Ihab Saad – ADM solved example

Ihab Saad
AI: Summary ©
The speaker discusses how to solve a problem with ADM by organizing activities in a network, starting with the B and C activities and connecting the nodes. They explain how to adjust properties of certain lines and calculate dates. The speaker emphasizes the importance of finishing certain activities for optimal results and explains the use of certain nodes for critical activities.
AI: Transcript ©
00:00:02 --> 00:00:06

I Hello again. Today we're going to start trying to solve the

00:00:06 --> 00:00:10

problem with ADM to see how can we draw the network, and how can we

00:00:10 --> 00:00:15

perform the calculations of error Diagramming Method. What we have

00:00:15 --> 00:00:18

here in front of us is a table showing different activities in

00:00:18 --> 00:00:23

the form of ij, together with the IPAS and the durations for each

00:00:23 --> 00:00:27

activities, for each one of the activities. So what we're going to

00:00:27 --> 00:00:30

do is, first, we're going to try to draw this network. Here we have

00:00:30 --> 00:00:34

an Excel file. We're going to try to draw the the network in Excel.

00:00:34 --> 00:00:37

And that's basically a very simple task. What we're going to do is

00:00:37 --> 00:00:39

we're going to go to insert

00:00:42 --> 00:00:46

and shapes. We're going to select a an oval, which we're going to

00:00:46 --> 00:00:48

make, like a circle here,

00:00:51 --> 00:00:58

and then what we're going to do, basically, is just copy and paste

00:00:58 --> 00:01:00

this circle several times,

00:01:04 --> 00:01:07

and now we're going to start dragging these circles one by one

00:01:07 --> 00:01:12

and drawing the network. So we start with activity AB, of course,

00:01:12 --> 00:01:16

as we notice here, we have ab, ac and ad. All of these three

00:01:16 --> 00:01:19

activities have no immediate predecessors. So

00:01:23 --> 00:01:25

we notice that these three activities have no immediate

00:01:25 --> 00:01:29

predecessors, which means that they start the network. So we're

00:01:29 --> 00:01:33

going to start with node A, and then draw activity ab, ac and ad.

00:01:33 --> 00:01:38

So we're going to drag one of these circles here, and that's

00:01:38 --> 00:01:43

going to be the node A. You can type a inside like that,

00:01:44 --> 00:01:48

and then we're gonna add drag another node here,

00:01:49 --> 00:01:52

B, another node

00:01:53 --> 00:01:57

C and another node D.

00:02:00 --> 00:02:02

So here we have

00:02:03 --> 00:02:04

B,

00:02:05 --> 00:02:06

C

00:02:07 --> 00:02:08

and D.

00:02:09 --> 00:02:12

What we're going to do next is we're going to connect these with

00:02:12 --> 00:02:16

a line. So we're going to select shapes. We can select an arrow, as

00:02:16 --> 00:02:19

we mentioned before, an arrow or a line doesn't make much difference,

00:02:19 --> 00:02:22

since we know that the flow is going to be from left to right, so

00:02:22 --> 00:02:24

we're going to connect AB,

00:02:26 --> 00:02:27

we're going To connect

00:02:28 --> 00:02:29

AC,

00:02:33 --> 00:02:35

and we're going to connect ad.

00:02:42 --> 00:02:46

So here we're done with the first three activities. Next we're going

00:02:46 --> 00:02:50

to look from B we have activity B, C and B, E, and both of them have

00:02:50 --> 00:02:55

a B as predecessor. So we're gonna drag two nodes here. So

00:03:03 --> 00:03:04

and connect,

00:03:12 --> 00:03:13

and here we have

00:03:15 --> 00:03:16

BC.

00:03:17 --> 00:03:22

Well, actually, BC is already here, so we don't need to drag a

00:03:22 --> 00:03:26

couple of nodes. We can just connect BC like that.

