Ihab Saad – ADM solved example

Ihab Saad
Share Page

AI: Summary ©

The speaker discusses how to solve a problem with ADM by organizing activities in a network, starting with the B and C activities and connecting the nodes. They explain how to adjust properties of certain lines and calculate dates. The speaker emphasizes the importance of finishing certain activities for optimal results and explains the use of certain nodes for critical activities.

AI: Summary ©

00:00:02 --> 00:00:06
			I Hello again. Today we're going
to start trying to solve the
		
00:00:06 --> 00:00:10
			problem with ADM to see how can we
draw the network, and how can we
		
00:00:10 --> 00:00:15
			perform the calculations of error
Diagramming Method. What we have
		
00:00:15 --> 00:00:18
			here in front of us is a table
showing different activities in
		
00:00:18 --> 00:00:23
			the form of ij, together with the
IPAS and the durations for each
		
00:00:23 --> 00:00:27
			activities, for each one of the
activities. So what we're going to
		
00:00:27 --> 00:00:30
			do is, first, we're going to try
to draw this network. Here we have
		
00:00:30 --> 00:00:34
			an Excel file. We're going to try
to draw the the network in Excel.
		
00:00:34 --> 00:00:37
			And that's basically a very simple
task. What we're going to do is
		
00:00:37 --> 00:00:39
			we're going to go to insert
		
00:00:42 --> 00:00:46
			and shapes. We're going to select
a an oval, which we're going to
		
00:00:46 --> 00:00:48
			make, like a circle here,
		
00:00:51 --> 00:00:58
			and then what we're going to do,
basically, is just copy and paste
		
00:00:58 --> 00:01:00
			this circle several times,
		
00:01:04 --> 00:01:07
			and now we're going to start
dragging these circles one by one
		
00:01:07 --> 00:01:12
			and drawing the network. So we
start with activity AB, of course,
		
00:01:12 --> 00:01:16
			as we notice here, we have ab, ac
and ad. All of these three
		
00:01:16 --> 00:01:19
			activities have no immediate
predecessors. So
		
00:01:23 --> 00:01:25
			we notice that these three
activities have no immediate
		
00:01:25 --> 00:01:29
			predecessors, which means that
they start the network. So we're
		
00:01:29 --> 00:01:33
			going to start with node A, and
then draw activity ab, ac and ad.
		
00:01:33 --> 00:01:38
			So we're going to drag one of
these circles here, and that's
		
00:01:38 --> 00:01:43
			going to be the node A. You can
type a inside like that,
		
00:01:44 --> 00:01:48
			and then we're gonna add drag
another node here,
		
00:01:49 --> 00:01:52
			B, another node
		
00:01:53 --> 00:01:57
			C and another node D.
		
00:02:00 --> 00:02:02
			So here we have
		
00:02:03 --> 00:02:04
			B,
		
00:02:05 --> 00:02:06
			C
		
00:02:07 --> 00:02:08
			and D.
		
00:02:09 --> 00:02:12
			What we're going to do next is
we're going to connect these with
		
00:02:12 --> 00:02:16
			a line. So we're going to select
shapes. We can select an arrow, as
		
00:02:16 --> 00:02:19
			we mentioned before, an arrow or a
line doesn't make much difference,
		
00:02:19 --> 00:02:22
			since we know that the flow is
going to be from left to right, so
		
00:02:22 --> 00:02:24
			we're going to connect AB,
		
00:02:26 --> 00:02:27
			we're going To connect
		
00:02:28 --> 00:02:29
			AC,
		
00:02:33 --> 00:02:35
			and we're going to connect ad.
		
00:02:42 --> 00:02:46
			So here we're done with the first
three activities. Next we're going
		
00:02:46 --> 00:02:50
			to look from B we have activity B,
C and B, E, and both of them have
		
00:02:50 --> 00:02:55
			a B as predecessor. So we're gonna
drag two nodes here. So
		
00:03:03 --> 00:03:04
			and connect,
		
00:03:12 --> 00:03:13
			and here we have
		
00:03:15 --> 00:03:16
			BC.
		
00:03:17 --> 00:03:22
			Well, actually, BC is already
here, so we don't need to drag a
		
00:03:22 --> 00:03:26
			couple of nodes. We can just
connect BC like that.
		
