and you have only eight foot long shores,

00:19:31 --> 00:19:33

and they're going to be tiered. Which are which means are going to

00:19:33 --> 00:19:35

be spliced.

00:19:36 --> 00:19:40

Additional requirements to be followed are that the short must

00:19:40 --> 00:19:44

be designed and inspected by a qualified person, vertically

00:19:44 --> 00:19:48

aligned, properly aligned, spliced to prevent misalignment, and

00:19:48 --> 00:19:54

braced in two directions at splice levels and in each tier. So all of

00:19:54 --> 00:19:57

these are precautions so that they do not collapse or deform a.

00:25:00 --> 00:25:03

An injury from particles from concrete while pulling or placing

00:25:03 --> 00:25:08

it. Washing facilities and I wash solution should be provided.

00:25:09 --> 00:25:12

Again, this is not mandatory, but definitely this is good practice.

00:25:12 --> 00:25:15

And as we mentioned before, you care about your employees. You

00:25:15 --> 00:25:18

want them to be safe, so we're going to follow that best

00:25:18 --> 00:25:23

practice. Let's pause here, and then we're going to resume this

00:25:23 --> 00:25:26

presentation in another video file. You.

Share Page