00:03:38 --> 00:03:40

And that's going to be be,

00:03:44 --> 00:03:46

but notice something here,

00:03:48 --> 00:03:50

activity BC has zero duration,

00:03:52 --> 00:03:56

therefore it has to be a dummy activity. So what we're going to

00:03:56 --> 00:03:59

do, we're going to change the properties of this line,

00:04:00 --> 00:04:05

going to format shape by right clicking on the line and changing

00:04:05 --> 00:04:08

it into a dash type, something like that.

00:04:10 --> 00:04:14

And here we have it on the activity between B and C, B and C.

00:04:15 --> 00:04:23

So then we have CF, which follows AC and BC

00:04:24 --> 00:04:28

CF. So let's just drag this node here,

00:04:30 --> 00:04:31

and this is going to be f,

00:04:34 --> 00:04:35

and draw the line CF and

00:04:50 --> 00:04:50

okay,

00:04:51 --> 00:04:58

and then we have CG, also has predecessors of AC and BC, so we

00:04:58 --> 00:04:59

have g is.

00:05:00 --> 00:05:03

Going to be somewhere here. So let's drag another node G,

00:05:10 --> 00:05:11

and the activity

00:05:14 --> 00:05:17

connecting the two nodes. Remember, in ATM, the activity is

00:05:17 --> 00:05:19

represented by the arrow connecting the two nodes,

00:05:21 --> 00:05:26

and then we have also DG, which has as a predecessor, ad. So we're

00:05:26 --> 00:05:27

going to connect DG,

00:05:29 --> 00:05:34

so it's very convenient that we place G at this position. Now you

00:05:34 --> 00:05:37

can you're going to see that we're going to have some different

00:05:37 --> 00:05:41

attempts at arranging these activities in the proper layout to

00:05:41 --> 00:05:44

be legible as much as possible. So far, it's working fine,

00:05:45 --> 00:05:48

alright. So next we have activity EI

00:05:50 --> 00:05:57

and EF, and both of them have, as predecessors, be so EI and EF,

00:05:58 --> 00:06:03

dragging two nodes, actually one node only, because here we have F

00:06:03 --> 00:06:09

already existing. So we're going to connect EI. This is going to be

00:06:09 --> 00:06:10

I

00:06:11 --> 00:06:12

connect Ei,

00:06:17 --> 00:06:19

and also connect EF. We're

00:06:25 --> 00:06:28

both of them have duration. So we only, as you notice from this

00:06:28 --> 00:06:31

table, we only have one dummy activity, which is activity, BC,

00:06:34 --> 00:06:39

all right, so now the next one is going to be G, H, which has as

00:06:39 --> 00:06:44

predecessors, CG and DG. So we're going to have H somewhere here,

00:06:50 --> 00:06:52

and we're going to connect

00:06:53 --> 00:06:54

GH.

00:06:59 --> 00:07:08

Next we have f j, F j, which has as predecessors, E, F and C, F. So

00:07:08 --> 00:07:09

let's put J somewhere here

00:07:15 --> 00:07:16

and connect

00:07:17 --> 00:07:18

F j, so

00:07:24 --> 00:07:28

and then we also have HJ and ij. We already have the node, so all

00:07:28 --> 00:07:30

we have to do is connect i

00:07:40 --> 00:07:40

i,

00:07:45 --> 00:07:47

and here we have our network.

00:07:50 --> 00:07:52

We have all the activities,

00:07:54 --> 00:07:55

i, j

00:07:57 --> 00:08:02

as its predecessor, e, i, that's fine. And HJ has its predecessor,

00:08:02 --> 00:08:06

GH, that's perfectly fine. So we ended up with one extra node. We

00:08:06 --> 00:08:07

can just delete that

00:08:09 --> 00:08:14

very well. The next step is to calculate the dates. As you

00:08:14 --> 00:08:18

remember, we mentioned that we're always going to start with day

00:08:18 --> 00:08:25

zero, so we're going to put zero here, and zero, also here and zero

00:08:25 --> 00:08:27

also here.

00:08:29 --> 00:08:34

Let's just make some adjustments so that it appears in a nicer way.