00:03:38 --> 00:03:40
			And that's going to be be,
		
00:03:44 --> 00:03:46
			but notice something here,
		
00:03:48 --> 00:03:50
			activity BC has zero duration,
		
00:03:52 --> 00:03:56
			therefore it has to be a dummy
activity. So what we're going to
		
00:03:56 --> 00:03:59
			do, we're going to change the
properties of this line,
		
00:04:00 --> 00:04:05
			going to format shape by right
clicking on the line and changing
		
00:04:05 --> 00:04:08
			it into a dash type, something
like that.
		
00:04:10 --> 00:04:14
			And here we have it on the
activity between B and C, B and C.
		
00:04:15 --> 00:04:23
			So then we have CF, which follows
AC and BC
		
00:04:24 --> 00:04:28
			CF. So let's just drag this node
here,
		
00:04:30 --> 00:04:31
			and this is going to be f,
		
00:04:34 --> 00:04:35
			and draw the line CF and
		
00:04:50 --> 00:04:50
			okay,
		
00:04:51 --> 00:04:58
			and then we have CG, also has
predecessors of AC and BC, so we
		
00:04:58 --> 00:04:59
			have g is.
		
00:05:00 --> 00:05:03
			Going to be somewhere here. So
let's drag another node G,
		
00:05:10 --> 00:05:11
			and the activity
		
00:05:14 --> 00:05:17
			connecting the two nodes.
Remember, in ATM, the activity is
		
00:05:17 --> 00:05:19
			represented by the arrow
connecting the two nodes,
		
00:05:21 --> 00:05:26
			and then we have also DG, which
has as a predecessor, ad. So we're
		
00:05:26 --> 00:05:27
			going to connect DG,
		
00:05:29 --> 00:05:34
			so it's very convenient that we
place G at this position. Now you
		
00:05:34 --> 00:05:37
			can you're going to see that we're
going to have some different
		
00:05:37 --> 00:05:41
			attempts at arranging these
activities in the proper layout to
		
00:05:41 --> 00:05:44
			be legible as much as possible. So
far, it's working fine,
		
00:05:45 --> 00:05:48
			alright. So next we have activity
EI
		
00:05:50 --> 00:05:57
			and EF, and both of them have, as
predecessors, be so EI and EF,
		
00:05:58 --> 00:06:03
			dragging two nodes, actually one
node only, because here we have F
		
00:06:03 --> 00:06:09
			already existing. So we're going
to connect EI. This is going to be
		
00:06:09 --> 00:06:10
			I
		
00:06:11 --> 00:06:12
			connect Ei,
		
00:06:17 --> 00:06:19
			and also connect EF. We're
		
00:06:25 --> 00:06:28
			both of them have duration. So we
only, as you notice from this
		
00:06:28 --> 00:06:31
			table, we only have one dummy
activity, which is activity, BC,
		
00:06:34 --> 00:06:39
			all right, so now the next one is
going to be G, H, which has as
		
00:06:39 --> 00:06:44
			predecessors, CG and DG. So we're
going to have H somewhere here,
		
00:06:50 --> 00:06:52
			and we're going to connect
		
00:06:53 --> 00:06:54
			GH.
		
00:06:59 --> 00:07:08
			Next we have f j, F j, which has
as predecessors, E, F and C, F. So
		
00:07:08 --> 00:07:09
			let's put J somewhere here
		
00:07:15 --> 00:07:16
			and connect
		
00:07:17 --> 00:07:18
			F j, so
		
00:07:24 --> 00:07:28
			and then we also have HJ and ij.
We already have the node, so all
		
00:07:28 --> 00:07:30
			we have to do is connect i
		
00:07:40 --> 00:07:40
			i,
		
00:07:45 --> 00:07:47
			and here we have our network.
		
00:07:50 --> 00:07:52
			We have all the activities,
		
00:07:54 --> 00:07:55
			i, j
		
00:07:57 --> 00:08:02
			as its predecessor, e, i, that's
fine. And HJ has its predecessor,
		
00:08:02 --> 00:08:06
			GH, that's perfectly fine. So we
ended up with one extra node. We
		
00:08:06 --> 00:08:07
			can just delete that
		
00:08:09 --> 00:08:14
			very well. The next step is to
calculate the dates. As you
		
00:08:14 --> 00:08:18
			remember, we mentioned that we're
always going to start with day
		
00:08:18 --> 00:08:25
			zero, so we're going to put zero
here, and zero, also here and zero
		
00:08:25 --> 00:08:27
			also here.
		
00:08:29 --> 00:08:34
			Let's just make some adjustments
so that it appears in a nicer way.
		
00:08:36 --> 00:08:38
			And here we're going to make it
like that.
		
00:08:40 --> 00:08:43
			Actually, you can try to Okay, so
far so good.
		
00:08:46 --> 00:08:51
			And then activity AB has a
duration of four days, so we're
		
00:08:51 --> 00:08:53
			gonna finish on day four.
		
00:08:56 --> 00:08:59
			So also, let's make it left
adjusted.
		
00:09:00 --> 00:09:03
			Activity AC has a duration of nine
days,
		
00:09:04 --> 00:09:06
			so it's going to finish on day
nine.
		
00:09:10 --> 00:09:15
			Ad has a duration of 16 days, so
it's going to finish on day 16. I
		
00:09:23 --> 00:09:29
			now activity, the node B has the
date number four, so anything that
		
00:09:29 --> 00:09:33
			starts from B is going to be on
four. So we're going to put four
		
00:09:33 --> 00:09:33
			here
		
00:09:40 --> 00:09:42
			and four here as well.
		
00:09:49 --> 00:09:54
			Now activity be has a duration of
13 days, so it's going to end on
		
00:09:54 --> 00:09:55
			day 17. So.
		
00:10:01 --> 00:10:05
			The Activity BC is a dummy
activity, so the duration is four,
		
00:10:05 --> 00:10:07
			therefore it's going to end on day
four as well.
		
00:10:10 --> 00:10:10
			Centered.
		
00:10:13 --> 00:10:16
			Now at node C, we have two dates
coming we have four coming from
		
00:10:16 --> 00:10:21
			BC, and we have nine coming from
AC. As you remember from our
		
00:10:21 --> 00:10:24
			lecture, we're going to take the
larger number in the forward pass,
		
00:10:24 --> 00:10:25
			so we're going to put here nine
		
00:10:28 --> 00:10:28
			and nine.
		
00:10:39 --> 00:10:46
			Duration of CG is 14 days, so it's
going to end on day 23
		
00:10:52 --> 00:10:58
			and duration of CF is seven days,
so it's going to end on day 16.
		
00:11:02 --> 00:11:06
			Duration of d G is
		
00:11:07 --> 00:11:10
			eight days. It's going to start on
day 16,
		
00:11:14 --> 00:11:18
			and it's going to end on day 24 I
		
00:11:25 --> 00:11:29
			now at node G again, we have two
numbers. We have 23 and 24
		
00:11:29 --> 00:11:31
			therefore the number that's going
to proceed with us is going to be
		
00:11:31 --> 00:11:33
			the 24 the larger number.
		
00:11:45 --> 00:11:50
			GH has a duration of 12 days, so
it's going to end on day 36
		
00:12:02 --> 00:12:02
			and
		
00:12:04 --> 00:12:07
			as you can see, it's very simple
calculations. We can just you can
		
00:12:07 --> 00:12:10
			just finish the calculations for
this network. Let's just finish
		
00:12:10 --> 00:12:13
			the forward pass, and you can go
ahead and do the backward pass
		
00:12:13 --> 00:12:13
			yourself.
		
00:12:15 --> 00:12:17
			So here we're going to start with
17 i
		
00:12:24 --> 00:12:26
			and EI
		
00:12:27 --> 00:12:30
			is 16 days. So it's going to be 33
		
00:12:35 --> 00:12:37
			here. Also we have 17
		
00:12:41 --> 00:12:45
			and EF has a duration of nine
days. So it's going to be 26
		
00:12:49 --> 00:12:52
			so at node F, we have 16 and 26
we're going to take the 26
		
00:12:56 --> 00:13:00
			and F, J has a duration of 10
days. So here we're going to have
		
00:13:00 --> 00:13:01
			36
		
00:13:07 --> 00:13:09
			and then I we have here 33
		
00:13:14 --> 00:13:20
			and duration of ij is 13, so it's
going to be
		
00:13:21 --> 00:13:23
			46 40 6h.
		