00:08:36 --> 00:08:38

And here we're going to make it like that.

00:08:40 --> 00:08:43

Actually, you can try to Okay, so far so good.

00:08:46 --> 00:08:51

And then activity AB has a duration of four days, so we're

00:08:51 --> 00:08:53

gonna finish on day four.

00:08:56 --> 00:08:59

So also, let's make it left adjusted.

00:09:00 --> 00:09:03

Activity AC has a duration of nine days,

00:09:04 --> 00:09:06

so it's going to finish on day nine.

00:09:10 --> 00:09:15

Ad has a duration of 16 days, so it's going to finish on day 16. I

00:09:23 --> 00:09:29

now activity, the node B has the date number four, so anything that

00:09:29 --> 00:09:33

starts from B is going to be on four. So we're going to put four

00:09:33 --> 00:09:33

here

00:09:40 --> 00:09:42

and four here as well.

00:09:49 --> 00:09:54

Now activity be has a duration of 13 days, so it's going to end on

00:09:54 --> 00:09:55

day 17. So.

00:10:01 --> 00:10:05

The Activity BC is a dummy activity, so the duration is four,

00:10:05 --> 00:10:07

therefore it's going to end on day four as well.

00:10:10 --> 00:10:10

Centered.

00:10:13 --> 00:10:16

Now at node C, we have two dates coming we have four coming from

00:10:16 --> 00:10:21

BC, and we have nine coming from AC. As you remember from our

00:10:21 --> 00:10:24

lecture, we're going to take the larger number in the forward pass,

00:10:24 --> 00:10:25

so we're going to put here nine

00:10:28 --> 00:10:28

and nine.

00:10:39 --> 00:10:46

Duration of CG is 14 days, so it's going to end on day 23

00:10:52 --> 00:10:58

and duration of CF is seven days, so it's going to end on day 16.

00:11:02 --> 00:11:06

Duration of d G is

00:11:07 --> 00:11:10

eight days. It's going to start on day 16,

00:11:14 --> 00:11:18

and it's going to end on day 24 I

00:11:25 --> 00:11:29

now at node G again, we have two numbers. We have 23 and 24

00:11:29 --> 00:11:31

therefore the number that's going to proceed with us is going to be

00:11:31 --> 00:11:33

the 24 the larger number.

00:11:45 --> 00:11:50

GH has a duration of 12 days, so it's going to end on day 36

00:12:02 --> 00:12:02

and

00:12:04 --> 00:12:07

as you can see, it's very simple calculations. We can just you can

00:12:07 --> 00:12:10

just finish the calculations for this network. Let's just finish

00:12:10 --> 00:12:13

the forward pass, and you can go ahead and do the backward pass

00:12:13 --> 00:12:13

yourself.

00:12:15 --> 00:12:17

So here we're going to start with 17 i

00:12:24 --> 00:12:26

and EI

00:12:27 --> 00:12:30

is 16 days. So it's going to be 33

00:12:35 --> 00:12:37

here. Also we have 17

00:12:41 --> 00:12:45

and EF has a duration of nine days. So it's going to be 26

00:12:49 --> 00:12:52

so at node F, we have 16 and 26 we're going to take the 26

00:12:56 --> 00:13:00

and F, J has a duration of 10 days. So here we're going to have

00:13:00 --> 00:13:01

36

00:13:07 --> 00:13:09

and then I we have here 33

00:13:14 --> 00:13:20

and duration of ij is 13, so it's going to be

00:13:21 --> 00:13:23

46 40 6h.