00:13:31 --> 00:13:33
			J is going to start here on 36
		
00:13:41 --> 00:13:45
			and has a duration of 11 days. So
it's going to be 47
		
00:13:48 --> 00:13:53
			now we have three numbers going to
know, j we have 4636 and 47 the
		
00:13:53 --> 00:13:58
			largest number, of course, is 47
so that's going to be my end of
		
00:13:58 --> 00:14:03
			the project. The project started
on day zero and ended on day 47
		
00:14:04 --> 00:14:07
			as you can see, the calculations
are not that hard at all. They are
		
00:14:07 --> 00:14:10
			very straightforward and simple.
What we're going to do in the
		
00:14:10 --> 00:14:13
			backward pass, actually, is
reverse everything that we did in
		
00:14:13 --> 00:14:17
			the forward pass. Let me start the
backward pass and leave it for you
		
00:14:17 --> 00:14:21
			to finish. So let's start with the
first set of activities. Here,
		
00:14:21 --> 00:14:26
			we're going to start with 47 as
the late start, which is going to
		
00:14:26 --> 00:14:31
			be underneath the arrow 47 and
let's change the color of these to
		
00:14:31 --> 00:14:33
			be red, for example,
		
00:14:35 --> 00:14:40
			just to distinguish the forward
from the backward passes. So 47
		
00:14:40 --> 00:14:43
			the duration of HJ was
		
00:14:50 --> 00:14:52
			11 days. So it's going to be 36
		
00:14:53 --> 00:14:55
			now we're subtracting. Remember,
I.
		
00:15:00 --> 00:15:05
			Now you notice here that HJ has
4747 3636 so obviously this is
		
00:15:05 --> 00:15:09
			going to be a critical activity.
Right now, if you follow that,
		
00:15:09 --> 00:15:12
			you're going to find that the
critical path is going to be
		
00:15:12 --> 00:15:14
			basically that bottom path,
		
00:15:15 --> 00:15:19
			because this is going to be the
longest path, leading with giving
		
00:15:19 --> 00:15:24
			us the longest dates, the latest
dates. So it's going to be a, d,
		
00:15:24 --> 00:15:29
			g, h j, that's going to be our
critical path at the end. How did
		
00:15:29 --> 00:15:32
			I know that? Because it has to be
a continuous path. And since it
		
00:15:32 --> 00:15:38
			passes through h j, then it has to
be that one. Why didn't we say a C
		
00:15:38 --> 00:15:44
			and C G? Because again, the number
coming to G from D, which is 24 is
		
00:15:44 --> 00:15:47
			larger than the number coming from
C, which is 23 therefore the
		
00:15:47 --> 00:15:51
			critical activity is going to be
DG. But let's go ahead and do a
		
00:15:51 --> 00:15:54
			couple more activities with the
dates. So here we're going to
		
00:15:54 --> 00:15:56
			start with 47 as well, and
		
00:15:59 --> 00:16:00
			let's put
		
00:16:01 --> 00:16:02
			it here,
		
00:16:03 --> 00:16:07
			red 47 minus 10, that's going to
be 37
		
00:16:15 --> 00:16:20
			now notice this activity has how
many days of total float 47 minus
		
00:16:20 --> 00:16:26
			36 or 37 minus 26 which is 11 days
of total float going to activity,
		
00:16:27 --> 00:16:28
			i j, it's going to be again 47
		
00:16:33 --> 00:16:34
			minus.
		
00:16:35 --> 00:16:37
			This is i j
		
00:16:39 --> 00:16:42
			minus 13, so it's going to be 34
		
00:16:54 --> 00:16:57
			and you can just keep doing the
backward pass. This one is going
		
00:16:57 --> 00:17:01
			to have only one day of total
float. What we can also do at the
		
00:17:01 --> 00:17:05
			end, we can just change the color
of the nodes that are going to be
		
00:17:05 --> 00:17:06
			critical.
		
00:17:08 --> 00:17:11
			So we're going to make it
something like this,
		
00:17:14 --> 00:17:19
			just to show them in a different
color, so that they have a special
		
00:17:19 --> 00:17:21
			status as critical activities.
		
00:17:23 --> 00:17:27
			And we can also change the color
of these lines. We're going to
		
00:17:27 --> 00:17:29
			select this group of lines, 1234,
		
00:17:31 --> 00:17:36
			activities, and right click Format
objects. Change the color line
		
00:17:36 --> 00:17:40
			color. Let's make it red as
critical
		
00:17:42 --> 00:17:47
			and here's our critical path. That
was really simple, wasn't it? So
		
00:17:47 --> 00:17:52
			what you have to do is finish that
as a as a practice, try to finish
		
00:17:52 --> 00:17:58
			this network and see if you're
going to get the same numbers for
		
00:17:58 --> 00:18:03
			activities, GH, Bg and A, D, which
should be critical, and then
		
00:18:03 --> 00:18:09
			calculate the total float for the
other activities. That's basically
		
00:18:09 --> 00:18:10
			our exercise for today. So.