00:13:31 --> 00:13:33

J is going to start here on 36

00:13:41 --> 00:13:45

and has a duration of 11 days. So it's going to be 47

00:13:48 --> 00:13:53

now we have three numbers going to know, j we have 4636 and 47 the

00:13:53 --> 00:13:58

largest number, of course, is 47 so that's going to be my end of

00:13:58 --> 00:14:03

the project. The project started on day zero and ended on day 47

00:14:04 --> 00:14:07

as you can see, the calculations are not that hard at all. They are

00:14:07 --> 00:14:10

very straightforward and simple. What we're going to do in the

00:14:10 --> 00:14:13

backward pass, actually, is reverse everything that we did in

00:14:13 --> 00:14:17

the forward pass. Let me start the backward pass and leave it for you

00:14:17 --> 00:14:21

to finish. So let's start with the first set of activities. Here,

00:14:21 --> 00:14:26

we're going to start with 47 as the late start, which is going to

00:14:26 --> 00:14:31

be underneath the arrow 47 and let's change the color of these to

00:14:31 --> 00:14:33

be red, for example,

00:14:35 --> 00:14:40

just to distinguish the forward from the backward passes. So 47

00:14:40 --> 00:14:43

the duration of HJ was

00:14:50 --> 00:14:52

11 days. So it's going to be 36

00:14:53 --> 00:14:55

now we're subtracting. Remember, I.

00:15:00 --> 00:15:05

Now you notice here that HJ has 4747 3636 so obviously this is

00:15:05 --> 00:15:09

going to be a critical activity. Right now, if you follow that,

00:15:09 --> 00:15:12

you're going to find that the critical path is going to be

00:15:12 --> 00:15:14

basically that bottom path,

00:15:15 --> 00:15:19

because this is going to be the longest path, leading with giving

00:15:19 --> 00:15:24

us the longest dates, the latest dates. So it's going to be a, d,

00:15:24 --> 00:15:29

g, h j, that's going to be our critical path at the end. How did

00:15:29 --> 00:15:32

I know that? Because it has to be a continuous path. And since it

00:15:32 --> 00:15:38

passes through h j, then it has to be that one. Why didn't we say a C

00:15:38 --> 00:15:44

and C G? Because again, the number coming to G from D, which is 24 is

00:15:44 --> 00:15:47

larger than the number coming from C, which is 23 therefore the

00:15:47 --> 00:15:51

critical activity is going to be DG. But let's go ahead and do a

00:15:51 --> 00:15:54

couple more activities with the dates. So here we're going to

00:15:54 --> 00:15:56

start with 47 as well, and

00:15:59 --> 00:16:00

let's put

00:16:01 --> 00:16:02

it here,

00:16:03 --> 00:16:07

red 47 minus 10, that's going to be 37

00:16:15 --> 00:16:20

now notice this activity has how many days of total float 47 minus

00:16:20 --> 00:16:26

36 or 37 minus 26 which is 11 days of total float going to activity,

00:16:27 --> 00:16:28

i j, it's going to be again 47

00:16:33 --> 00:16:34

minus.

00:16:35 --> 00:16:37

This is i j

00:16:39 --> 00:16:42

minus 13, so it's going to be 34

00:16:54 --> 00:16:57

and you can just keep doing the backward pass. This one is going

00:16:57 --> 00:17:01

to have only one day of total float. What we can also do at the

00:17:01 --> 00:17:05

end, we can just change the color of the nodes that are going to be

00:17:05 --> 00:17:06

critical.

00:17:08 --> 00:17:11

So we're going to make it something like this,

00:17:14 --> 00:17:19

just to show them in a different color, so that they have a special

00:17:19 --> 00:17:21

status as critical activities.

00:17:23 --> 00:17:27

And we can also change the color of these lines. We're going to

00:17:27 --> 00:17:29

select this group of lines, 1234,

00:17:31 --> 00:17:36

activities, and right click Format objects. Change the color line

00:17:36 --> 00:17:40

color. Let's make it red as critical

00:17:42 --> 00:17:47

and here's our critical path. That was really simple, wasn't it? So

00:17:47 --> 00:17:52

what you have to do is finish that as a as a practice, try to finish

00:17:52 --> 00:17:58

this network and see if you're going to get the same numbers for

00:17:58 --> 00:18:03

activities, GH, Bg and A, D, which should be critical, and then

00:18:03 --> 00:18:09

calculate the total float for the other activities. That's basically

00:18:09 --> 00:18:10

our exercise for today. So.

Share Page